.
Maeda Corporation |
||||
|
||||
Expansion
of Shek Wu Hui Sewage Treatment
Works |
||||
|
Fourth Quarterly
EM&A Report (Sept 06 – Nov 06) December 2006 Report no: 01284R0332 |
|||
Hyder Consulting Ltd Incorporated in Hong Kong with limited liability—COI Number 126012 47th Floor, Hopewell Centre, 183 Queens Road East, Wanchai, Hong Kong Tel: +852
2911 2233 Fax: +852
2805 5028 www.hyderconsulting.com
|
||||
Maeda Corporation |
|||||||||
|
|||||||||
Expansion of Shek Wu Hui Sewage Treatment Works |
|||||||||
Fourth Quarterly EM&A Report (Sept 06 – Nov 06) |
|||||||||
Author: |
Gigi Ho |
|
|||||||
Checker: |
Sharifah Or |
|
|||||||
Approver: |
Guiyi Li |
|
|||||||
|
|||||||||
Report no: |
EA01284R0332 |
|
|
Date: |
December 2006 |
||||
Certified by Environmental Team Leader Sharifah
Or |
|||||||||
|
|||||||||
Contents
3.1 Project
and
Work Area, Environmental Sensitive Receivers and Monitoring Locations 4
5 Implementation Status of
Environmental Protection and Pollution Control/Mitigation Measures 8
7 Non-compliance, Complaints,
Notifications of Summons and Successful Prosecutions 8
7.4 Review of the Reasons and
Implications of Non-compliance, Complaints, Summons and Prosecutions 9
9 Comments, Recommendations and
Conclusions................................................ 13
List of Tables
Table 2-1 Key Personnel Contact Names and Telephone Number for the Project 2
Table 2-2 Status of Permit/Licence for the Project 3
Table 4-3 Event/ Action Plan for Air Quality Monitoring 5
Table 4-4 Event/ Action Plan for Noise Monitoring 6
Table 7-5 Summaries of Site Inspections
and Recommendations 8
Table 8-6 The Quantity of Waste Generation 9
List of Appendices
Appendix 1 Project
Organization
Appendix 2 Construction Programme
Appendix 4 Project
Area, Environmental Sensitive Receiver and Monitoring Location
Appendix 5 Action and Limit
Levels
Appendix 6 Environmental
Requirement and Implementation Status
Appendix 7 Monitoring Results and
Graphical Plots
Appendix 8 Cumulative Number
of Complaint, Notification of Summon and Successful Prosecution
The expansion of Shek Wu Hui Sewage Treatment
Works (SWHSTW) aims to increase the treatment capacity of the existing SWHSTW
to cope with the increasing wastewater flows and loads as a result of the
population growth in the catchment area of Fanling/Sheung Shui and the
committed extension of sewerage system to unsewered areas. It is considered as a project
constituting a material change to an exempted designated project under Schedule
2 of EIAO. Thus, the procedures under the EIAO have been followed and an
Environmental Monitoring and Audit (EM&A) Programme has to be carried
out. The present report documents the outcomes of the EM&A Works
undertaken between September and November 2006.
Breaches of
Action and Limit Levels
Noise
No
non-compliance of action/limit level was recorded at all monitoring stations
for noise during the reporting period.
1-hr TSP
No
non-compliance of action/limit level was recorded at all monitoring stations
for 1-hr TSP during the reporting period.
24-hr TSP
No non-compliance
of action/limit level was recorded at all monitoring stations for 24-hr TSP during the reporting period.
Complaints
Log
During this reporting period, no environmental complaint was received.
Notifications
of Any Summons and Successful Prosecutions
During the reporting period, no notification of summons or successful prosecution was recorded.
Reporting
Changes
There was no reporting change during the reporting period.
Future Key
Issues
The
construction activities for the coming three months will include excavation, pile head / cap
construction, sheet piling work, sub-structure and superstructure construction,
pipe works and internal/
external finishing.
Shek Wu Hui Sewage Treatment Works (SWHSTW)
provides treatment to the wastewater generated from Fanling/Sheung Shui areas
before discharge it into Mai Po Inner Deep Bay Ramsar Site through River Indus
and Shenzhen River, thus helps protecting the water quality of River Indus,
Shenzhen River and Mai Po Inner Deep Bay Ramsar Site. The expansion of SWHSTW aims to expand the treatment capacity of
the existing SWHSTW to cope with the increasing wastewater flows and loads as a
result of the population growth in the catchment area of Fanling/Sheung Shui
and the committed extension of sewerage system to unsewered areas.
In accordance with Section 9(2)(g) of the Environmental Impact Assessment Ordinance (EIAO), the SWHSTW is an exempted designated project as the existing SWHSTW has been in operation before the EIAO came into effect on 1 April 1998. However, since the proposed works involve physical expansion and alternation to the existing SWHSTW (hereafter called “the Project”) and may cause adverse environmental impacts if mitigation measures are not in place, it shall be considered as a project constituting a material change to an exempted designated project under Schedule 2 of EIAO. Hence the procedures under the EIAO have been followed. A Project Profile (PP) for direct application of the EP (Application No.DIR-121/2005) was approved by Environmental Protection Department (EPD) in May 2005 and an environmental permit (EP-218/2005) was obtained prior to the commencement of the expansion works.
Drainage Services Department (DSD) awarded the civil contract of
the expansion of SWHSTW to Maeda Corporation (Maeda) in September 2005. Maeda appointed Hyder Consulting Limited
(HCL) as the Contractor’s Environmental Team (ET) during
the construction period. CH2M HILL Hong
Kong Limited (formerly known as CH2M-IDC Hong Kong Limited) is the independent
environmental checker (IEC). The
construction contract commenced in September 2005 and the total construction
period is approximately 36
months. The notified commencement date
of work to the Director of EPD is 14 December 2005.
2.2 Management Structure and Project Organisation
The Engineer (DSD) is responsible for overseeing the construction works and ensuring that they are undertaken by the Contractor (Maeda) in accordance with the specification and contractual requirements. The Contractor shall report to the Engineer. The ET is employed by the Contractor and is responsible for conducting the EM&A programme. The IEC shall advise the Engineer on the environmental issues related to the Project.
The key personnel contact names and telephone number are summarised in Table 2-1. The project organisation is shown in Appendix 1.
Party |
Position |
Name |
Telephone number |
Project Proponent - DSD |
Project Manager |
Raymond Lee |
2594 7457 |
Engineer’s Representative |
Tim Tsoi |
2594 7460 |
|
Contractor - Maeda |
Site Agent |
George Cheung |
9268 1918 |
ET - Hyder |
ET Leader |
Sharifah Or |
2911 2730 |
IEC – CH2M HILL |
IEC |
David Yeung |
2872 2934 |
Table 2-1 Key Personnel Contact Names and Telephone Number for the Project
Construction programme of the Project is attached in Appendix 2.
2.4 Works Undertaken during the Reporting Quarter
Works
undertaken during the reporting period included:
§
excavation
§
cable
/ utilities diversion
§
sheet
piling work
§
installation
of wailings and struts
§
substructure
and superstructure construction
2.5 Status of Environmental Permit/ Licence
The status of the Environmental Permit/Licence for the Project is shown below.
Permit/Licence |
Application Date |
Date of issue |
Ref. No. |
Valid Until |
Environmental
Permit |
21
May 2005 |
16
June 2005 |
EP-218/2005 |
N/A |
Notification was made to EPD pursuant to Section 3(1) of
the Air Pollution Control (Construction Dust) Regulation (Form NA was submitted) |
22
Sep 2005 |
N/A |
N/A |
N/A |
Registration
as a chemical waste producer |
26
Sep 2005 |
4
Nov 2005 |
WPN:
5213-624-M2446-06 |
N/A |
Effluent
Discharge Licence |
11
Nov 2005 |
20
Dec 2005 |
Licence
No.: W5/1I287/1 |
19
Dec 2010 |
Application
for Exemption Account for Disposal of Construction Waste |
12
Dec 2005 |
Approved
by EPD on 31 Dec 2005 |
Application
No.: RN/00134 |
25
Sep 2008 |
Construction
Noise Permit |
15
May 2006 |
26
May 2006 |
Permit
No.: GW-RN0272-06 |
From
1 Jun 2006 to 30 Nov 2006 |
Construction
Noise Permit |
4
September 2006 |
18
September 2006 |
Permit
No.: GW-RN0469-06 |
From
18 Sep 2006 to 10 Oct 2006 |
Table 2-2 Status of Permit/Licence for the
Project
3.1 Project and Work Area, Environmental Sensitive Receivers and Monitoring Locations
The site is located at the existing Shek Wu Hui Sewage Treatment Plant, next to Chuk Wan Street. It has been subdivided into different Works Areas/Portions as illustrated in Appendix 3. Project area, environmental sensitive receivers and monitoring locations are shown in Appendix 4.
4.1.1 Air Quality
During the construction phase impact monitoring, 1-hour and 24-hour Total Suspended Particulates (TSP) levels should be measured at the selected air monitoring locations in accordance with the EM&A Manual. These two parameters are aimed to indicate the impacts of construction dust on air quality.
4.1.2 Noise
The construction noise level should be measured in terms of the A-weighted equivalent continuous sound pressure level (Leq) for 30 minutes. Leq(30 min) is used as the monitoring parameter for the period between 0700 and 1900 hours on normal weekdays. For all other time periods, three consecutive Leq(5min) are employed for comparison with the Noise Control Ordinance (NCO) criteria.
Other noise parameters such as L10 and L90 should also be obtained for reference.
4.2.1 Air Quality
The
baseline monitoring results documented in the Baseline Monitoring Report for
the Project (our report ref.: EA01284R0012) form the basis for derivation of
the Action and Limit Levels for air quality impact monitoring. Appendix 5 shows the derived Action and
Limit Levels for the Project. If the
air quality criteria are exceeded due to the Project, the Event/Action Plan
summarised in Table 4-3 should be triggered immediately.
4.2.2 Noise
The Action and Limit Levels for construction noise are defined in Appendix 5. If valid non-compliance of the criteria occurs, actions in accordance with the Event and Action Plan in Table 4-4 should be implemented. If construction works are undertaken during the restricted hours, a construction noise permit under NCO shall be obtained by the Contractor.
The Event and Action Plans for air quality and noise monitoring are shown in Tables 4-3 and 4-4, respectively.
EVENT |
ACTION |
|||
ET |
IEC |
ER |
CONTRACTOR |
|
ACTION LEVEL |
||||
Exceedance for
one sample |
·
Identify source, investigate the causes of exceedance and propose
remedial measures; ·
Inform IEC and ER; ·
Repeat measurement to confirm finding. |
·
Check monitoring data submitted by ET; ·
Check Contractor’s working method. |
·
Notify Contractor. |
·
Rectify any unacceptable practice; ·
Amend working methods if appropriate. |
Exceedance for
two or more consecutive samples |
·
Identify source, investigate the cause of exceedance and propose
remedial measures; ·
Inform IEC and ER; ·
Advise ER on the effectiveness of the proposed remedial measures; ·
Repeat measurements to confirm findings; ·
Increase monitoring frequency to daily; ·
Discuss with IEC and Contractor on remedial actions required; ·
If exceedance continues, arrange meeting with IEC and ER; ·
If exceedance stops, cease additional monitoring. |
·
Check monitoring data submitted by ET; ·
Check Contractor’s working method; ·
Discuss with ET and Contractor on possible remedial measures; ·
Advise the ET on the effectiveness of the proposed remedial measures; ·
Supervise Implementation of remedial measures. |
·
Confirm receipt of notification of exceedance in writing; ·
Notify Contractor; ·
Ensure remedial measures properly implemented. |
·
Submit proposals for remedial to ER within 3 working days of
notification; ·
Implement the agreed proposals; ·
Amend proposal if appropriate. |
LIMIT LEVEL |
||||
Exceedance for
one sample |
·
Identify source, investigate the causes of exceedance and propose
remedial measures; ·
Inform IEC, ER, Contractor and EPD; ·
Repeat measurement to confirm finding; ·
Increase monitoring frequency to daily; ·
Assess effectiveness of Contractor’s remedial actions and keep IEC,
EPD and ER informed of the results. ·
If exceedance stops, cease additional monitoring. |
·
Check monitoring data submitted by ET; ·
Check Contractor’s working method; ·
Discuss with ET and Contractor on possible remedial measures; ·
Advise ER on the effectiveness of the proposed remedial measures; ·
Supervise implementation of remedial measures. |
·
Confirm receipt of notification of exceedance in writing; ·
Notify Contractor; ·
Ensure remedial measures properly implemented. |
·
Take immediate action to avoid further exceedance; ·
Submit proposals for remedial actions to IEC within 3 working days of
notification; ·
Implement the agreed proposals; ·
Amend proposal if appropriate. |
Exceedance for
two or more consecutive samples |
·
Notify IEC, ER, Contractor and EPD; ·
Identify source, investigate the cause of exceedance and propose remedial
measures; ·
Repeat measurement to confirm findings; ·
Increase monitoring frequency to daily; ·
Carry out analysis of Contractor’s working procedures to determine
possible mitigation to be implemented; ·
Arrange meeting with IEC and ER to discuss the remedial actions to be
taken; ·
Assess effectiveness of Contractor’s remedial actions and keep IEC,
EPD and ER informed of the results; ·
If exceedance stops, cease additional monitoring. |
·
Discuss amongst ER, ET, and Contractor on the potential remedial
actions; ·
Review Contractor’s remedial actions whenever necessary to assure
their effectiveness and advise ER accordingly; ·
Supervise the implementation of remedial measures. |
·
Confirm receipt of notification of exceedance in writing; ·
Notify Contractor; ·
In consultation with the IEC, agree with the Contractor on the
remedial measures to be implemented; ·
Ensure remedial measures properly implemented; ·
If exceedance continues, consider what portion of the work is
responsible and instruct the Contractor to stop that portion of work until
the exceedance is abated. |
·
Take immediate action to avoid further exceedance; ·
Submit proposals for remedial actions to IEC within 3 working days of
notification; ·
Implement the agreed proposals; ·
Resubmit proposals if problem still not under control; ·
Stop the relevant portion of works as determined by ER until the
exceedance is abated. |
Table
4-3 Event/
Action Plan for Air Quality Monitoring
EVENT |
Action |
|||
ET |
IEC |
ER |
CONTRACTOR |
|
Action Level |
·
Notify IEC and ER; ·
Carry out investigation; ·
Report the results of investigation to the
IEC, ER and Contractors; ·
Discuss with the Contractor and formulate
remedial measures; ·
Increase monitoring requrency to check mitigation
effectiveness. |
·
Review the analysed results submitted by the
ET; ·
Review the proposed remedial measures by the
Contractor and advise the ER accordingly; ·
Supervise the implementation of remedial
measure. |
·
Confirm receipt of notification of failure in
writing; ·
Notify Contractor; ·
Require Contractor to propose remedial
measures for the analysed noise problem; ·
Ensure remedial measures are properly
implemented. |
·
Submit noise mitigation proposal to IEC; ·
Implement noise mitigation proposals. |
Limit Level |
·
Identify source; ·
Inform IEC, ER, EPD and Contractor; ·
Repeat measurements to confirm findings; ·
Increase monitoring frequency to check
mitigation effectiveness; ·
Carry out analysis of Contractor’s working
procedures to determine possible mitigation to be implemented; ·
Inform IEC, ER and EPD the causes and actions
taken for the exceedances; ·
Assess effectiveness of Contractor’s remedial
actions and keep IEC, EPD and ER informed of the results; ·
If exceedance stops, cease additional
monitoring. |
·
Discuss amongst ER, ET, and Contractor on the
potential remedial actions; ·
Review Contractors remedial actions whenever
necessary to assure their effectiveness and advise the ER accordingly; ·
Supervise the implementation of remedial
measures. |
·
Confirm receipt of notification of failure in
writing; ·
Notify Contractor; ·
Require Contractor to propose remedial
measures for the analysed noise problem; ·
Ensure remedial measures properly
implemented; ·
If exceedance continues, consider what
portion of the work is responsible and instruct the Contractor to stop that
portion of work until the exceedance is abated. |
·
Take immediate action to avoid further
exceedance; ·
Submit proposals for remedial actions to IEC
within 3 working days of notification; ·
Implement the agreed proposals; ·
Resubmit proposals if problem still not under
control; ·
Stop the relevant portion of works as
determined by th ER until the exceedance is abated. |
Table
4-4 Event/
Action Plan for Noise Monitoring
4.4 Environmental Mitigation Measures and Requirements
The recommended measures for mitigating air quality, water quality, noise, waste and all other possible environmental impacts due to the construction works have been stated clearly in the EM&A Manual. The details of the measures implemented by the Contractor are shown in Appendix 6.
The status of the mitigation measures implemented by the Contractor is listed in Appendix 6.
6.1 Graphical Plots of Monitoring Parameters
Graphical plots of the monitoring results are summarized in Appendix 7.
6.2
Factors Which Might Affect the Monitoring Results
Dust from other sources such as roads with the movement of heavy vehicles
in the vicinity of the monitoring stations would affect the air quality
monitoring results.
7.1
Non-compliance
of Action and Limit Levels
No non-compliance of Action or Limit Level was
recorded for air quality and noise monitoring.
7.2
Complaints Received
In case of an environmental complaint received, all related parties should follow the complaints response procedures specified in the EM&A Manual.
During this reporting quarter, no environmental complaint was received. Cumulative number of environmental complaint is shown in Appendix 8.
7.3
Notifications of Summons and Successful Prosecutions
No notification of summons or
successful prosecution was recorded during the
reporting period. The cumulative
number of notifications of
summons and successful prosecutions are shown in Appendix 8.
7.4 Review of the Reasons and Implications of Non-compliance, Complaints, Summons and Prosecutions
7.4.1
Non-compliance
of Acton/Limit Level
No valid exceedance of Action/Limit Level was recorded during the reporting period.
7.4.2 Complaints, Summons and Prosecutions
No complaints, summons and prosecutions were recorded during the reporting period.
Weekly site inspections have been carried out during the reporting period. The findings of the site inspections and appropriate mitigation measures were recorded in the site inspection checklists. The observations raised during the site inspections, corresponding recommendations and rectification status are summarised in Table 7-5.
Table 7-5 Summaries of Site Inspections and Recommendations
EPD conducted site visit on 25 September
2006 and 29 November 2006 during the reporting period. EPD inspected the effluent discharge at all
areas and chemical waste storage area and checked whether Environmental Permit
and Construction Noise Permit were displayed at site entrance on 25 September
2006. EPD had no adverse comment.
EPD inspected
the effluent discharge, chemical waste storage area, wheel washing facility and
dust control measure on 29 November 2006.
No adverse comment was given.
According to the information provided by the
Contractor, Table 8-5 shows waste materials were generated during the reporting
period.
Type of Waste |
Sept 06 |
Oct 06 |
Nov 06 |
Inert C&D material (m3) |
3495 |
2360 |
3567 |
General Refuse (m3) |
65 |
65 |
32.5 |
Chemical waste (L) |
0 |
0 |
0 |
Table 8-6 The
Quantity of Waste Generation
Inert C&D materials were disposed of at Tuen Mun Area 38 Public Fill. General refuse was collected and disposed of at NENT Landfill. No chemical waste was produced during the reporting period. Trip ticket system was implemented and disposal records were in order on site. The Waste Management Plan was followed.
EM&A works have been undertaken between September and November 2006 for the Project based on the requirements set in the EM&A Manual.
All monitoring equipments have been calibrated and all monitoring protocols have been carried out properly according to the EM&A Manual.
No valid exceedance of Action/Limit Level on air quality and noise was recorded during the reporting period.
No
compliant, notification of summons or successful prosecution was recorded
during the reporting period.
The overall
EM&A programme is considered efficient during the reporting period and no
material and technical changes are considered necessary.
Appendix 1 |
Project Organization |
Appendix 2 |
Construction Programme |
Appendix 3 |
Works Area |
Appendix 4 |
Project Area, Environmental Sensitive Receiver and Monitoring Location |
Appendix 5 |
Action and Limit Levels |
Appendix 6 |
Environmental Requirements and Implementation Status |
Appendix 7 |
Monitoring Results and Graphical Plots |
Appendix 8 |
Cumulative Statistics of Complaint, Notification of Summons and
Successful Prosecution |