TABLE OF CONTENTS

EXECUTIVE SUMMARY

Breaches of Reference Criteria and Action Level

Key Issues and Findings

Reporting Change

1.         INTRODUCTION

Background

Environmental Status

Implementation Status

2.         BRIDGE RUNOFF MONITORING

Monitoring Requirements

Monitoring Equipment

Monitoring Parameters, Frequency and Duration

Monitoring Locations

Monitoring Methodology

QA/QC Procedure and Detection Limits

Results and Observations

Other Factors Affecting the Monitoring Results

Actions Taken in the Event of Exceedance

Review of Effectiveness of Road Cleaning Frequency

Review of Monitoring Methodology and Reference Criteria

3.         CONCLUSIONS

 

List of Tables and Graphs

 

Table 2.1           Road Surface Runoff from Carriageway Monitoring Equipment

Table 2.2           Locations of Road Surface Runoff Monitoring

Table 2.3           Detection Limit for Monitoring Parameters

 

List of Figures

 

Figure 1.1        Layout of Work Site

Figure 2.1        Road Surface Runoff from Carriageway Monitoring Locations

 

 

List of Appendices

 

Appendix A        Shenzhen Bay Crossing Vehicular Traffic (July 2007 to August 2008)

Appendix B       Action Levels and Event Action Plans

Appendix C       QA / QC results

Appendix D       Extract of Meteorological Observations for Lau Fau Shan Automatic Weather Station (January to March 2008)

Appendix E       Road Surface Runoff Calculations from Carriageway Monitoring Results and Graphical Presentations

 

 


EXECUTIVE SUMMARY

 

This is the second Review Report for Bridge Surface Runoff from Carriageway Monitoring prepared by ENSR Asia (HK) Ltd. (ENSR), the designated Environmental Team (ET), for the operational phase of the Project “Hong Kong-Shenzhen Western Corridor”. Operation of the Project commenced on 1 July 2007. This report presents the results and findings of the bridge runoff monitoring work during the second monitoring period (January to March 2008).

 

Monitoring of surface runoff from the carriageway was required to be carried out on 6 occasions in the first three months and another 6 occasions in months 7 to 9 after the operation of the HK-SWC bridge. The monitoring of the first monitoring period has been postponed due to the time required for obtaining relevant permits and licences before working on the expressway. The monitoring events commenced in September 2007.

Breaches of Reference Criteria and Action Level

There were a total of 6 monitoring of bridge surface runoff from carriageway carried out in the reporting period to fulfill the requirement stipulated in the Environmental Permits (EP-162/2003/B and EP-290/2007) and EM&A Manuals.

 

Elevated Event Mean Concentration (EMC) of nitrite and nitrate was recorded on 19 January 2008.  No 3 consecutive monitoring results of nitrite and nitrate exceeded the reference criteria and hence, no action level exceedance was triggered.  The elevated EMC of a parameter in one single event was considered unlikely due to inadequate road cleaning along HK-SWC.

 

No action level exceedance was recorded in the reporting period.

 

Key Issues and Findings

Key issue to be considered during the operation of the HK-SWC includes:

 

·           Sufficient cleaning of the carriageway to be carried out by vacuum air sweeper(s) to remove grits and pollutants.

 

Reporting Change

Further to the comments provided by EPD, further revision of the review report is required to elaborate the monitoring results.

 

The monthly summary of vehicular traffic using the HK-SWC between July 2007 and August 2008 were available during the report preparation and is included in Appendix A and information was updated in Section 1. Weather information of March 2008 is also available and is enclosed in Appendix D.


 

1.       INTRODUCTION

Background

1.1               ENSR Asia (HK) Ltd. (ENSR) (hereinafter called the “ET”) was appointed by Highways Department (hereinafter called the “Client”) to undertake Environmental Monitoring and Audit for “Hong Kong-Shenzhen Western Corridor” (hereinafter called the “Project”) during operational phase. Under the requirements of Section 6.4 of Environmental Permit EP-162/2003/B, Section 3.2 of the Environmental Permit EP-290/2007 and relevant sections of the EM&A Manuals, bridge runoff monitoring was required to be carried out on 6 occasions in the first three months and another 6 occasions in months 7 to 9 after commencing the operation of the HK-SWC bridge.

1.2               Operation for the Project commenced on 1 July 2007. Commencement of the first monitoring period for bridge runoff monitoring was postponed to September 2007 due to the time required for obtaining relevant permits and licences before working on the expressway. This report summarises the results and findings of the bridge runoff monitoring work during the second monitoring period (January to March 2008).

1.3               Due to safety concern and limitation on working on the bridge deck of HK-SWC, an alternative method was approved by EPD. Detailed information is provided in Section 2 of this report.

1.4               Further to the comments provided by EPD on the report, revision of the review report is required to elaborate the monitoring results.

Environmental Status

1.1               The Hong Kong – Shenzhen Western Corridor came into operation since 1 July 2007. According to the statistics of the vehicular traffic using the HK-SWC from the “Transport Monthly Digest” issued by Transport Department, the average daily vehicles (two-way) using the HK-SWC increased from 1,292 nos. in July 2007 to 5,407 nos. in March 2008. The monthly summary of vehicular traffic using the HK-SWC abstracted from the Transport Department’s “Transport Monthly Digest” is provided in Appendix A.

1.2               As stipulated in the EPs and the EM&A Manuals, the HK-SWC bridge deck is required to be cleaned by vacuum air sweeper(s) twice a week to remove grits and pollutants. The layout of the Project site is provided in Figure 1.1.

Implementation Status

1.3               It was required by the EPs and EM&A Manuals that the carriageway should be cleaned twice a week by vacuum air sweeper(s) to remove grits and pollutants.

1.4               Since the commencement of operation of HK-SWC, the cleaning and maintenance work was carried out by the maintenance contractor.

1.5               During the operation of the HK-SWC in the reporting period, vacuum air sweeper was used for road cleaning on the bridge deck and the cleaning events were carried out at least once every two days along the hard-shoulder and left-lane of both bounds, which was already higher than the frequency recommended in the EPs and the EM&A Manuals. Gullies along HK-SWC were cleaned and stagnant water inside the gullies was removed once every 6 months.

 


2.        BRIDGE RUNOFF MONITORING

Monitoring Requirements

2.1               The monitoring is to determine the characteristics of bridge runoff in particular the first flush from the HK-SWC bridge during rain-storm events and to review the frequency of road cleaning.

2.2               The original method on road surface runoff monitoring involves installation of equipments onto the bridge deck or the parapets on both sides of the expressway. After reviewing by relevant government departments, including the Hong Kong Police Force and Fire Services Department, the installation of equipment was considered causing disturbance to other road users including the fire services and police vehicles during emergency operation and considered relatively unsafe for the ET staff working on the expressway.

2.3               A procedural guide detailing the methodology of using a water tanker to simulate an artificial rainfall by spraying water onto the catchment area of the monitoring gully during bridge closure at night was prepared. The guide was vetted by the IEC and the Engineer and was reviewed by EPD.

2.4               The proposed criteria, action level and actions required are included in Appendix B.

Monitoring Equipment

2.5               A portable automatic sampler of non-contact type, equipped with a suction pipe, was used for sampling. The pump flow rate is adjustable. Table 2.1 summarises the equipment used.

 

Table 2.1      Road Surface Runoff from Carriageway Monitoring Equipment

 

Equipment

Model

Variable Speed Sampler (with pump head)

Masterflex Model 7571

Pump Head

Masterflex Model 7518

Monitoring Parameters, Frequency and Duration

2.6               Monitoring should include in total 12 sampling / rainstorm events (12 sets of data) and cover the dry season period. A total of 6 sets of sampling data should be collected during the first 3 months after the opening of the HK-SWC bridge. The other 6 sets of sampling data should be collected in month 7 to month 9 after opening of the HK-SWC Bridge. The minimum interval between two sampling events shall not be less than 4 days.

2.7               The commencement of the road surface runoff monitoring programme was postponed to September 2007 due to time required for obtaining consent and relevant permits and licenses from relevant government departments for working on the bridge deck. The first monitoring period of road surface runoff from carriageway was from 27 September 2007 to 10 November 2007, while the second monitoring period was from 5 January 2008 to 1 March 2008.

 

 

 

 

 

2.8               All samples were cooled to 4°C without being frozen and delivered to a HOKLAS laboratory within 24 hours for analysis for the following pollutants in highway runoff:

ŸTotal Suspended Solids

ŸTotal Organic Carbon

ŸChemical Oxygen Demand

ŸNitrite and Nitrate

ŸTotal Kjeldahl Nitrogen

ŸTotal Phosphorus

ŸCopper

ŸLead

ŸZinc

Monitoring Locations

2.9               In each monitoring event, water samples were collected from six different road gullies, three on each side of the carriageways.

2.10           The exact monitoring locations were recorded in terms of nearby lighting pole / highways chainage. The exact monitoring locations are shown in Figure 2.1 and are listed in Table 2.2 below.

 

Table 2.2  Locations of Road Surface Runoff Monitoring

 

Date

Shenzhen bound

Hong Kong bound

5 January 2008

Lighting Pole BD3720

Lighting Pole BD4568

Lighting Pole BD3701

Lighting Pole BD3614

Lighting Pole BD4626

Lighting Pole BD3652

12 January 2008

Lighting Pole BD3764

Lighting Pole BD4553

Lighting Pole BD3742

(Chainage 3.0N)

Lighting Pole BD3615

(Under the speed sign)

Lighting Pole BD4638

(Under the speed sign)

Lighting Pole BD3645

(Under the speed sign)

19 January 2008

Lighting Pole BD3748

(Under the speed sign)

Lighting Pole BD4562

Lighting Pole BD3713

(Chainage 2.0N)

Lighting Pole BD3610

(Chainage 2.0S)

Lighting Pole BD4634

Lighting Pole BD3639

(Chainage 3.0S)

16 February 2008

Lighting Pole BD3742

Lighting Pole BD4568

Lighting Pole BD3721

Lighting Pole BD2650

Lighting Pole BD4647

Lighting Pole BD3624

23 February 2008

Lighting Pole BD3748

Lighting Pole BD4574

Lighting Pole BD3728

Lighting Pole BD3610

Lighting Pole BD4642

Lighting Pole BD3627

1 March 2008

Lighting Pole BD3771

(Chainage 4.0N)

Lighting Pole BD4555

 

Lighting Pole BD3731

 

Lighting Pole BD3615

(Under the Speed Sign)

Lighting Pole BD4640

Lighting Pole BD3654

Monitoring Methodology

2.11           A water tanker with sprinklers was deployed to spray water on the road surface around the catchment area of the monitoring gully. It simulated an artificial rain and provided a washing effect on the road surface under rainstorm event.

 

2.12           At each monitoring location, the water tanker stopped on the left lane near the monitoring gully and spray water over the catchment area. The water would wash the whole area and drain into the monitoring gully. The position of the tanker and spraying angle of the sprinkler were adjusted to achieve the best washing effect.

2.13           A portable automatic sampler was used for sampling. The suction tube inlet was placed at the mid level of the sedimentation pond inside the monitoring gully. The sampling works was started once bridge runoff discharge was observed from the gully to the connected down pipe.

2.14           Each water sample collected was of 1L in volume and 24 individual samples were collected in each monitoring event. Four composite samples, each of 6L, were prepared from the 24 individual water samples for laboratory analysis. The first composite sample was a mix of the first water sample collected from each monitoring gully. Similar preparation procedure applied to the remaining three composite samples.

2.15           Upon mixing, the composite samples were filled into suitable containers (preserved / non-preserved) based on the testing parameters before delivery.

2.16           An additional composite sample was prepared by mixing the samples taken from the water tanker before and after the monitoring. This sample was collected to understand the quality of spraying water and for reference purpose. The concentration of pollutant of the reference sample was subtracted from the raw monitoring data to derive the increment, which was then compared against the reference criteria.

2.17           The samples were cooled to 4°C without being frozen. The samples were delivered to the ALS Techichem (HK) Pty Ltd., a HOKLAS laboratory, within 24 hours for analysis.

QA/QC Procedure and Detection Limits

2.18           ALS Technichem Pty. Ltd. followed comprehensive quality assurance and quality control programmes. For QA/QC procedures, at least one duplicate sample was analysed for every batch of 20 samples as required by HOKLAS. The QA/QC results are summarised in Appendix C.

2.19           The detection limits for the monitoring parameters are listed in Table 2.3.

 

Table 2.3  Detection Limit for Monitoring Parameters

 

Parameter

Recommended Method

Detection Limit (mg/L)

Total suspended solids

APHA 2540D

2

Total organic carbon

APHA 5310 B

1

Chemical oxygen demand

APHA 5220 C&D

2

Nitrate

APHA 4500-NO3-

0.01

Nitrite

APHA 4500-NO2-

0.01

Total Kjeidahl Nitrogen

ASTM D3590-89B

0.1

Total phosphorus

ASTM D515-88B

0.1

Copper

APHA 3120B

0.001

Lead

APHA 3120B

0.01

Zinc

APHA 3120B

0.01

Results and Observations

2.20           There were six monitorings of road surface runoff from carriageway carried out in the reporting period. All monitorings were carried out under fine weather condition. Meteorological Data, including daily total rainfall, were obtained from the Hong Kong Observatory on-site wind station at Lau Fau Shan. All weather data extracted from Lau Fau Shan weather station for January, February and March 2008 are annexed in Appendix D.

2.21           The average flow rate of water spraying by the water tanker was about 4.0 L/s.  Collection of each of the 1L sample was completed within 2 – 3 minutes.

2.22           In order to determine the pollutant concentration due to bridge runoff water only, the concentration of pollutant of the reference sample was subtracted from the raw monitoring data to derive the increment due only to bridge runoff.  The concentration of pollutant of the reference sample was assigned to be zero when its concentration is below the detection limit.

2.23           Event Mean Concentrations (EMCs) was calculated from the monitoring results, i.e. locally generated EMC values for specific pollutant in the particular site in concern, Shenzhen Western Corridor, were worked out. The EMCs values of the monitoring results are then compared with the reference criterion.  EMC is commonly used for stormwater runoff monitoring. EMC has been adopted in studies for evaluation of characteristics of highway runoff and government reports in different countries such as USA, Toronto, Malaysia and Korea.   EMC was also presented in Urban Stormwater Management Manual for Malaysisa.  The same analytical technique was used by Driscoll and by Barrett in Table EM4.6 of EM&A Manual. 

2.24           The EMC for a pollutant was derived from the average concentration for each of the events monitored.  Pollutants that were present in the samples at concentrations at concentrations below the detection limit were assigned the value of the detection limit when event mean concentrations (EMC) were calculated.  Therefore, the EMC of a pollutant that is present in amounts below the detection limit is reported as greater than the actual concentrations in the sample. 

2.25           The calculation of all monitoring results and graphical presentation are provided in Appendix E.

Total Suspended Solids (TSS)

2.26           TSS is the key element in measuring the road surface runoff monitoring since a high TSS level does not only imply high concentration of particles, but also cause high concentration of other pollutants, including heavy metals, nutrients, which would be adsorbed onto the surface of the particles.

2.27           The TSS levels in six monitorings were generally low. The highest EMC of TSS was 19 mg/L and the lowest concentration was 5 mg/L.

2.28           There was no exceedance of EMC of TSS recorded in the second monitoring period.

Nitrate and Nitrite (NO3-+NO2-)

2.29           Nitrate and Nitrite are two of the nutrients for aquatic life. Nitrite ion itself is relatively unstable and is a transition stage ion to nitrate ion, which is a more stable form. Nitrite, to aquatic life, is more toxic than nitrate.

2.30           It was recorded that high nitrite and nitrate concentration was found in the reference sample taken from the water tanker, ranging from 1.32 – 1.80 mg/L,  The magnitude is relatively high in comparison with other parameters.    

2.31           Only one EMC of Nitrite & Nitrate on 19 January 2008 was over the reference criterion in the second monitoring period.  No 3 consecutive monitoring results of nitrite and nitrate exceeding the reference criteria.  No Action Level was triggered.  

        Total Kjeldahl Nitrogen (TKN)

2.32           The Total Kjeldahl Nitrogen is the sum of ammonia, ammonium and total organic nitrogen. Since organic nitrogen, ammonia and ammonium undergo nitrification to form nitrite or nitrate, the nitrification process would consume oxygen. High concentration of TKN would cause depletion in oxygen and thus causes impact to the aquatic system.

2.33           The TKN concentrations in all the samples were low. The highest EMC of TKN measured was 0.9 mg/L.

2.34           All EMCs of TKN monitoring results complied with the reference criterion.

        Total Phosphorus (TP)

2.35           Phosphorus is one of the major nutrients for the aquatic life. Since phosphorus is usually the limiting nutrients in the aquatic system, excess phosphorus input to the aquatic environment could lead to eutrophication and trigger algal bloom.

2.36           The total phosphorus concentration of all monitoring samples were below detection limit (i.e. <0.1 mg/L). There was no exceedance in total phosphorus recorded in the second monitoring period.

        Total Organic Carbon (TOC)

2.37           The TOC concentration measures all the carbon content in organic form. The input of the organic carbon into the water body may be considered as an addition of nutrients, since the organic carbon could be decomposed and reused in the aquatic environment.

2.38           The highest EMC of TOC calculated was 17 mg/L.

2.39           All EMCs of TOC monitoring results complied with the reference criterion.

        Chemical Oxygen Demand (COD)

2.40           Chemical oxygen demand measures the concentration of oxidizable chemicals, usually used as a measurement of organic compound in water.

2.41           All EMCs of COD were below the reference criterion. The highest EMC of COD calculated was 44mg/L.

        Copper (Cu), Lead (Pb) and Zinc (Zn)

2.42           Copper, lead and zinc are heavy metals, which are the most commonly found pollutants in highways runoff. These heavy metals are usually combined / associated with sediment particles and are considered to have a direct impact to aquatic life at a high concentration.

2.43           Copper deposited onto the carriageway could be generated from the brake pads / other metallic parts of the vehicles, while zinc could be deposited from tyres of vehicles. Lead could come from fuels of trucks and is considered to be one of the most toxic / acute pollutants in water.

2.44           The concentrations of copper, lead and zinc were generally low throughout the reporting period.

2.45           The concentrations of lead in most of the monitoring samples were below detection limit (i.e. <0.01 mg/L), while the maximum concentration was 0.02 mg/L. The low concentration could be due to the restriction of use of leaded petrol / fuel in vehicles.

2.46           The EMCs of copper, lead and zinc in all samples were within the reference criteria.

Other Factors Affecting the Monitoring Results

2.47           The stagnant water inside the gullies that contains certain amount of pollutants would affect the monitoring results.  The samples were collected from the gullies, therefore, the samples collected was not only due to surface runoff in Shenzhen Western Corridor, but also include pollutants that already existed in stagnant water inside gullies .

2.48           Meteorological factors like air quality might be influential to pollutant concentrations in runoff.  Spraying water from water tanker has the potential to entrain airborne pollutants, especially nitrogen and phosphorous. 

 

Actions Taken in the Event of Exceedance

2.49           No action level exceedance was recorded.

Review of Effectiveness of Road Cleaning Frequency

2.50           For assessing the effectiveness of road cleaning frequency, the bridge runoff monitoring data, the cleaning work carried out by the maintenance Contractor employed by the Client and site observations were reviewed.

2.51           In the reporting period, one elevated EMC of nitrite and nitrate was recorded on 19 January 2008.  Other than that, no elevation of other parameters was recorded.

2.52           It was recommended in the EPs and EM&A manuals, the cleaning frequency shall be twice a week with any consecutive cleaning events not separated by more than four days. The cleaning frequency of the carriageway of the Project by the maintenance Contractor was higher than the minimum cleaning frequency as stated in the EPs and EM&A Manuals. In the reporting period, the carriageway was cleaned at least once every two days along the hard-shoulder and left-lane of both bounds by a suction road sweeper.

2.53           No action level exceedance was recorded.  Thus, the current road cleaning practices and frequency was considered effective and sufficient.

Review of Monitoring Methodology and Reference Criteria

2.54           After reviewing the monitoring method stated in the EM&A manual, it is not guaranteed that sufficient rainfall events would happen within the monitoring months and due to the safety concern on working on the bridge deck, an alternative methodology, which includes using a water tanker to simulate an artificial rainfall, for bridge runoff monitoring was adopted.

2.55           Since the bridge runoff monitoring at HK-SWC was the first bridge runoff monitoring established in Hong Kong and there was no background information and data available before the first monitoring period, no review of the reference criteria was carried out.

2.56           Since Deep Bay is an area of ecological importance, particularly to shorebirds, any input of pollutants to the Deep Bay water should be minimized. The most concerned pollutants would be heavy metals. The EMCs of heavy metals (copper, lead and zinc) were low and were well below the reference criteria. Impacts from heavy metals in road runoff water are considered small. Besides heavy metals, input of nutrients, including organic carbon, nitrogen-containing chemicals and phosphorus-containing chemicals, would be another concern, since these nutrients can lead to extensive growth of algae in the Deep Bay. Yet, the concentrations of these pollutants are low, the impact to the Deep Bay environment is considered small.

2.57           The Deep Bay catchment area is about 535km2, which is much larger as compared to the surface area of the bridge deck. As the concentration of pollutants are low and the volume of runoff from the bridge deck is small (due to the relatively small surface area), the impact to water quality and ecology was considered insignificant.

2.58           It was recommended that samples should be collected from storm drain inlet of the gutter, i.e. before runoff entering into gullies, to prevent the monitoring data affecting by the stagnant water inside the gullies which contain certain amount of pollutants.  Referring to the methodology in study by Barrett, the runoff samples were collected from a single storm-drain inlet located along the gutter of a curbed section of the highway.

2.59           Use of EMC is a general and appropriate method to evaluate the effects of storm water runoff on receiving waters.  Obtaining local event mean concentration for the area of concern was suggested to have accurate estimation, determination of reference criteria and monitoring programme as well.   Whereas obtaining local event mean concentration is not feasible, applying literature event mean concentration could be used as a guideline.

 

3.        CONCLUSIONS

 

3.1               Six bridge surface runoff from carriageway monitoring events were carried out in January to March 2008. All monitoring results in the reporting period were checked and reviewed.

3.2               All monitoring results complied with the reference criteria except one EMC of nitrite and nitrate is over the reference criterion occurred on 19 January 2008. 

3.3               No 3 consecutive monitoring with the same parameter (1 or more than 1 parameter) exceeded the reference criteria.  No Action Level was triggered.

3.4               The current cleaning frequency and method of the bridge deck was considered sufficient and effective.