Contents

Executive Summary                                                                                     

1                      introduction                                                                          

1.1                   Background                                                                           

1.2                   Purpose of the Report                                                     

1.3                   Structure of the Report                                                

2                      Cable Installation Water quality monitoring     

2.1                   Monitoring Locations                                                        

2.2                   Monitoring Parameters and Frequency                 

2.3                   Monitoring Equipment and Methodology               

2.4                   Baseline Monitoring Results                                        

3                      Conclusion                                                                              

 

LIST OF ANNEXES

Annex A

Baseline Monitoring Schedule

Annex B

Calibration Reports of Multi-parameter Sensor

Annex C

QA/QC Results for Suspended Solids Testing

Annex D

Baseline Water Quality Monitoring Results

 

LIST OF ANNEXES

Figure 1.1

The Route of the Proposed Cable System

Figure 1.2

Location of Water Quality Monitoring Stations

Figure 2.1

Water Quality Monitoring Stations (Zones B to D)

 

EXECUTIVE SUMMARY

ERM-Hong Kong, Limited (ERM) was appointed by Tata Communications (Bermuda) Ltd to undertake baseline water quality monitoring (ie for cable installation) prior to the commencement of construction works for VSNL Intra Asia Submarine Cable System – Deep Water Bay (Application No. DIR-155/2007).   

This Baseline Monitoring Report has been prepared in compliance with the Further Environmental Permit (FEP-01/294/2007) and Environmental Monitoring and Audit Manual for VSNL Intra Asia Submarine Cable System – Deep Water Bay (the ‘Project’).

Baseline water quality monitoring (ie for cable installation) was conducted between 27 February and 13 March 2009 at six designated monitoring stations near Po Toi Island (ie Zones B to D) established for the Project.  The monitoring was carried out 3 days per week, at mid-flood and mid-ebb tides, at three depths (surface, middle and bottom), for 2 weeks prior to the commencement of construction works.  No major activities were undertaken during baseline monitoring.  Water quality monitoring results are, therefore, representative of the baseline conditions for the Project.

 


1                                            introduction

1.1                                      Background

Tata Communications (Bermuda) Ltd (formerly Videsh Sanchar Nigam Limited (VSNL)) proposes to install a submarine telecommunications cable, which will run from Deep Water Bay and through southeast Hong Kong offshore waters.  The cable landing site will be at the western edge of Deep Water Bay beach at an existing cable landing manhole location.  From Deep Water Bay, the cable will extend southwards towards the East Lamma Channel.  Near to Round Island, the cable will turn approximately parallel to the East Lamma Channel passing to the south of Po Toi island.  The cable will then run eastward close to the boundary of HKSAR waters and then out beyond Hong Kong territorial waters into the South China Sea.  At the southeast offshore waters, it will be necessary to install a grout mattress to protect the cable where it crosses Hongkong Electric Co., Ltd’s (HKE) gas pipeline.  A map of the proposed cable route is presented in Figure 1.1.

In August 2007, a Project Profile (PP) for the Project included an assessment of the potential environmental impacts associated with the installation of the submarine cable circuit was prepared and submitted to the Environmental Protection Department (EPD) under section 5.(1)(b) and 5.(11) of the Environmental Impact Assessment Ordinance (EIAO) for application for Permission to apply directly for Environmental Permit (EP).  The Environmental Protection Department, subsequently issued an Environmental Permit (EP-294/2007) and Further Environmental Permit (FEP-01/294/2007).  Amendments to the permitting requirements were incorporated into Environmental Permit to address potential environmental impacts associated with cable crossings over the HKE’s gas pipeline in southeast Hong Kong waters.  Under the requirements of Condition 3 of the EP, an EM&A programme as set out in the Environmental Monitoring and Audit Manual (EM&A Manual) is required to be implemented.  In accordance with the EM&A Manual, baseline monitoring of water quality is required for the Project.

ERM-Hong Kong, Limited (ERM) was appointed by Tata Communications (Bermuda) Limited as the Monitoring Team (MT) to implement the part of the EM&A programme (ie Cable Installation Water Quality Monitoring and Site Inspection) for the Project.

Given that the water sampling stations in Zones A and E (Deep Water Bay) are situated quite far away from those in Zones B to D (Po Toi) and the expected different water quality characterises, we recommended to present the baseline data in two separate reports (ie Part A for Deep Water Bay and Part B for Po Toi) and the corresponding Action and Limit Levels would be derived from the baseline data for each side (ie Deep Water Bay, Po Toi).  Due to rough sea conditions and foggy weather, the baseline water quality monitoring survey scheduled on 1 March 2009 for the Po Toi side was cancelled due to safety concerns.  As such, the baseline monitoring for the Po Toi section of works was delayed and an additional baseline monitoring survey was undertaken on 13 March 2009.  The results of the data obtained from monitoring stations near Deep Water Bay (ie Monitoring Zones A and E) were presented in the Baseline Water Quality Monitoring Report Part A which was submitted to EPD on 11 March 2009 (Figure 1.2).  This report (ie Baseline Water Quality Monitoring Report Part B), therefore, only presents results of the monitoring data for Zones B to D near Po Toi Island.

1.2                                      Purpose of the Report

The purpose of this Baseline Water Quality Monitoring Report Part B is to determine the baseline marine water quality at the designated monitoring locations near Po Toi Island (ie Monitoring Zones B to D) prior to the commencement of the works of jetting machine operation.  These levels will be used as the basis for assessing environmental impact and compliance monitoring during the construction (jetting machine operation) of the Project.  This report presents the monitoring requirements, methodologies and results of the baseline ambient marine water quality measurements at the monitoring locations in accordance with the EM&A Manual.   

1.3                                      Structure of the Report

The structure of the report is as follows:

Section 1 :  Introduction

Details the background, purpose and structure of the report.

 

Section 2 :  Water Quality Monitoring

Summarises the water quality monitoring parameters, monitoring programmes, monitoring methodologies, monitoring frequency, monitoring locations, monitoring results and establishes the Action and Limit Levels in accordance with the EM&A Manual.

 

Section 3 :  Conclusions

Concludes the representativeness of the baseline monitoring results and observations for the Project.

 

2                                            Cable Installation Water quality monitoring

The following Section provides details of the baseline monitoring of water quality prior to the installation of the submarine cable.

2.1                                      Monitoring Locations

In accordance with the EM&A Manual, prior to the installation of the cable, water quality sampling was undertaken at monitoring stations near Po Toi Island (ie Zones B to D).  The locations of the sampling stations are shown in Figure 2.1. 

·           C1, C2 and C3 are located approximately 600 m north of the cable alignment at Po Toi for monitoring the effect of cable laying works on coral communities in the area;

·           F1 is used to monitor the effect of the cable installation works on the Po Toi Fish Culture Zone (FCZ); and

·           R2 and R3 are Control Stations for C1, C2, C3 and F1 at Po Toi which are not supposed to be influenced by the cable laying works due to their remoteness to the construction works.

The suggested co-ordinates of Zones B to D as well as the above monitoring stations are listed in Table 2.1 and Table 2.2, respectively.

Table 2.1        Co-ordinates of Starting Points and Ending Points for Zones B to D (HK Grid)

Zone

Starting Point

Ending Point

 

Easting

Northing

Easting

Northing

B

841917.597

802680.115

844161.823

801308.268

C

844161.823

801308.268

845555.155

801495.491

D

845555.155

801495.491

846970.152

801749.210

 

Table 2.2        Co-ordinates of Baseline Monitoring Stations (HK Grid)

Station

Nature         

Corresponding Control Station

Easting

Northing

C1

Coral Colonies

R2, R3

843547.181

802010.004

C2 (a)

Coral Colonies

R2, R3

844800

801840

C3

Coral Colonies

R2, R3

846179.538

802224.554

F1 (b)

Fish Culture Zone

R2, R3

843920

802730

R2

Control Station

-

842074.745

803375.183

R3 (c)

Control Station

-

846444

804982

Notes:

(a)        The original location of C2 was situated very close to the shore.  C2 is therefore moved 80 m seaward from the original location due to safety reasons and the new location is considered representative.

(b)        The original location of F1 was situated very close to the shore.  F1 is therefore moved 40 m

      seaward from the original location due to safety reasons and the new location is considered

      representative.

(c)    The original location of R3 was situated approximately 1500 m off the east coast of Po Toi

      Island.  In view of frequent rough sea conditions in that area and the subsequent safety

      concerns, R3 is moved close to the midpoint of Po Toi Island and Sung Kong.  Given that

      R3 is a control station, its new location is considered representative.

2.2                                      Monitoring Parameters and Frequency

The baseline water quality monitoring was conducted in accordance with the requirements stated in the EM&A Manual, which are presented below.

2.2.1                                Monitoring Parameters

Parameters measured in situ were:

·           dissolved oxygen (DO) (% saturation and mg L-1);

·           temperature (°C);

·           turbidity (NTU); and

·           salinity (‰).

The only parameter measured in the laboratory was:

·           suspended solids (SS) (mgL-1).

In addition to the water quality parameters, other relevant data were measured and recorded in field logs, including the location of the sampling stations, water depth, time, weather conditions, sea conditions, tidal state, special phenomena and work activities undertaken around the monitoring and works area that may influence the monitoring results.

2.2.2                                Monitoring Frequency

Baseline water quality monitoring was carried out for two weeks, with the frequency of three days per week.  The interval between two sets of monitoring was not less than 36 hours.  The monitoring was undertaken at six locations (four impact monitoring stations C1, C2, C3, F1 and two control monitoring stations R2 and R3), as shown in Figure 2.1.  Samples were taken during mid-flood and mid-ebb tidal state on each sampling occasion.

2.3                                      Monitoring Equipment and Methodology

2.3.1                                Monitoring Equipment

Dissolved Oxygen, Temperature, Salinity, Turbidity Measuring Equipment

The instrument was a portable, weatherproof multi-parameter measuring instrument (YSI 6820) complete with cables, multi-probe sensor, comprehensive operation manuals, and was operable from a DC power source.  It was capable of measuring:

·           dissolved oxygen levels in the range of 0 – 50 mg L-1; and 0-500% saturation;

·           temperature of -5 to 50 °C;

·           turbidity levels between 0-1000 NTU (response of the sensor was checked with certified standard turbidity solutions before the start of measurement); and,

·           salinity in the range of 0-40 ppt (checked with 30 ppt Salinity solutions before the start of the measurement).

Water Depth Gauge

The water depth gauge affixed to the bottom of the water quality monitoring vessel was used.

Current Velocity and Direction

Current velocity and direction was estimated by conducting float tracking.

Positioning Device

A Global Positioning System (GPS) was used (C-Navigator World DGPS, GPS 72A) during monitoring to ensure the accurate recording of the position of the monitoring vessel before taking measurements.  The use of DGPS was used for positioning device, which was well calibrated at appropriate checkpoint.

Water Sampling Equipment

Water samples for suspended solids measurement were collected by the use of a multi-bottle water sampling system (General Oceanics Inc., Rosette Sampler ROS02), consisting of PVC bottles of more than two litres, which could be effectively sealed with cups at both ends.  The water sampler had a positive latching system to keep it open and prevent premature closure until released by a messenger when the sampler was at the selected water depth.

2.3.2                                Monitoring Methodology

Timing & Frequency

The water quality sampling was undertaken within a 3 hour window of 1.5 hours before and 1.5 hours after mid-flood and mid-ebb tides.  Tidal range for flood and ebb tides was not be less than 0.5m for capturing representative tides. 

Reference were made to the predicted tides at Waglan Island, which is the tidal station nearest to the Project site, published on the website of Hong Kong Observatory([1]).  Based on the predicted water levels at Waglan Island, the baseline water quality monitoring was conducted between 27 February and 13 March 2009, following the schedule presented in Annex A.

Duplicate samples were collected from each of the monitoring events for in situ measurements and laboratory analysis.

Depths

Each station was sampled and measurements were taken at three depths, 1 m below the sea surface, mid depth and 1m above the sea bed.  For stations that were less than 3 m in depth, only the mid depth sample was taken.

Protocols

The multi-parameter measuring instrument (YSI 6820) was checked and calibrated by an HOKLAS accredited laboratory before use (see calibration reports in Annex B).  Onsite calibration was also carried out to check the responses of sensors and electrodes using certified standard solutions before each use.  Sufficient stocks of spare parts were maintained for replacements when necessary, and backup monitoring equipment was made available.

Water samples for SS measurements were collected in high density polythene bottles, packed in ice (cooled to 4° C without being frozen), and delivered to an HOKLAS accredited laboratory as soon as possible after collection.

Laboratory Analysis

All laboratory work was carried out by an HOKLAS accredited laboratory.  Water samples of about 1,000 mL were collected at the monitoring and control stations for carrying out the laboratory determinations.  The determination work started within the next working day after collection of the water samples.  The SS laboratory measurements were provided to the client within 2 days of the sampling event (48 hours).  The analyses followed the standard methods as described in APHA Standard Methods for the Examination of Water and Wastewater, 19th Edition, unless otherwise specified (APHA 2540D for SS).

The QA/QC details were in accordance with requirements of HOKLAS or another internationally accredited scheme (details refer to Annex C).

2.4                                      Baseline Monitoring Results

The monitoring data and graphical presentations are summarised in Annex D.  No major activities influencing the water quality were identified during the monitoring period.

The Action and Limit Levels were set in the EM&A Manual and the proposed Action and Limit Levels were determined as shown in Table 2.3. 

Table 2.3        Determination of Action and Limit Level of Water Quality

Parameter

Action Level

Limit Level

DO in mgL-1 (b)

Surface and Mid-depth

5%-ile of baseline data for surface and middle layer

Bottom

5%-ile of baseline data for bottom layers

Surface and Mid-depth

4mg/L or 1%-ile of baseline for surface and middle layer

Bottom

2mg/L or 1%-ile of baseline data for bottom layer

SS in mgL-1

(Depth-averaged (a)) (c)

95%-ile of baseline data, or

20% exceedance of value at any impact station compared with corresponding data from control stations

 

99%-ile of baseline data, or

30% exceedance of value at any impact station compared with corresponding data from control stations

Turbidity in NTU

(Depth-averaged (a)) (c)

95%-ile of baseline data, or

20% exceedance of value at any impact station compared with corresponding data from control stations

99%-ile of baseline data, or

30% exceedance of value at any impact station compared with corresponding data from control stations

Notes:

a.         “Depth-averaged” is calculated by taking the arithmetic means of reading of all three depths.

b.         For DO, non-compliance of the water quality limits occurs when monitoring result is lower than the Action/Limit Levels.

c.          For SS and turbidity, non-compliance of the water quality limits occurs when monitoring result is higher than the Action/Limit Levels.

The Action and Limit Levels of DO and turbidity are derived from the baseline monitoring data for all impact stations for Zones B to D (including Stations F1, C1, C2 and C3), and the results are presented in Table 2.4.  Two sets of the Action and Limit levels of suspended solids are established for two groups of impact monitoring station(s) in the area, namely F1 to monitor the FCZ and C1, C2 as well as C3 to monitor the coral communities (see Tables 2.5 and 2.6). 

Please note that the results of Part B Baseline Monitoring are used to determine the Action and Limit Levels for the works to be undertaken near Po Toi Island (ie Zones B to D).


Table 2.4         Proposed Action and Limit Levels of Water Quality for Zones B to D

Parameter

Action Level

Limit Level

Dissolved Oxygen (DO) (1)

Surface and Mid-depth (2)

Surface and Mid-depth (2)

 

5%-ile of baseline data for surface and middle layer = 7.22 mg L-1

1%-ile of baseline data for bottom layer =7.12 mg L-1

 

 

 

 

Bottom

Bottom

 

5%-ile of baseline data for bottom layers = 7.14 mg L-1

1%-ile of baseline for bottom layer = 7.05 mg L-1

 

 

 

Depth-averaged Turbidity (Tby) (3) (4)

95%-ile of baseline data = 6.49 NTU

99%-ile of baseline data = 8.35 NTU

 

or 120% of control station's Tby at the same tide of the same day

or 130% of control station's Tby at the same tide of the same day

 

 

 

Notes:

(1)    For DO, non-compliance of the water quality limits occurs when monitoring result is lower than the limits.

(2)    The Action and Limit Levels for DO for Surface & Middle layer were calculated from the combined pool of baseline surface layer data and baseline middle layer data.

(3)    “Depth-averaged” is calculated by taking the arithmetic means of reading of all three depths.

(4)    For turbidity, non-compliance of the water quality limits occurs when monitoring result is higher than the limits.

Table 2.5        Proposed Action and Limit Levels of Suspended Solids for Impact Stations F1, C1, C2, and C3.

Parameter

Action Level

Limit Level

Depth-averaged Suspended Solids (SS)

Station F1

95%-ile of baseline data = 6.89 mg L-1

Station F1

99%-ile of baseline data = 7.11 mg L-1

 

Stations C1, C2 and C3

95%-ile of baseline data = 12.42 mg L-1

Stations C1, C2 and C3

99%-ile of baseline data = 14.28 mg L-1

 

 

 

 

or 120% of control station's SS at the same tide of the same day

or 130% of control station's SS at the same tide of the same day

 

 

 

Notes:

(1)    “Depth-averaged” is calculated by taking the arithmetic means of reading of all three depths.

(2)    Non-compliance of the water quality limits occurs when monitoring result is higher than the limits.

 


3                                            Conclusion

Baseline water quality monitoring was conducted between 27 February and 13 March 2009 at six designated monitoring stations near Po Toi Island (ie Zones B to D) established for the Project.  The monitoring was carried out 3 days per week, at mid-flood and mid-ebb tides, at three depths (surface, middle and bottom), for 2 weeks prior to the commencement of construction works.  No major activities were undertaken during baseline monitoring.  Water quality monitoring results are, therefore, representative of the baseline conditions for the Project.

The baseline monitoring results were used to determine the Action and Limit Levels for the DO, SS and turbidity for impact monitoring to be conducted at Zones B to D throughout the construction phase of the Project. 


 



([1])         Hong Kong Observatory (2009) http://www.hko.gov.hk/tide/eWAGtide.htm