Contents
1.1 Purpose of the Report
1.2 Structure of the Report
2.1 Background
2.2 Marine Construction Works Undertaken during Reporting Week
2.3 Status of Environmental Approval Documents
3 Water Quality Monitoring
Requirements
3.1 Monitoring Locations
3.2 Monitoring Parameters and Frequency
3.3 Monitoring Equipment and Methodology
4.1 Data Collected During Mid-Ebb and/or Mid-Flood Tidal Conditions
4.2 Continuous In-Situ Measurement Data
5 Environmental
Non-CONFORMANCES
5.1 Summary of Environmental Exceedance
5.2 Summary of Environmental Complaint
5.3 Summary of Environmental Summons and Prosecution
6.1 Key Issues For The Coming Month
6.2 Monitoring Schedule For The Coming Months
LIST
OF TABLES
Table
2.1 Summary of Marine Works Undertaken During
the Reporting Week
Table 2.2 Summary of Environmental Licensing,
Notification, Permit and Reporting Status
Table 3.3.1 Co-ordinates of Starting Points and Ending
Points for Zone A (HK Grid)
Table 3.3.2 Co-ordinates of Impact Monitoring Stations
in Zone A (HK Grid)
Table 3.3 Monitoring Frequency and Parameters for
Impact Monitoring at Zone A
Table 3.4 Proposed Action and Limit Levels of Water
Quality for Zones A and E
Table 4.2 Exceedances of Action and Limit Levels for
Bottom Dissolved Oxygen on 23 May 2009
Table 6.1 Construction Works to be Undertaken in the
Coming Monitoring Period
LIST
OF ANNEXES
Annex
A |
|
Annex
B |
|
Annex
C |
|
Annex
D |
LIST
OF ANNEXES
Figure 2.1 |
|
Figure
3.1 |
The construction works for
the VSNL Intra Asia Submarine Cable System –
Summary of Construction Works
undertaken during the Reporting Period
During
the reporting week, onboard
cable joint operations and preparation works were carried out in Zone A on 22 May and 23 May 2009, respectively. Due to weather constraints, the working
vessel had been on a four point mooring in Zone A awaiting
safe conditions offshore to progress cable installation operations since the
afternoon of 23 May 2009. No
onboard or underwater construction activities had been undertaken throughout
the remaining week. Neither the
injector nor the thrusters were in operation.
Water Quality
Daily monitoring events were scheduled between 22 May and 28 May 2009 at
Environmental Non-conformance
Daily exceedances of Action
and Limit Levels for dissolved oxygen were recorded in the reporting week. Depth-averaged turbidity and suspended solids
were generally compliant with
the Action and Limit Levels with the exception of 22 May and 28 May 2009. Results of the detailed investigation
indicated that none of the exceedances were
attributed to the Project construction works.
No complaints were received during the reporting week.
No environmental summons/prosecution
were received during the reporting week.
Future Key Issues
Construction activities to be undertaken in the
coming monitoring period (ie 29 May to 4 June 2009) are Phase
III cable installation works.
ERM-Hong Kong, Limited (ERM) was appointed
by Tata Communications (Bermuda) Ltd (formerly Videsh Sanchar Nigam
Limited (VSNL)) as the Monitoring Team (MT) to implement
the Environmental Monitoring and Audit (EM&A) programme for the VSNL Intra
Asia Submarine Cable System –
This is the fourth Weekly Impact
Monitoring Report, which
summarises the impact monitoring results and audit findings for the EM&A
programme during the reporting period from 22 May to 28 May 2009.
The structure of the report is as follows:
Section
1 : Introduction
Details the background, purpose and structure of the
report.
Section
2 : Project
Information
Summarises
background and scope of the project, the construction works undertaken and the
status of Environmental Permits/Licenses during the reporting period.
Section
3 : Water
Quality Monitoring Requirements
Summarises the
monitoring parameters, monitoring programmes, monitoring methodologies,
monitoring frequency, monitoring locations, Action and Limit Levels, and Event
/ Action Plans.
Section
4 : Monitoring
Results
Summarises the monitoring results obtained in the reporting period.
Section
5 : Environmental
Non-conformance
Summarises
any monitoring exceedance, environmental complaints
and environmental summons within the reporting period.
Section
6 : Future
Key Issues
Summarises the
monitoring schedule for the next week.
Section
7 : Conclusions
Presents the key findings of the impact
monitoring results.
Tata
Communications (Bermuda) Ltd (formerly Videsh Sanchar Nigam Limited (VSNL)) proposes to install a submarine
telecommunications cable, which will run from
In
August 2007, a Project Profile (PP) included an
assessment of the potential environmental impacts associated with the
installation of the submarine cable circuit was prepared and submitted to the
Environmental Protection Department (EPD) under section 5.(1)(b) and 5.(11) of the
Environmental Impact Assessment Ordinance (EIAO) for application for
Permission to apply directly for an Environmental Permit (EP). The Environmental Protection Department,
subsequently issued an Environmental Permit (EP-294/2007) and Further
Environmental Permit (FEP-01/294/2007).
Amendments to the permitting requirements were incorporated into the Environmental
Permit to address potential environmental impacts associated with cable
crossings over the HKE’s gas pipeline in southeast
Baseline
Monitoring was conducted near
Impact
Monitoring has been carried out at
2.2
Marine Construction
Works Undertaken during Reporting Week
The
cable installation barge “CB Networker” installs the cable in three phases:
·
Phase
I – Locate in-service cables by divers (ie
completed);
·
Phase
II – Conduct route clearance and pre-lay trial run of burial tool “Injector”
(completed); and
·
Phase
III – Install cable along the proposed route using the burial tool “Injector”.
A
summary of the major works undertaken during the reporting week is shown in Table 2.1.
Table 2.1 Summary
of Marine Works Undertaken During the Reporting Week
Date |
Works Area |
Activity |
Zone A |
Onboard
activities to join the Pre-laid shore end to the cable on board the barge |
|
23 May 2009 |
Zone A |
Preparation
works for Phase III Cable Installation in the morning. Weather downtime afterwards |
24 May 2009 |
Zone A |
Weather
downtime |
25 May 2009 |
Zone A |
Weather
downtime |
26 May 2009 |
Zone A |
Weather
downtime |
27 May 2009 |
Zone A |
Weather
downtime |
28 May 2009 |
Zone A |
Weather
downtime |
2.3
Status of
Environmental Approval Documents
A
summary of the relevant permits, licences, notifications and/or reports on
environmental protection for this Project is presented in Table 2.2.
Table 2.2 Summary
of Environmental Licensing, Notification, Permit and Reporting Status
Permit / Licence / Notification / Report |
Reference |
Validity Period |
Remarks |
Environmental Permit |
(EP-294/2007) |
Throughout the construction period |
Granted on 23 November 2008 |
Further Environmental Permit |
(FEP-01/294/2007) |
Throughout the construction period |
Granted on 9 July 2008 |
EM&A Manual |
- |
Throughout the construction period |
Approved by EPD on 12 March 2009 |
Baseline Water Quality Monitoring Report (Part A) |
- |
Throughout the construction period for Zones A and
E |
Approved by EPD on 1 April 2009 |
Baseline Water Quality Monitoring Report (Part B) |
- |
Throughout the construction period for Zones B to D |
Approved by EPD on 30 April 2009 |
In accordance with the EM&A Manual, during the installation
of the cable in Zone A, water quality sampling was undertaken at stations
situated around the cable laying works at
·
S1
and S2 are situated at the two Seawater Intake Points in
·
S3 is
a Sensitive Receiver used to monitor the water quality condition of the Coastal Protection Areas
at
·
B1 is
an Impact Station used to monitor the effect of the construction activities on
·
R1 is
a Control Station for S1, S2, S3 and B1 at
The
co-ordinates of Zone A and the above monitoring
stations are listed in Table 3.1 and Table 3.2, respectively.
Table 3.3.1 Co-ordinates
of Starting Points and Ending Points for Zone A (HK
Grid)
Zone |
Starting Point |
Ending Point |
||
Easting |
Northing |
Easting |
Northing |
|
A |
837029.763 |
811601.699 |
836367.572 |
810545.975 |
Table 3.3.2 Co-ordinates
of Impact Monitoring Stations in Zone A (HK Grid)
Station |
Nature |
Corresponding Control Station |
Easting |
Northing |
S1 |
Seawater
Intakes |
R1 |
836538.669 |
811528.535 |
S2 |
Seawater
Intakes |
R1 |
836195.047 |
810956.409 |
S3 |
Coastal
Protection Areas |
R1 |
836677.103 |
810666.744 |
B1 |
Gazetted
Beach |
R1 |
837241.114 |
811498.400 |
R1 |
Control Station |
- |
835951.109 |
809052.535 |
3.2
Monitoring Parameters
and Frequency
The
impact water quality monitoring was conducted in accordance with the requirements
stated in the EM&A Manual. These are presented below.
3.2.1
Monitoring
Parameters
Parameters measured in situ were:
·
dissolved oxygen (DO) (%
saturation and mg L-1);
·
temperature (°C);
·
turbidity (NTU); and
·
salinity (‰).
The
only parameter measured in the laboratory was:
·
suspended solids (SS) (mgL-1).
In addition to the water
quality parameters, other relevant data were measured and recorded in field
logs, including the location of the sampling stations, water depth, time,
weather conditions, sea conditions, tidal state, special phenomena and work
activities undertaken around the monitoring and works area that may influence
the monitoring results.
3.2.2
Monitoring
Frequency
Impact Monitoring at S1, S2, S3, B1 and R1 took
place when the cable installation works were undertaken within 500 m (Zone A)
of monitoring stations S1, S2, S3 and B1.
The sampling works ceased when no cable installation works were
conducted inside Zone A.
Impact
monitoring was carried out during the barge operating hours, normally covering
both mid-flood and mid-ebb tidal conditions, until water quality monitoring was
not required.
In-situ
and SS data of the control and impact stations within Zone A were collected daily
during mid-flood and mid-ebb tidal states (Table
3.3), unless the mid-ebb tide and/or the mid-flood tide were not occurring during
the monitoring period. In addition,
continuous in-situ measurements were
taken at the impact monitoring stations, ie B1, S1,
S2 and S3, at 30- to 60- minute intervals (subject to the weather conditions
and travelling time between stations) within Zone A. The monitoring frequency and parameters
for Impact Monitoring are summarised in Table
3.3.
Table
3.3 Monitoring
Frequency and Parameters for Impact Monitoring at Zone A
Zone |
Station Type |
Monitoring Station |
Monitoring Frequency |
Monitoring Parameter |
|
Mid-ebb Tide / Mid-flood Tide |
30- to 60- Minute Interval |
||||
A |
Control |
R1 |
Daily when cable installation works undertaken in
Zone A |
Temperature, Turbidity, Salinity, DO, SS |
- |
Impact |
S1, S2, S3 and B1 |
Temperature, Turbidity, Salinity, DO |
3.3
Monitoring Equipment
and Methodology
3.3.1
Monitoring
Equipment
Dissolved Oxygen, Temperature, Salinity, Turbidity Measuring Equipment
The instrument was a portable, weatherproof multi-parameter measuring
instrument (YSI 6820) complete with cables, multi-probe sensor, comprehensive
operation manuals, and was operable from a DC power source. It was capable of measuring:
·
dissolved oxygen levels in
the range of 0 – 50 mg L-1; and 0-500% saturation;
·
temperature of -5 to 50 °C;
·
turbidity levels between
0-1000 NTU (response of the sensor was checked with certified standard
turbidity solutions before the start of measurement); and,
·
salinity in the range of 0-40 ppt (checked with 30 ppt Salinity solutions before the start of the measurement).
Water Depth Gauge
The water depth gauge affixed to the bottom of the water quality
monitoring vessel was used.
Current Velocity and Direction
Current velocity and direction was estimated by conducting float
tracking.
Positioning Device
A Global Positioning System (GPS) was used (C-Navigator World DGPS, GPS
72A) during monitoring to ensure the accurate recording of the position of the
monitoring vessel before taking measurements. The use of DGPS was used for positioning
device, which was well calibrated at an appropriate checkpoint.
Water Sampling Equipment
Water samples for suspended solids measurement were collected by the use
of a multi-bottle water sampling system (General Oceanics Inc., Rosette Sampler ROS02), consisting of PVC bottles
of more than two litres, which could be effectively
sealed with cups at both ends. The
water sampler had a positive latching system to keep it open and prevent
premature closure until released by a messenger when the sampler was at the
selected water depth.
3.3.2
Monitoring
Methodology
Timing & Frequency
In-situ and SS data were collected daily at both
control and impact stations within Zone A provided that the monitoring period had
covered the mid-flood tide and/or mid-ebb tide. The water quality sampling was undertaken within a 3 hour window of 1.5
hours before and 1.5 hours after mid-flood and mid-ebb tides. Tidal range for flood and ebb tides was
not less than 0.5m for capturing representative tides.
Continuous In-situ
measurements were taken at 30- to 60- minute intervals (subject to the weather
conditions and travelling time between stations) for each impact station within
Zone A.
Reference was made to the predicted tides at Waglan
Island, which is the tidal station nearest to the Project site, published on
the website of Hong Kong Observatory([1]). Based on the predicted water
levels at
Duplicate samples were collected from each of the monitoring events for in
situ measurements and laboratory analysis.
Depths
Each station was sampled and measurements were taken at three depths, 1
m below the sea surface, mid depth and 1m above the sea bed.
Protocols
The multi-parameter measuring instrument (YSI 6820) was checked and
calibrated by an HOKLAS accredited laboratory before use. Onsite calibration was also carried out
to check the responses of sensors and electrodes using certified standard
solutions before each use. Sufficient
stocks of spare parts were maintained for replacements when necessary, and backup
monitoring equipment was made available.
Water samples for SS measurements were collected in high density
polythene bottles, packed in ice (cooled to 4° C without being frozen), and
delivered to an HOKLAS accredited laboratory as soon as possible after
collection.
Laboratory Analysis
All laboratory work was carried out by a HOKLAS accredited
laboratory. Water samples of about
1,000 mL were collected at the monitoring and control
stations for carrying out the laboratory determinations. The determination work started within the
next working day after collection of the water samples. The analyses followed the standard methods
as described in APHA Standard Methods for
the Examination of Water and Wastewater, 19th Edition, unless
otherwise specified (APHA 2540D for SS).
The QA/QC details were in accordance with requirements of HOKLAS or
another internationally accredited scheme (for details refer to Annex B).
3.3.3
Action
and Limit Levels
The Action and Limit levels for Zones A
and E, which were established based on the results of Baseline Environmental Monitoring Part A, are presented in Tables 3.4.
Table 3.4 Proposed
Action and Limit Levels of Water Quality for Zones A and E
Parameter |
Action
Level |
Limit
Level |
Dissolved Oxygen (DO) (1) |
Surface and Mid-depth (2) |
Surface and Mid-depth (2) |
|
5%-ile
of baseline data for surface and middle layer = 6.59 mg L-1 |
1%-ile
of baseline data for bottom layer = 6.42 mg L-1 |
|
|
|
|
Bottom |
Bottom |
|
5%-ile
of baseline data for bottom layers = 6.58 mg L-1 |
1%-ile of baseline for bottom layer = 6.42 mg L-1 |
|
|
|
Depth-averaged Suspended Solids (SS) (3) (4) |
95%-ile of baseline data = 7.91 mg L-1 |
99%-ile of baseline data = 8.96 mg L-1 |
|
or 120% of control station's SS at the same
tide of the same day |
or 130%
of control station's SS at the same tide of the same day |
|
|
|
Depth-averaged Turbidity (Tby)
(3) (4) |
95%-ile of baseline data
= 5.17 NTU |
99%-ile of baseline data
= 5.72 NTU |
|
or 120% of control station's Tby at the same tide of the same day |
or 130% of control station's Tby at the same tide of the same day |
|
|
|
Notes: (1) For
DO, non-compliance of the water quality limits occurs when monitoring result is
lower than the limits. (2) The
Action and Limit Levels for DO for Surface & Middle layer were calculated
from the combined pool of baseline surface layer data and baseline middle
layer data. (3) “Depth-averaged”
is calculated by taking the arithmetic means of reading of all three depths. (4) For
turbidity and SS, non-compliance of the water quality limits occurs when
monitoring result is higher than the limits. |
3.3.4
Event
and Action Plan
The Event and Action Plan for water
quality monitoring which was stipulated in the EM&A Manual is presented in Table
3.5.
Table
3.5 Event
Action Plan for Water Quality
Event |
Contractor |
Action
Level Exceedance |
Step 1 - repeat sampling event. Step 2 – identify source(s) of impact and confirm whether exceedance was due to the construction works; Step 3 – inform EPD, AFCD and LCSD and confirm notification of the
non-compliance in writing; Step 4 - discuss with cable installation contractor the most appropriate
method of reducing suspended solids during cable installation (e.g. reduce
cable laying speed/volume of water used during installation). Step 5 - repeat measurements after implementation of mitigation for
confirmation of compliance. Step 6 - if non compliance continues - increase measures in Step 4 and
repeat measurements in Step 5. If
non compliance occurs a third time, suspend cable laying operations. |
Limit Level Exceedance |
Undertake Steps 1-5 immediately, if further non
compliance continues at the Limit Level, suspend cable laying operations
until an effective solution is identified. |
Daily monitoring
events were scheduled between 22 May and 28 May 2009 at
4.1
Data Collected During
Mid-Ebb and/or Mid-Flood Tidal Conditions
The monitoring data taken during the mid-ebb
and/or mid-flood tidal conditions for Zone A are presented in Annex C and compared against the
baseline monitoring results in Figures C1
- C4. The impact monitoring
results, except DO, obtained during this week were mostly comparable to the
results recorded during the baseline monitoring. As shown in Figures C1 and C2,
dissolved oxygen levels at all the monitoring stations have started to decrease
since 22 May 2009 and then dropped close to or below the Limit Levels. It should be noted that DO levels measured
at all the impact stations were of similar magnitude to DO levels detected at
the control station. This implies
the background levels of DO were also relatively low.
Depth-averaged turbidity and suspended solids
were generally compliant with the Action and Limit Levels; however, SS exceedances were noted at stations B1, S1 and S2 on 22 May
2009. There was an exceedance of the Action Level for turbidity at station B1
on 28 May 2008. A review of the
above exceedance is discussed in the following
section.
4.1.1
Exceedance on 22 May 2009
Exceedances of the Action and Limit Levels for Bottom
Dissolved Oxygen (DOB) and Depth-averaged Suspended Solids (SS) were recorded
on 22 May 2009 (Table 4.1).
The Contractor confirmed that the
Networker was on a four point mooring in Zone A throughout the day of 22 May
2009. Onboard activities were
undertaken to join the Pre-laid shore end to the cable on board the barge. Neither the injector nor the thrusters
were in operation.
The levels of suspended solids measured at
stations S1, S2 and B1 were 0.1 – 1.1 mg/L higher than 120% of the control station’s
SS whilst these values did not exceed the Action and Limit Levels derived from
the baseline data. In addition, SS
levels of all impact stations did not show non-compliance during the following
mid-flood tide. It was, therefore,
considered that the SS exceedances were more likely to
be caused by localised factors or temporary tidal influence rather than the
Project works.
The DOB concentrations recorded at stations
S1 and S3 were 0.05 – 0.22 mg/L below the Action Level. However, the DOB of the water samples
taken at the control station R1 was even lower than the Limit Level during both
the mid-ebb and mid-flood tidal conditions. This indicates the ambient DOB levels
were relatively low and the decrease in DOB could be due to natural fluctuation. Nevertheless, the DOB levels at stations
S1 and S3 were compliant with the Water Quality Objective of not less than 2
mg/L for 90% of samples for bottom DO.
No spatial trend could be drawn from the
monitoring results and hence there were no indications of pollution sources
coming from the Project works area.
The exceedances were, therefore, considered
unlikely related to the Project works.
Table
4.1 Exceedances of Action and Limit Levels for Bottom Dissolved
Oxygen and Depth-averaged Suspended Solids on 22 May 2009
Exceedance
Log No. |
0096120_22
May 09_SS_E_Station S1 0096120_22
May 09_SS_E_Station S2 0096120_22
May 09_SS_E_Station B1 0096120_22
May 09_DOB_E_Station S1 0096120_22
May 09_DOB_E_Station S3 0096120_22
May 09_DOB_F_Station S3 |
||
Sampling date |
22
May 2009 |
||
Monitoring station |
B1,
S1, S2 and S3 |
||
Parameter |
Depth-averaged
Suspended Solids (mg/L) Dissolved
Oxygen, Bottom (DOB) (mg/L) |
||
Action Levels |
Mid-Ebb |
DOB = 6.58 (baseline data) SS
: 120% of R1 = 6.4 or 7.91 (baseline data) |
|
Mid-Flood |
DOB = 6.58 (baseline data) SS
: 120% of R1 = 10.0 or 7.91 (baseline data) |
||
Limit Levels |
Mid-Ebb |
DOB = 6.42 (baseline data) SS
: 130% of R1 = 6.9 or 8.96 (baseline data) |
|
Mid-Flood |
DOB = 6.42 (baseline data) SS
: 130% of R1 =10.8 or 8.96 (baseline data) |
||
Measured Levels at Station B1 |
Mid-Ebb |
SS
= 6.67 |
(exceeds Action Level) |
Mid-Flood |
SS
= 5.67 |
|
|
Measured Levels at Station S1 |
Mid-Ebb |
SS
= 6.50 DOB
= 6.36 |
(exceeds Action Level) (exceeds Limit Level) |
Mid-Flood |
SS
= 4.17 DOB
= 8.08 |
|
|
Measured Levels at Station S2 |
Mid-Ebb |
SS
= 7.50 |
(exceeds
Limit Level) |
Mid-Flood |
SS
= 3.85 |
|
|
Measured Levels at Station S3 |
Mid-Ebb |
DOB
= 6.53 |
(exceeds
Action Level) |
Mid-Flood |
DOB
= 6.51 |
(exceeds
Action Level) |
4.1.2
Exceedance on 23 May 2009
Exceedances of the Action and Limit Levels for Bottom
Dissolved Oxygen (DOB) were recorded at stations S2 and S3 on 23 May 2009 (Table 4.2).
The Contractor confirmed that preparation
works were undertaken on the morning of 23 May 2009 until the weather
conditions became too severe to proceed. Starting from 12:00 hrs, the working
vessel had been on a four point mooring in Zone A and no construction had been
carried out afterwards. Neither the
injector nor the thrusters were in operation.
Similar to 22 May 2009, the DOB levels detected
at stations S2 and S3 were only 0.13 – 0.79 mg/L lower than the Action Levels
but were higher than those recorded at the control station R1. It was also noted that the DOB of the
water samples taken at the control station R1 exceeded the Limit Levels during
both the mid-ebb and mid-flood tidal conditions. This implies the ambient DOB levels were
still relatively low and the decrease in DOB could be due to natural
fluctuation. No action was hence
required. Nevertheless, the DOB levels
at stations S1 and S3 were compliant with the Water Quality Objective of not
less than 2 mg/L for 90% of samples for bottom DO.
Table 4.2 Exceedances of Action and Limit Levels for Bottom Dissolved
Oxygen on 23 May 2009
Exceedance
Log No. |
0096120_23
May 09_DOB_E_Station S2 0096120_23
May 09_DOB_E_Station S3 0096120_23
May 09_DOB_F_Station S2 0096120_23
May 09_DOB_F_Station S3 |
||
Sampling date |
23
May 2009 |
||
Monitoring station |
S2
and S3 |
||
Parameter |
Dissolved
Oxygen, Bottom (DOB) (mg/L) |
||
Action Levels |
Mid-Ebb Mid-Flood |
6.58 (baseline data) |
|
Limit Levels |
Mid-Ebb Mid-Flood |
6.42 (baseline data) |
|
Measured Levels at Station S2 |
Mid-Ebb |
5.79 |
(exceeds
Limit Level) |
Mid-Flood |
6.45 |
(exceeds
Action Level) |
|
Measured Levels at Station S3 |
Mid-Ebb |
5.79 |
(exceeds
Limit Level) |
Mid-Flood |
5.88 |
(exceeds
Limit Level) |
4.1.3
Exceedance form 24 May to 28 May 2009
Due to weather constraints, the working
vessel had been on a four point mooring in Zone A
awaiting safe conditions offshore to progress cable installation operations
since the afternoon of 23 May 2009. No onboard or underwater construction
activities had been undertaken during the period of 24 May and 28 May 2009. Neither the injector nor the thrusters
were in operation. However, daily exceedances of Limit Levels for dissolved oxygen were
recorded during the water quality monitoring in these five days.
It was observed that the DO concentrations
measured at all the impact stations were comparable to those recorded at the control
station R1 during this monitoring period (ie 24 May
and 28 May 2009). Besides,
non-compliances of DO levels were also noted at the control station R1. This suggests the ambient DO levels were
relatively low and DO depletion was first detected in the bottom layer of the
water column on 22 May 2009.
In the beginning of the week, the weather
was sunny and hot (high solar radiation) which would favour thermal
stratification. Freshwater input
from the precipitation during the weekend (reducing salinity) could cause the
density difference between the surface layer and the salty deep waters to be
greater. The stratification could
limit the circulation of oxygen between the layers of waters due to the density
difference. Dissolved oxygen levels
could decrease in the bottom layer because photosynthesis and contact with the
air may be significantly reduced.
The already reduced oxygen levels could be further depleted through the
decomposition of organic matters washed into the marine waters during the
rainstorm. This phenomenon is
supported by the fact that DOB exceedances were noted
whilst relatively high DO concentrations were measured at the surface and
mid-depth on 22 May and 23 May 2009.
It is believed that the thermocline was broken by strong wind/wave or heavy
rainstorm leading to mixing of oxygen-rich surface waters with oxygen-deficient
bottom waters. There is the
potential for all DO present in the waters to be rapidly removed for satisfying
the oxygen demand resulting in further oxygen depletion throughout the water
column in the subsequent days.
Although such situation may last for a certain period of time due to the
unstable weather conditions, DO concentrations measured at all impact stations were
in compliance with the Water Quality Objectives for DO (ie
not less than 2 mg/L for 90% of samples for bottom DO and not less than 4 mg/L
for 90% of samples for depth-averaged DO).
This explains that the recent declining
trends of dissolved oxygen and daily DO exceedances
may be due to natural fluctuation (ie stratification
followed by de-stratification).
It should be noted that although exceedances of the Action and Limit Levels for DO occurred,
no non-compliances of the WQOs were reported.
Exceedances of the Action Levels for depth-averaged
turbidity and SS were noted at station B1 on 28 May 2009 during the mid-ebb
tide. The turbidity and SS levels measured at B1 was slightly higher than the Action
Levels derived from the baseline data but these values were well below the 120%
of the control station’s turbidity and SS.
At the time of the monitoring event, station B1 was located upstream of
the working vessel during the mid-ebb tide. Therefore, the turbidity and SS exceedances were considered to be caused by some localised
activities in the vicinity of B1 which were not related to the project.
4.2
Continuous In-Situ
Measurement Data
Continuous in-situ measurements were taken at the impact monitoring stations, ie B1, S1, S2 and S3, at 30- to 60- minute intervals
(subject to the weather conditions and travelling time between stations) for
Zone A and the results and the graphical presentations were included in Annex D.
In general, the water quality of Zone A
was stable throughout each sampling day with the exception of some fluctuations
in DO during the first few days.
5.1
Summary of
Environmental Exceedance
Daily Notification of Exceedances
(NOEs) with detailed investigation reports were
issued to EPD and AFCD during the reporting period for recording water quality
monitoring exceedances on dissolved oxygen, turbidity
and suspended solids of the monitoring stations. The exceedances
were examined against the Project works.
Results of the detailed investigation indicated that none of the exceedances were attributed to the Project construction
works.
5.2
Summary of
Environmental Complaint
No complaints were received during the
reporting period.
5.3
Summary of
Environmental Summons and Prosecution
No summons or prosecution on environmental
matters were received during the reporting period.
6.1
Key Issues For The
Coming Month
Works to be taken for the coming
monitoring period are summarised in Table
6.1.
Table
6.1 Construction
Works to be Undertaken in the Coming Monitoring Period
Zone |
Works to be taken |
A |
Phase III Cable
Installation |
E |
Phase III Cable
Installation |
B |
Phase III Cable
Installation |
C |
Phase III Cable
Installation |
D |
Phase III Cable
Installation |
6.2
Monitoring Schedule
For The Coming Months
The tentative schedule of water quality
monitoring for the coming week (ie 29 May to 4 June 2009) is presented in Annex A. The water
sampling will be conducted at the same monitoring location as in this reporting
week. However, the tentative
schedule of the water quality monitoring is subject to continued operational
progress and weather constraints.
This Weekly Impact Monitoring Report
presents the EM&A work undertaken during the period from 22 May to 28 May
2009 in accordance with the EM&A Manual and the requirements under FEP-01/294/2007.
Daily exceedances
of Action and Limit Levels for dissolved oxygen were recorded in the reporting
week. Depth-averaged turbidity and
suspended solids were generally compliant with the Action and Limit Levels with the exception of 22
May and 28 May 2009. Results of the
detailed investigation indicated that none of the exceedances
were attributed to the Project construction works.
No complaints and
summons/prosecution were received during the reporting week.
The MT will keep track of the EM&A
programme to verify compliance of environmental requirements and the proper
implementation of all necessary mitigation measures.