Contents

Executive Summary                                                                                     

1                      introduction                                                                          

1.1                   Purpose of the Report                                                     

1.2                   Structure of the Report                                                

2                      Project Information                                                          

2.1                   Background                                                                           

2.2                   Marine Construction Works Undertaken during Reporting Week      

2.3                   Status of Environmental Approval Documents

3                      Water Quality Monitoring Requirements                

3.1                   Monitoring Locations                                                        

3.2                   Monitoring Parameters and Frequency                 

3.3                   Monitoring Equipment and Methodology               

4                      Impact Monitoring Results                                             

4.1                   Data Collected During Mid-Ebb and/or Mid-Flood Tidal Conditions     

4.2                   Continuous In-Situ Measurement Data                     

5                      Environmental Non-CONFORMANCES                          

5.1                   Summary of Environmental Exceedance                

5.2                   Summary of Environmental Complaint                    

5.3                   Summary of Environmental Summons and Prosecution

6                      Future Key Issues                                                                 

6.1                   Key Issues For The Coming Month                                

6.2                   Monitoring Schedule For The Coming Month        

7                      Conclusions                                                                           

 


LIST OF TABLES

Table 2.1        Summary of Marine Works Undertaken During the Reporting Week

Table 2.2        Summary of Environmental Licensing, Notification, Permit and Reporting Status

Table 3.1        Co-ordinates of Starting Points and Ending Points for Zones A to E (HK Grid)

Table 3.2        Co-ordinates of All Monitoring Stations (HK Grid)

Table 3.3        Monitoring Frequency and Parameters for Impact Monitoring

Table 3.4        Action and Limit Levels of Water Quality for Zones A and E

Table 3.5        Action and Limit Levels of Dissolved Oxygen and Turbidity for Zones B to D

Table 3.6        Action and Limit Levels of Suspended Solids for Impact Stations F1, C1, C2, and C3

Table 4.1        Exceedances of Action and Limit Levels for Depth-averaged Turbidity and Suspended Solids on 29 May 2009

 

 

LIST OF ANNEXES

Annex A

Impact Monitoring Schedule

Annex B

QA/QC Results of Laboratory Testing for Suspended Solids

Annex C

Impact Water Quality Monitoring Results

Annex D

Continuous In-situ Measurement Data

 

LIST OF Figure

Figure 2.1

The Route of the Proposed Cable System

Figure 3.1

Water Quality Monitoring Stations (Zones A to E)

 

 

Executive Summary

The construction works for the VSNL Intra Asia Submarine Cable System – Deep Water Bay commenced on 16 March 2009.  This is the fifth Weekly Impact Monitoring Report presenting the impact water quality monitoring conducted during the period from 29 May to 4 June 2009 in accordance with the EM&A Manual.

Summary of Construction Works undertaken during the Reporting Period

Due to weather constraints, the working vessel continued to be on a four point mooring in Zone A on 29 May 2009.  Installation of cable along the proposed route was undertaken in Zones A to E on 30 May and 31 May 2009.  Phase III cable installation works were completed on 2 June 2009 and the working vessel returned to China Merchants Wharf for demobilisation on the same day. 

Water Quality

Three monitoring events were scheduled between 29 May and 4 June 2009.  All monitoring events at all designated monitoring stations were performed on schedule, ie on 29 May, 30 May and 31 May 2009. 

Environmental Non-conformance

Daily exceedances of Action and Limit Levels for dissolved oxygen were recorded on the three monitoring events (ie 29 May, 30 May and 31 May 2009).  Depth-averaged turbidity and suspended solids were generally compliant with the Action and Limit Levels with the exception of 29 May 2009.  Results of the detailed investigation indicated that none of the exceedances were attributed to the Project construction works.

No complaints were received during the reporting week.

No environmental summons/prosecution were received during the reporting week.

Future Key Issues

As there will be no cable installation works in the following weeks, the impact monitoring will be suspended and the post-project monitoring will take place in early July 2009 after the completion of the grout mattress installation at the crossing of Tata’s cable system and HKE's gas pipeline in south east Hong Kong waters.  A pilot study water quality monitoring will be undertaken during the installation of the grout mattress and the results will be presented in the Pilot Study Monitoring Report.

 


1                                  introduction

ERM-Hong Kong, Limited (ERM) was appointed by Tata Communications (Bermuda) Ltd (formerly Videsh Sanchar Nigam Limited (VSNL)) as the Monitoring Team (MT) to implement the Environmental Monitoring and Audit (EM&A) programme for the VSNL Intra Asia Submarine Cable System – Deep Water Bay (thereinafter called the (‘Project’)).

1.1                            Purpose of the Report

This is the fifth Weekly Impact Monitoring Report, which summarises the impact monitoring results and audit findings for the EM&A programme during the reporting period from 29 May to 4 June 2009.

1.2                            Structure of the Report

The structure of the report is as follows:

Section 1 :  Introduction

Details the background, purpose and structure of the report.

 

Section 2 :  Project Information

Summarises background and scope of the project, the construction works undertaken and the status of Environmental Permits/Licenses during the reporting period.

 

Section 3 :  Water Quality Monitoring Requirements

Summarises the monitoring parameters, monitoring programmes, monitoring methodologies, monitoring frequency, monitoring locations, Action and Limit Levels, and Event / Action Plans.

 

Section 4 :  Monitoring Results

Summarises the monitoring results obtained in the reporting period.

 

Section 5 :  Environmental Non-conformance

Summarises any monitoring exceedance, environmental complaints and environmental summons within the reporting period.

 

Section 6 :  Future Key Issues

Summarises the monitoring schedule for the next week.

 

Section 7 :  Conclusions

Presents the key findings of the impact monitoring results.

 

2                                  Project Information

2.1                            Background

Tata Communications (Bermuda) Ltd (formerly Videsh Sanchar Nigam Limited (VSNL)) proposes to install a submarine telecommunications cable, which will run from Deep Water Bay and through southeast Hong Kong offshore waters.  The cable landing site will be at the western edge of Deep Water Bay beach at an existing cable landing manhole location.  From Deep Water Bay, the cable will extend southwards towards the East Lamma Channel.  Near to Round Island, the cable will turn approximately parallel to the East Lamma Channel passing to the south of Po Toi Island.  The cable will then run eastward close to the boundary of HKSAR waters and then out beyond Hong Kong territorial waters into the South China Sea.  At the southeast offshore waters, it will be necessary to install a grout mattress to protect the cable where it crosses Hong Kong Electric Co., Ltd’s (HKE) gas pipeline.  A map of the proposed cable route is presented in Figure 2.1.

In August 2007, a Project Profile (PP) included an assessment of the potential environmental impacts associated with the installation of the submarine cable circuit was prepared and submitted to the Environmental Protection Department (EPD) under section 5.(1)(b) and 5.(11) of the Environmental Impact Assessment Ordinance (EIAO) for application for Permission to apply directly for an Environmental Permit (EP).  The Environmental Protection Department, subsequently issued an Environmental Permit (EP-294/2007) and Further Environmental Permit (FEP-01/294/2007).  Amendments to the permitting requirements were incorporated into the Environmental Permit to address potential environmental impacts associated with cable crossings over the HKE’s gas pipeline in southeast Hong Kong waters.  Under the requirements of Condition 3 of the EP, an EM&A programme as set out in the Environmental Monitoring and Audit Manual (EM&A Manual) is required to be implemented.  In accordance with the EM&A Manual, impact monitoring of water quality is required for the Project.

Baseline Monitoring was conducted near Deep Water Bay (ie Zones A and E) between 27 February 2009 and 9 March 2009 and the results were presented in the Baseline Water Quality Monitoring Report Part A.  Baseline monitoring for the Po Toi section of works was undertaken from 27 February 2009 to 13 March 2009 and the Baseline Water Quality Monitoring Report Part B presented the results of the monitoring data for Zones B to D near Po Toi Island.

Impact Monitoring has been carried out at Deep Water Bay (ie Zone A) since 25 March 2009. 

This report presents results of the data from monitoring stations in Zones A to E during the cable installation works.  Results of the impact monitoring data will therefore be compared against the results of the Baseline Environmental Monitoring Part A and Part B.

2.2                            Marine Construction Works Undertaken during Reporting Week

The cable installation barge “CB Networker” installs the cable in three phases:

·           Phase I – Locate in-service cables by divers (completed);

·           Phase II – Conduct route clearance and pre-lay trial run of burial tool “Injector” (completed); and

·           Phase III – Install cable along the proposed route using the burial tool “Injector”.

A summary of the major works undertaken during the reporting week is shown in Table 2.1.

Table 2.1        Summary of Marine Works Undertaken During the Reporting Week

Date

Works Area

Activity

29 May 2009

Zone A

Weather downtime

30 May 2009

Zones A and E

Installation of cable along the proposed route using the burial tool “Injector”

31 May 2009

Zones B to D

Installation of cable along the proposed route using the burial tool “Injector”

1 June 2009

Outside Zones A to E

Installation of cable along the proposed route using the burial tool “Injector”

2 June 2009

Outside Zones A to E

Installation of cable along the proposed route using the burial tool “Injector”.  Vessel docked alongside China Merchants Wharf for demobilisation

3 June 2009

China Merchants Wharf

Demobilisation

4 June 2009

China Merchants Wharf

Demobilisation

 

2.3                            Status of Environmental Approval Documents

A summary of the relevant permits, licences, notifications and/or reports on environmental protection for this Project is presented in Table 2.2.


Table 2.2        Summary of Environmental Licensing, Notification, Permit and Reporting Status

Permit / Licence / Notification / Report

Reference

Validity Period

Remarks

Environmental Permit

(EP-294/2007)

Throughout the construction period

 

Granted on 23 November 2008

Further Environmental Permit

(FEP-01/294/2007)

Throughout the construction period

 

Granted on 9 July 2008

EM&A Manual

-

Throughout the construction period

 

Approved by EPD on 12 March 2009

Baseline Water Quality Monitoring Report (Part A)

-

Throughout the construction period for Zones A and E

Approved by EPD on 1 April 2009

Baseline Water Quality Monitoring Report (Part B)

-

Throughout the construction period for Zones B to D

Approved by EPD on 30 April 2009


3                                  Water Quality Monitoring Requirements

3.1                            Monitoring Locations

In accordance with the EM&A Manual, during the installation of the cable, water quality sampling was undertaken at stations situated around the cable laying works at Deep Water Bay (ie Zone A), Round Island (ie Zone E) and Po Toi (ie Zones B to D).  The monitoring at those stations is to ensure the construction works of the Project do not affect the sensitive area nearby (shown in Figure 3.1)

·           S1 and S2 are situated at the two Seawater Intake Points in Deep Water Bay.  They are within 500 m west/northwest of the cable alignment at Deep Water Bay for monitoring the effect of cable laying works in the area.  The monitoring works started when the cable installation works were carried out in Zone A;

·           S3 is a Sensitive Receiver used to monitor the water quality condition of the Coastal Protection Areas at Middle Island.  The water sampling water took place when the cable installation works were conducted in Zone A;

·           B1 is an Impact Station used to monitor the effect of the construction activities on Deep Water Bay Beach when the cable installation works were undertaken in Zone A;

·           R1 is a Control Station for S1, S2, S3 and B1 at Deep Water Bay which is not supposed to be influenced by the cable laying works due to its remoteness from the construction works;

·           C1, C2 and C3 are located approximately 600 m north of the cable alignment at Po Toi for monitoring the effect of cable laying works on coral communities in the area.  The water quality monitoring at C1 would be initiated when the cable installation barge entered Zone B.  Similarly, the monitoring works were carried out at C2 and C3 when the cable installation barge moved inside Zones C and D, respectively;

·           F1 is used to monitor the effect of the cable installation works on the Po Toi Fish Culture Zone (FCZ).  It is approximately 1,500 m to the north of the cable alignment, which is not supposed to be influenced by the cable laying works due to its remoteness to the construction works.  The water quality of the Po Toi FCZ was monitored when the cable installation was undertaken inside Zones B to D;

·           R2 and R3 are Control Stations for C1, C2, C3 and F1 at Po Toi which are not supposed to be influenced by the cable laying works due to their remoteness to the construction works;

·           C4 and C5 are Impact Stations used to monitor the effect of cable laying works on the water quality conditions for the coral communities found at Round Island and the southern side of Chung Hom Wan, respectively.  The water quality monitoring works commenced when the cable installation barge entered Zone E; and

·           R4 is Control Station for C4 and C5 in Zone E.  It is not expected to be influenced by the construction works.

The co-ordinates of each zone and the above monitoring stations are listed in Table 3.1 and Table 3.2, respectively.

Table 3.1        Co-ordinates of Starting Points and Ending Points for Zones A to E (HK Grid)

Zone

Starting Point

 

Ending Point

 

 

Easting

Northing

Easting

Northing

A

837029.763

811601.699

836367.572

810545.975

B

841917.597

802680.115

844161.823

801308.268

C

844161.823

801308.268

845555.155

801495.491

D

845555.155

801495.491

846970.152

801749.210

E

836469.415

809294.174

837478.871

807740.633

Table 3.2        Co-ordinates of All Monitoring Stations (HK Grid)

Station

Nature            

Corresponding Control Station

Easting

Northing

S1

Seawater Intakes

R1

836538.669

811528.535

S2

Seawater Intakes

R1

836195.047

810956.409

S3

Coastal Protection Areas

R1

 

836677.103

810666.744

B1

Gazetted Beach

R1

837241.114

811498.400

 

 

 

 

 

C1

Coral Colonies

R2, R3

843547.181

802010.004

C2

Coral Colonies

R2, R3

844800

801840

C3

Coral Colonies

R2, R3

846179.538

802224.554

C4

Coral Colonies

R4

836863.233

808528.950

C5

Coral Colonies

R4

838197.242

808036.724

 

 

 

 

 

F1

Fish Culture Zone

R2, R3

843920

802730

 

 

 

 

 

R1

Control Station

-

835951.109

809052.535

R2

Control Station

-

842074.745

803375.183

R3

Control Station

-

846444

804982

R4

Control Station

-

835934.876

807347.391

3.2                            Monitoring Parameters and Frequency

The impact water quality monitoring was conducted in accordance with the requirements stated in the EM&A Manual.  These are presented below.

3.2.1                      Monitoring Parameters

Parameters measured in situ were:

·           dissolved oxygen (DO) (% saturation and mg L-1);

·           temperature (°C);

·           turbidity (NTU); and

·           salinity (‰).

The only parameter measured in the laboratory was:

·           suspended solids (SS) (mgL-1).

In addition to the water quality parameters, other relevant data were measured and recorded in field logs, including the location of the sampling stations, water depth, time, weather conditions, sea conditions, tidal state, special phenomena and work activities undertaken around the monitoring and works area that may influence the monitoring results.

3.2.2                      Monitoring Frequency

Impact Monitoring at S1, S2, S3, B1 and R1 took place when the cable installation works were undertaken within 500 m (Zone A) of monitoring stations S1, S2, S3 and B1.  The sampling works ceased when no cable installation works were conducted inside Zone A.

Impact Monitoring at C1, C2, C3, F1, R2 and R3 commenced when the cable installation barge was within Zones B, C or D near Po Toi (coral colonies).  The monitoring works were carried out at C1 and F1 when the cable installation barge moved inside Zone B.  The water quality monitoring at C2 and F1 was initiated once the cable installation barge exited Zone B and entered Zone C.  Likewise, in situ measurements and water samples were taken at C3 and F1 when the cable installation was conducted inside Zone D.  The sampling works halted upon the demobilisation of the cable installation barge.

Impact Monitoring at C4, C5 and R4 started when the cable installation barge entered Zone E.  No monitoring works would be performed once the cable installation barge left Zone E.

Impact monitoring was carried out during the barge operating hours, normally covering both mid-flood and mid-ebb tidal conditions, until water quality monitoring was not required.

In-situ and SS data of the control and impact stations within the impact zone were collected daily during mid-flood and mid-ebb tidal states (Table 3.3), unless the mid-ebb tide and/or the mid-flood tide were not occurring during the monitoring period.  In addition, continuous in-situ measurements were taken at the impact monitoring stations, ie C1-5, B1, F1 & S1-3, at 30- to 60- minute intervals (subject to the weather conditions and travelling time between stations) within the zone subject to monitoring.  The monitoring frequency and parameters for Impact Monitoring are summarised in Table 3.3.

Table 3.3        Monitoring Frequency and Parameters for Impact Monitoring

Zone

Station Type

Monitoring Station

Monitoring Frequency

Monitoring Parameter

Mid-ebb Tide / Mid-flood Tide

30- to 60- Minute Interval

A

Control

R1

Daily when cable installation works undertaken in Zone A

Temperature, Turbidity, Salinity, DO, SS

-

Impact

S1, S2, S3 and B1

Temperature, Turbidity, Salinity, DO

B

Control

R2 and R3

Daily when cable installation works undertaken in Zone B

-

Impact

C1, F1

Temperature, Turbidity, Salinity, DO

C

Control

R2 and R3

Daily when cable installation works undertaken in Zone C

-

Impact

C2, F1

Temperature, Turbidity, Salinity, DO

D

Control

R2 and R3

Daily when cable installation works undertaken in Zone D

-

Impact

C3, F1

Temperature, Turbidity, Salinity, DO

E

Control

R4

Daily when cable installation works undertaken in Zone E

-

Impact

C4 and C5

Temperature, Turbidity, Salinity, DO

3.3                            Monitoring Equipment and Methodology

3.3.1                      Monitoring Equipment

Dissolved Oxygen, Temperature, Salinity, Turbidity Measuring Equipment

The instrument was a portable, weatherproof multi-parameter measuring instrument (YSI 6820) complete with cables, multi-probe sensor, comprehensive operation manuals, and was operable from a DC power source.  It was capable of measuring:

·           dissolved oxygen levels in the range of 0 – 50 mg L-1; and 0-500% saturation;

·           temperature of -5 to 50 °C;

·           turbidity levels between 0-1000 NTU (response of the sensor was checked with certified standard turbidity solutions before the start of measurement); and,

·           salinity in the range of 0-40 ppt (checked with 30 ppt Salinity solutions before the start of the measurement).

Water Depth Gauge

The water depth gauge affixed to the bottom of the water quality monitoring vessel was used.

Current Velocity and Direction

Current velocity and direction was estimated by conducting float tracking.

Positioning Device

A Global Positioning System (GPS) was used (C-Navigator World DGPS, GPS 72A) during monitoring to ensure the accurate recording of the position of the monitoring vessel before taking measurements.  The use of DGPS was used for positioning device, which was well calibrated at an appropriate checkpoint.

Water Sampling Equipment

Water samples for suspended solids measurement were collected by the use of a multi-bottle water sampling system (General Oceanics Inc., Rosette Sampler ROS02), consisting of PVC bottles of more than two litres, which could be effectively sealed with cups at both ends.  The water sampler had a positive latching system to keep it open and prevent premature closure until released by a messenger when the sampler was at the selected water depth.

3.3.2                      Monitoring Methodology

Timing & Frequency

In-situ and SS data were collected daily at both control and impact stations in the zone which was under monitoring provided that the monitoring period had covered the mid-flood tide and/or mid-ebb tide.  The water quality sampling was undertaken within a 3 hour window of 1.5 hours before and 1.5 hours after mid-flood and mid-ebb tides.  Tidal range for flood and ebb tides was not less than 0.5 m for capturing representative tides.  Continuous In-situ measurements were taken at 30- to 60- minute intervals (subject to the weather conditions and travelling time between stations) for each impact station within the zone subject to monitoring.

Reference was made to the predicted tides at Waglan Island, which is the tidal station nearest to the Project site, published on the website of Hong Kong Observatory([1]).  Based on the predicted water levels at Waglan Island, the impact water quality monitoring was conducted following the schedule presented in Annex A.

Duplicate samples were collected from each of the monitoring events for in situ measurements and laboratory analysis.

Depths

Each station was sampled and measurements were taken at three depths, 1 m below the sea surface, mid depth and 1m above the sea bed.

Protocols

The multi-parameter measuring instrument (YSI 6820) was checked and calibrated by an HOKLAS accredited laboratory before use.  Onsite calibration was also carried out to check the responses of sensors and electrodes using certified standard solutions before each use.  Sufficient stocks of spare parts were maintained for replacements when necessary, and backup monitoring equipment was made available.

Water samples for SS measurements were collected in high density polythene bottles, packed in ice (cooled to 4° C without being frozen), and delivered to an HOKLAS accredited laboratory as soon as possible after collection.

Laboratory Analysis

All laboratory work was carried out by a HOKLAS accredited laboratory.  Water samples of about 1,000 mL were collected at the monitoring and control stations for carrying out the laboratory determinations.  The determination work started within the next working day after collection of the water samples.  The analyses followed the standard methods as described in APHA Standard Methods for the Examination of Water and Wastewater, 19th Edition, unless otherwise specified (APHA 2540D for SS).

The QA/QC details were in accordance with requirements of HOKLAS or another internationally accredited scheme (for details refer to Annex B).

3.3.3                      Action and Limit Levels

The Action and Limit levels for Zones A and E, which were established based on the results of Baseline Environmental Monitoring Part A, are presented in Tables 3.4.

Table 3.4        Action and Limit Levels of Water Quality for Zones A and E

Parameter

Action Level

Limit Level

Dissolved Oxygen (DO) (1)

Surface and Mid-depth (2)

Surface and Mid-depth (2)

 

5%-ile of baseline data for surface and middle layer = 6.59 mg L-1

1%-ile of baseline data for bottom layer = 6.42 mg L-1

 

 

 

 

Bottom

Bottom

 

5%-ile of baseline data for bottom layers = 6.58 mg L-1

1%-ile of baseline for bottom layer = 6.42 mg L-1

 

 

 

Depth-averaged Suspended Solids (SS) (3) (4)

95%-ile of baseline data = 7.91 mg L-1

99%-ile of baseline data = 8.96 mg L-1

 

or 120% of control station's SS at the same tide of the same day

or 130% of control station's SS at the same tide of the same day

 

 

 

Depth-averaged Turbidity (Tby) (3) (4)

95%-ile of baseline data = 5.17 NTU

99%-ile of baseline data = 5.72 NTU

 

or 120% of control station's Tby at the same tide of the same day

or 130% of control station's Tby at the same tide of the same day

 

 

 

Notes:

(1)    For DO, non-compliance of the water quality limits occurs when monitoring result is lower than the limits.

(2)    The Action and Limit Levels for DO for Surface & Middle layer were calculated from the combined pool of baseline surface layer data and baseline middle layer data.

(3)    “Depth-averaged” is calculated by taking the arithmetic means of reading of all three depths.

(4)    For turbidity and SS, non-compliance of the water quality limits occurs when monitoring result is higher than the limits.

 

The Action and Limit levels for Zones B to D, which were established based on the results of Baseline Environmental Monitoring Part B.  The Action and Limit Levels of DO and turbidity are derived from the baseline monitoring data for all impact stations for Zones B to D (including Stations F1, C1, C2 and C3), and the results are presented in Table 3.5.  Two sets of the Action and Limit levels of suspended solids were established for two groups of impact monitoring station(s) in the area, namely F1 to monitor the FCZ and C1, C2 as well as C3 to monitor the coral communities (see Table 3.6). 

Table 3.5        Action and Limit Levels of Dissolved Oxygen and Turbidity for Zones B to D

Parameter

Action Level

Limit Level

Dissolved Oxygen (DO) (1)

Surface and Mid-depth (2)

Surface and Mid-depth (2)

 

5%-ile of baseline data for surface and middle layer = 7.22 mg L-1

1%-ile of baseline data for bottom layer =7.12 mg L-1

 

 

 

 

Bottom

Bottom

 

5%-ile of baseline data for bottom layers = 7.14 mg L-1

1%-ile of baseline for bottom layer = 7.05 mg L-1

 

 

 

Depth-averaged Turbidity (Tby) (3) (4)

95%-ile of baseline data = 6.49 NTU

99%-ile of baseline data = 8.35 NTU

 

or 120% of control station's Tby at the same tide of the same day

or 130% of control station's Tby at the same tide of the same day

 

 

 

Notes:

(1)    For DO, non-compliance of the water quality limits occurs when monitoring result is lower than the limits.

(2)    The Action and Limit Levels for DO for Surface & Middle layer were calculated from the combined pool of baseline surface layer data and baseline middle layer data.

(3)    “Depth-averaged” is calculated by taking the arithmetic means of reading of all three depths.

(4)    For turbidity, non-compliance of the water quality limits occurs when monitoring result is higher than the limits.

 

Table 3.6        Action and Limit Levels of Suspended Solids for Impact Stations F1, C1, C2, and C3

Parameter

Action Level

Limit Level

Depth-averaged Suspended Solids (SS)

Station F1

95%-ile of baseline data = 6.89 mg L-1

Station F1

99%-ile of baseline data = 7.11 mg L-1

 

Stations C1, C2 and C3

95%-ile of baseline data = 12.42 mg L-1

Stations C1, C2 and C3

99%-ile of baseline data = 14.28 mg L-1

 

 

 

 

or 120% of control station's SS at the same tide of the same day

or 130% of control station's SS at the same tide of the same day

 

 

 

Notes:

(1)    “Depth-averaged” is calculated by taking the arithmetic means of reading of all three depths.

(2)    Non-compliance of the water quality limits occurs when monitoring result is higher than the limits.

 


3.3.4                                Event and Action Plan

The Event and Action Plan for water quality monitoring which was stipulated in the EM&A Manual is presented in Table 3.7.

Table 3.7       Event Action Plan for Water Quality

Event

Contractor

Action Level Exceedance

Step 1 - repeat sampling event.

Step 2 – identify source(s) of impact and confirm whether exceedance was due to the construction works;

Step 3 – inform EPD, AFCD and LCSD and confirm notification of the non-compliance in writing;

Step 4 - discuss with cable installation contractor the most appropriate method of reducing suspended solids during cable installation (e.g. reduce cable laying speed/volume of water used during installation).

Step 5 - repeat measurements after implementation of mitigation for confirmation of compliance.

Step 6 - if non compliance continues - increase measures in Step 4 and repeat measurements in Step 5.  If non compliance occurs a third time, suspend cable laying operations.

Limit Level Exceedance

Undertake Steps 1-5 immediately, if further non compliance continues at the Limit Level, suspend cable laying operations until an effective solution is identified.


4                                  Impact Monitoring Results

A total of three monitoring events were scheduled between 29 May and 4 June 2009.  All monitoring events at all designated monitoring stations were performed on schedule, ie on 29 May, 30 May and 31 May 2009.

4.1                            Data Collected During Mid-Ebb and/or Mid-Flood Tidal Conditions

The monitoring data taken during the mid-ebb and/or mid-flood tidal conditions are presented in Annex C and compared against the baseline monitoring results in Figures C1 – C12.  The impact monitoring results, except DO, obtained during this week were mostly comparable to the results recorded during the baseline monitoring.  Similar to the results of the previous week, dissolved oxygen levels at all the monitoring stations appeared to be fluctuating and lower than the baseline data.  It should be noted that DO levels measured at all the impact stations were of similar magnitude to DO levels detected at the control stations.  This implies the background levels of DO were also relatively low. 

Depth-averaged turbidity and suspended solids were generally compliant with the Action and Limit Levels with the exception of 29 May 2009.  A review of the above exceedance is discussed in the following section.

4.1.1                      Exceedances for Dissolved Oxygen from 29 May to 31 May 2009

Due to weather constraints, the working vessel had been on a four point mooring in Zone A awaiting safe conditions offshore to progress cable installation operations since the afternoon of 23 May 2009.  No onboard or underwater construction activities had been carried out during the period of 24 May and 29 May 2009.  Neither the injector nor the thrusters were in operation.  However, daily exceedances of Limit Levels for dissolved oxygen were recorded during the water quality monitoring in these six days.

It was concluded in the previous weekly impact report that the recent declining trends of dissolved oxygen and daily DO exceedances could be due to natural fluctuation (ie stratification followed by de-stratification) and such situation may last for a certain period of time due to the unstable weather conditions.

During the cable installation works undertaken in Zones A to E between 30 May and 31 May 2009, exceedances of Action and Limit Levels for dissolved oxygen continued to occur.  Similarly, the DO concentrations measured at all the impact stations were comparable to those recorded at the control stations on 30 May and 31 May 2009.  In addition, non-compliances of DO levels were also noted at the control stations.  This suggests the ambient DO levels were relatively low and DO depletion was first detected in the bottom layer of the water column on 22 May 2009 (see Annex C).  

As seen in Figures D2 and D3 in Annex D, the concentrations of DO were very stable and maintained at steady levels during the marine works on 30 May and 31 May 2009.  Furthermore, DO concentrations measured before the commencement of the cable installation works in Zone B were found to be lower than those recorded during and after the marine works (Figure D3).  Hence, the DO exceedances could be a result of natural fluctuation in DO levels as discussed earlier.

Given no exceedances of turbidity and SS were reported, there were no indications of the pollution sources coming from the Project works area.  The DO exceedances were, therefore, considered unlikely related to the Project works.

It should be noted that although exceedances of the Action and Limit Levels for DO occurred, no non-compliances of the WQOs (ie not less than 2 mg/L for 90% of samples for bottom DO and not less than 4 mg/L for 90% of samples for depth-averaged DO) were reported.

4.1.2                      Exceedances for Depth-averaged Turbidity and Suspended Solids on 29 May 2009

Exceedances of the Action and Limit Levels for Depth-averaged Turbidity and Suspended Solids (SS) were recorded on 29 May 2009 (Table 4.1). 

The Contractor confirmed that the Networker was on a four point mooring in Zone A and no onboard or underwater construction activities had been undertaken throughout the day of 29 May 2009.  Neither the injector nor the thrusters were in operation.

During the mid-flood tide in the morning, the levels of turbidity and suspended solids measured at station B1 exceeded the Limit Levels derived from the baseline data whilst these values were well below 120% of the control station’s turbidity and SS, respectively.  Turbidity and SS levels of station B1 did not show non-compliance during the following mid-ebb tide. 

Exceedances of the Action and Limit Levels for SS were noted at station S2 and S3 during the mid-ebb tide.  The SS level measured at S3 was 0.2 mg/L higher than the 120% of the control station’s SS but less than the Action Level derived from the baseline data.  Similarly, the SS of S2 was 0.6 mg/L above the 130% of the control station’s SS but did not exceed the Limit Level derived from the baseline data.  Although the turbidity level of S2 was not in compliance with the Action and Limit Levels derived from the baseline data, it did not exceed the 120% of turbidity recorded at the control station R1.  It is important to note that turbidity and SS levels of stations S2 and S3 did not show non-compliances during the preceding mid-flood tide.  

It was, therefore, considered that the turbidity and SS exceedances were more likely to be caused by localised factors or temporary tidal influence rather than the Project works.

Table 4.1        Exceedances of Action and Limit Levels for Depth-averaged Turbidity and Suspended Solids on 29 May 2009

Exceedance Log No.

0096120_29 May 09_Turb_E_Station S2

0096120_29 May 09_Turb_F_Station B1

0096120_29 May 09_SS_E_Station S2

0096120_29 May 09_SS_F_Station B1

0096120_29 May 09_SS_E_Station S3

Sampling date

29 May 2009

Monitoring station

B1, S2 and S3

Parameter

Depth-averaged Turbidity (NTU)

Depth-averaged Suspended Solids (SS, mg/L)

Action Levels

Mid-Ebb

Turbidity : 120% of R1 = 8.9 or 5.17 (baseline data)

SS : 120% of R1 = 7.6 or 7.91 (baseline data)

Mid-Flood

Turbidity : 120% of R1 = 6.8 or 5.17 (baseline data)

SS : 120% of R1 = 9.6 or 7.91 (baseline data)

Limit Levels

Mid-Ebb

Turbidity : 130% of R1 = 9.7 or 5.72 (baseline data)

SS : 130% of R1 = 8.2 or 8.96 (baseline data)

Mid-Flood

Turbidity : 130% of R1 = 7.4 or 5.72 (baseline data)

SS : 130% of R1 =10.4 or 8.96 (baseline data)

Measured Levels at Station B1

Mid-Ebb

Turbidity = 3.35

SS = 4.5

 

Mid-Flood

Turbidity = 5.97

SS = 9.5

(exceeds Limit Level)

(exceeds Limit Level)

Measured Levels at Station S2

Mid-Ebb

Turbidity = 6.08

SS = 8.8

(exceeds Limit Level)

(exceeds Limit Level)

Mid-Flood

Turbidity = 4.4

SS = 5.2

 

Measured Levels at Station S3

Mid-Ebb

Turbidity = 5.17

SS = 7.8

 

(exceeds Action Level)

Mid-Flood

Turbidity = 3.85

SS = 5.3

 

 

4.2                            Continuous In-Situ Measurement Data

Continuous in-situ measurements were taken at the impact monitoring stations within the required monitoring zone at 30- to 60- minute intervals (subject to the weather conditions and travelling time between stations) and the results and the graphical presentations were included in Annex D.

In general, the water quality in the vicinity of the Project works was stable and acceptable throughout each sampling day (ie 29 May, 30 May and 31 May 2009) with the exception of some fluctuations in the turbidity levels. 

 

5                                  Environmental Non-CONFORMANCES

5.1                            Summary of Environmental Exceedance

Daily Notification of Exceedances (NOEs) with detailed investigation reports were issued to EPD and AFCD during the monitoring period (ie 29 May to 31 May 2009) for recording water quality monitoring exceedances on dissolved oxygen, turbidity and suspended solids of the monitoring stations.  The exceedances were examined against the Project works.  Results of the detailed investigation indicated that none of the exceedances were attributed to the Project construction works.

5.2                            Summary of Environmental Complaint

No complaints were received during the reporting period.

5.3                            Summary of Environmental Summons and Prosecution

No summons or prosecution on environmental matters were received during the reporting period.

 

6                                  Future Key Issues

6.1                            Key Issues For The Coming Month

As there will be no cable installation works in the following weeks, the impact monitoring will be suspended and the post-project monitoring will take place after the completion of the grout mattress installation at the crossing of Tata’s cable system and HKE's gas pipeline in south east Hong Kong waters.  A pilot study water quality monitoring will be undertaken during the installation of the grout mattress and the results will be presented in the Pilot Study Monitoring Report.

6.2                            Monitoring Schedule For The Coming Month

The post-project monitoring is tentatively scheduled in early July 2009 subject to works progress and weather constraints.  The water sampling will be conducted at the same monitoring location as in this reporting week.

 

7                                  Conclusions

This Weekly Impact Monitoring Report presents the EM&A work undertaken during the period from 29 May to 4 June 2009 in accordance with the EM&A Manual and the requirements under FEP-01/294/2007.

Daily exceedances of Action and Limit Levels for dissolved oxygen were recorded on the three monitoring events (ie 29 May, 30 May and 31 May 2009).  Depth-averaged turbidity and suspended solids were generally compliant with the Action and Limit Levels with the exception of 29 May 2009.  Results of the detailed investigation indicated that none of the exceedances were attributed to the Project construction works.

No complaints and summons/prosecution were received during the reporting week.

The MT will keep track of the EM&A programme to verify compliance of environmental requirements and the proper implementation of all necessary mitigation measures.

 



([1])         Hong Kong Observatory (2009) http://www.hko.gov.hk/tide/eWLtide.htm