Contents

Executive Summary                                                                                     

1                      introduction                                                                          

1.1                   Purpose of the Report                                                     

1.2                   Structure of the Report                                                

2                      Project Information                                                          

2.1                   Background                                                                           

2.2                   Marine Construction Works Undertaken during Reporting Week      

2.3                   Status of Environmental Approval Documents

3                      Water Quality Monitoring Requirements                

3.1                   Monitoring Locations                                                        

3.2                   Monitoring Parameters and Frequency                 

3.3                   Monitoring Equipment and Methodology               

4                      Impact Monitoring Results                                             

4.1                   Data Collected During Mid-Ebb and/or Mid-Flood Tidal Conditions     

4.2                   Continuous In-Situ Measurement Data                     

5                      Environmental Non-CONFORMANCES                          

5.1                   Summary of Environmental Exceedance                

5.2                   Summary of Environmental Complaint                    

5.3                   Summary of Environmental Summons and Prosecution

6                      Future Key Issues                                                                 

6.1                   Key Issues For The Coming Week                                   

6.2                   Monitoring Schedule For The Coming WEEK           

7                      Conclusions                                                                           

 


LIST OF TABLES

Table 2.1        Summary of Marine Works Undertaken During the Reporting Week

Table 2.2        Summary of Environmental Licensing, Notification, Permit and Reporting Status

Table.3.1        Co-ordinates of Starting Points and Ending Points for Zone A (HK Grid)

Table 3.2        Co-ordinates of All Monitoring Stations in Zone A (HK Grid)

Table 3.3        Monitoring Frequency and Parameters for Impact Monitoring

Table 3.4        Action and Limit Levels of Water Quality for Zone A

Table 3.5       Event Action Plan for Water Quality

Table 4.1       Summary of Exceedances occurring during the Reporting Week

 

LIST OF FIGURES

Figure 2.1       The Route of the Proposed Cable System

 

 

LIST OF ANNEXES

Annex A

Impact Monitoring Schedule

Annex B

QA/QC Results of Laboratory Testing for Suspended Solids

Annex C

Impact Water Quality Monitoring Results

Annex D

Continuous In-situ Measurement Data

 

Executive Summary

The construction works for the VSNL Intra Asia Submarine Cable System – Deep Water Bay commenced on 16 March 2009.  This is the seventh Weekly Impact Monitoring Report presenting the impact water quality monitoring conducted during the period from 31 July to 6 August 2009 in accordance with the EM&A Manual.

Summary of Construction Works undertaken during the Reporting Period

The barge “Challenger II” had been anchored in Deep Water Bay since 24 July, when marine works commenced.  During the reporting period cable repair operations continued, with initial and final splicing of the cable, re-laying of the cable on the sea bed and installation of some split pipes.  Marine works were temporarily suspended in the afternoon on 3 August due to a typhoon warning, and due to this weather did not resume again until 5 August.

Water Quality

For the impact monitoring, six monitoring events were scheduled between 31 July and 6 August 2009.  Aside from the 4 August, when a typhoon warning stopped marine works, monitoring events at all designated monitoring stations were performed on schedule, ie five events took place on 31 July, 1 August, 3 August, 5 August and 6 August 2009.

Environmental Non-conformance

Daily exceedances of Action and Limit Levels for dissolved oxygen were recorded during the reporting period.  Depth-averaged turbidity was in general compliant with the Action and Limit Levels aside from on 1 August, when Station S3 recorded an Action Level exceedance.  Depth-averaged suspended solids exceeded Action Levels on one day (1 August, at Station B1) and both Action and Limit Levels on one day (6 August, at Station B1).  Results of detailed investigations into these exceedances indicated that none of them were attributed to the Project construction works.

No complaints were received during the reporting week.

No environmental summons/prosecution were received during the reporting week.

Future Key Issues

During the coming week, the repair of the cable will continue including jetting works and installation of articulated pipes.

 


1                                            introduction

ERM-Hong Kong, Limited (ERM) was appointed by Tata Communications (Bermuda) Ltd (formerly Videsh Sanchar Nigam Limited (VSNL)) as the Monitoring Team (MT) to implement the Environmental Monitoring and Audit (EM&A) programme for the VSNL Intra Asia Submarine Cable System – Deep Water Bay (thereinafter called the (‘Project’)).

1.1                                      Purpose of the Report

This is the seventh Weekly Impact Monitoring Report, which summarises the impact monitoring results and audit findings for the EM&A programme during the reporting period from 31 July to 6 August 2009.

1.2                                      Structure of the Report

The structure of the report is as follows:

Section 1 :  Introduction

Details the background, purpose and structure of the report.

 

Section 2 :  Project Information

Summarises background and scope of the project, the construction works undertaken and the status of Environmental Permits/Licenses during the reporting period.

 

Section 3 :  Water Quality Monitoring Requirements

Summarises the monitoring parameters, monitoring programmes, monitoring methodologies, monitoring frequency, monitoring locations, Action and Limit Levels, and Event / Action Plans.

 

Section 4 :  Impact Monitoring Results

Summarises the monitoring results obtained in the reporting period.

 

Section 5 :  Environmental Non-conformance

Summarises any monitoring exceedances, environmental complaints and environmental summons within the reporting period.

 

Section 6 :  Future Key Issues

Summarises the monitoring schedule for the next week.

 

Section 7 :  Conclusions

Presents the key findings of the impact monitoring results.

 

 

2                                            Project Information

2.1                                      Background

Tata Communications (Bermuda) Ltd (formerly Videsh Sanchar Nigam Limited (VSNL)) proposes to install a submarine telecommunications cable, which will run from Deep Water Bay and through southeast Hong Kong offshore waters.  The cable landing site will be at the western edge of Deep Water Bay beach at an existing cable landing manhole location.  From Deep Water Bay, the cable will extend southwards towards the East Lamma Channel.  Near to Round Island, the cable will turn approximately parallel to the East Lamma Channel passing to the south of Po Toi Island.  The cable will then run eastward close to the boundary of HKSAR waters and then out beyond Hong Kong territorial waters into the South China Sea.  At the southeast offshore waters, it will be necessary to install a grout mattress to protect the cable where it crosses Hong Kong Electric Co., Ltd’s (HKE) gas pipeline.  A map of the proposed cable route is presented in Figure 2.1.

In August 2007, a Project Profile (PP) included an assessment of the potential environmental impacts associated with the installation of the submarine cable circuit was prepared and submitted to the Environmental Protection Department (EPD) under section 5.(1)(b) and 5.(11) of the Environmental Impact Assessment Ordinance (EIAO) for application for Permission to apply directly for an Environmental Permit (EP).  The Environmental Protection Department, subsequently issued an Environmental Permit (EP-294/2007) and Further Environmental Permit (FEP-01/294/2007).  Amendments to the permitting requirements were incorporated into the Environmental Permit to address potential environmental impacts associated with cable crossings over the HKE’s gas pipeline in southeast Hong Kong waters.  Under the requirements of Condition 3 of the EP, an EM&A programme as set out in the Environmental Monitoring and Audit Manual (EM&A Manual) is required to be implemented.  In accordance with the EM&A Manual, impact monitoring of water quality is required for the Project.

Baseline Monitoring was conducted near Deep Water Bay (ie Zones A and E) between 27 February 2009 and 9 March 2009 and the results were presented in the Baseline Water Quality Monitoring Report Part A.  Baseline monitoring for the Po Toi section of works was undertaken from 27 February 2009 to 13 March 2009 and the Baseline Water Quality Monitoring Report Part B presented the results of the monitoring data for Zones B to D near Po Toi Island.

Impact Monitoring has been carried out at Deep Water Bay (ie Zone A) since 25 March 2009.  The barge “CB Networker” completed the cable installation works in Hong Kong waters on 2 June 2009 and the water quality monitoring was suspended subsequently.

A cable fault has recently been identified in the previously laid submarine telecommunications cable in Zone A.  Hence, the marine works of this Project have been resumed on 24 July 2009 to locate the cable fault and replace the cable.  This report presents results of the data from monitoring stations in Zone A during cable repair works.  Results of the impact monitoring data will therefore be compared against the results of the Baseline Environmental Monitoring Part A.

2.2                                      Marine Construction Works Undertaken during Reporting Week

During the reporting period, the cable repair barge “Challenger I” continued cable repair works.  A summary of the major works undertaken during the reporting period is shown in Table 2.1.

Table 2.1        Summary of Marine Works Undertaken During the Reporting Week

Date

Works Area

Activity

31 July 2009

Zone A

De-burial and recovery of cable.  Start initial splicing of cable.

1 August 2009

Zone A

Completion of initial cable splice. Re-laying of cable. Recovery of further section of cable and removal of some split pipes.  Start of final splicing of cable.

2 August 2009

Zones A

Finalisation of final splicing and cable testing.  Diver inspection.  No jetting or water pumping works.

3 August 2009

Zones A

Deployment of final splice/final bight to the water.  Work suspended in the mid-afternoon due to typhoon warning.  Barge ‘Challenger I’ demobilized from Deep Water Bay to To Kwa Wan typhoon shelter.

4 August 2009

Zones A

Work suspended due to typhoon warnings.

5 August 2009

Zone A

Re-mobilization of ‘Challenger I’ barge to Deep Water Bay.  Installation of split pipes in the late afternoon..

6 August 2009

Zone A

Further installation of split pipes.

 

2.3                                      Status of Environmental Approval Documents

A summary of the relevant permits, licences, notifications and/or reports on environmental protection for this Project is presented in Table 2.2.


Table 2.2        Summary of Environmental Licensing, Notification, Permit and Reporting Status

Permit / Licence / Notification / Report

Reference

Validity Period

Remarks

Environmental Permit

(EP-294/2007)

Throughout the construction period

 

Granted on 23 November 2008

Further Environmental Permit

(FEP-01/294/2007)

Throughout the construction period

 

Granted on 9 July 2008

EM&A Manual

-

Throughout the construction period

 

Approved by EPD on 12 March 2009

Baseline Water Quality Monitoring Report (Part A)

-

Throughout the construction period for Zones A and E

Approved by EPD on 1 April 2009

Baseline Water Quality Monitoring Report (Part B)

-

Throughout the construction period for Zones B to D

Approved by EPD on 30 April 2009

Pre Installation Geophysical Survey Report

-

Throughout the construction period for the Grout Mattress Installation

Accepted by AFCD and EPD on 7 July 2009


3                                            Water Quality Monitoring Requirements

3.1                                      Monitoring Locations

In accordance with the EM&A Manual, during all marine works relating to the cable, water quality sampling was undertaken at stations situated around the cable works at Deep Water Bay (ie Zone A).  This meant water quality sampling was undertaken throughout the reporting period at the following stations.

·            S1 and S2, situated at the two Seawater Intake Points in Deep Water Bay.  They are within 500 m west/northwest of the cable alignment at Deep Water Bay for monitoring the effect of cable laying works in the area;

·           S3, a Sensitive Receiver used to monitor the water quality condition of the Coastal Protection Areas at Middle Island;

·           B1, an Impact Station used to monitor the effect of the construction activities on Deep Water Bay Beach;

·           R1, a Control Station for S1, S2, S3 and B1 at Deep Water Bay which is not supposed to be influenced by the cable repair works due to its remoteness from the cable construction works;

The co-ordinates of Zone A and the above monitoring stations are listed in Table.3.1 and Table 3.2, respectively.

Table.3.1        Co-ordinates of Starting Points and Ending Points for Zone A (HK Grid)

Zone

Starting Point

Ending Point

Easting

Northing

Easting

Northing

A

837029.763

811601.699

836367.572

810545.975

Table 3.2        Co-ordinates of All Monitoring Stations in Zone A (HK Grid)

Station

Nature            

Corresponding Control Station

Easting

Northing

S1

Seawater Intakes

R1

836538.669

811528.535

S2

Seawater Intakes

R1

836195.047

810956.409

S3

Coastal Protection Areas

R1

836677.103

810666.744

B1

Gazetted Beach

R1

837241.114

811498.400

R1

Control Station

-

835951.109

809052.535

 

3.2                                      Monitoring Parameters and Frequency

The impact water quality monitoring was conducted in accordance with the requirements stated in the EM&A Manual.  These are presented below.

3.2.1                                Monitoring Parameters

Parameters measured in situ were:

·            dissolved oxygen (DO) (% saturation and mg L-1);

·            temperature (°C);

·            turbidity (NTU); and

·            salinity (‰).

The only parameter measured in the laboratory was:

·           suspended solids (SS) (mgL-1).

In addition to the water quality parameters, other relevant data were measured and recorded in field logs, including the location of the sampling stations, water depth, time, weather conditions, sea conditions, tidal state, special phenomena and work activities undertaken around the monitoring and works area that may influence the monitoring results.

3.2.2                                Monitoring Frequency

Impact Monitoring at S1, S2, S3, B1 and R1 took place when the cable repair works were undertaken within 500 m (Zone A) of monitoring stations S1, S2, S3 and B1, which was throughout the reporting period.  .

Impact monitoring was carried out during the barge operating hours, normally covering both mid-flood and mid-ebb tidal conditions, until water quality monitoring was not required.

In-situ and SS data of the control and impact stations within the impact zone were collected daily during mid-flood and mid-ebb tidal states (Table 3.3), unless the mid-ebb tide and/or the mid-flood tide were not occurring during the monitoring period.  In addition, continuous in-situ measurements were taken at the impact monitoring stations, ie B1 & S1-3, at 30- to 60- minute intervals (subject to the weather conditions and travelling time between stations) within Zone A.  The monitoring frequency and parameters for Impact Monitoring are summarised in Table 3.3.

Table 3.3        Monitoring Frequency and Parameters for Impact Monitoring

Zone

Station Type

Monitoring Station

Monitoring Frequency

Monitoring Parameter

Mid-ebb Tide / Mid-flood Tide

30- to 60- Minute Interval

A

Control

R1

Daily when cable installation works undertaken in Zone A

Temperature, Turbidity, Salinity, DO, SS

-

Impact

S1, S2, S3 and B1

Temperature, Turbidity, Salinity, DO

3.3                                      Monitoring Equipment and Methodology

3.3.1                                Monitoring Equipment

Dissolved Oxygen, Temperature, Salinity, Turbidity Measuring Equipment

The instrument was a portable, weatherproof multi-parameter measuring instrument (YSI 6820) complete with cables, multi-probe sensor, comprehensive operation manuals, and was operable from a DC power source.  It was capable of measuring:

·            dissolved oxygen levels in the range of 0 – 50 mg L-1; and 0-500% saturation;

·            temperature of -5 to 50 °C;

·            turbidity levels between 0-1000 NTU (response of the sensor was checked with certified standard turbidity solutions before the start of measurement); and,

·            salinity in the range of 0-40 ppt (checked with 30 ppt Salinity solutions before the start of the measurement).

Water Depth Gauge

The water depth gauge affixed to the bottom of the water quality monitoring vessel was used.

Current Velocity and Direction

Current velocity and direction was estimated by conducting float tracking.

Positioning Device

A Global Positioning System (GPS) was used (C-Navigator World DGPS, GPS 72A) during monitoring to ensure the accurate recording of the position of the monitoring vessel before taking measurements.  The use of DGPS was used for positioning device, which was well calibrated at an appropriate checkpoint.

Water Sampling Equipment

Water samples for suspended solids measurement were collected by the use of a multi-bottle water sampling system (General Oceanics Inc., Rosette Sampler ROS02), consisting of PVC bottles of more than two litres, which could be effectively sealed with cups at both ends.  The water sampler had a positive latching system to keep it open and prevent premature closure until released by a messenger when the sampler was at the selected water depth.

3.3.2                                Monitoring Methodology

Timing & Frequency

In-situ and SS data were collected daily at both control and impact stations in Zone A, provided that the monitoring period had covered the mid-flood tide and/or mid-ebb tide.  The water quality sampling was undertaken within a 3 hour window of 1.5 hours before and 1.5 hours after mid-flood and mid-ebb tides.  Tidal range for flood and ebb tides was not less than 0.5 m for capturing representative tides.  Continuous In-situ measurements were taken at 30- to 60- minute intervals (subject to the weather conditions and travelling time between stations) for each impact station within Zone A.

Reference was made to the predicted tides at Waglan Island, which is the tidal station nearest to the Project site, published on the website of Hong Kong Observatory([1]).  Based on the predicted water levels at Waglan Island, the impact water quality monitoring was conducted following the schedule presented in Annex A.

Duplicate samples were collected from each of the monitoring events for in situ measurements and laboratory analysis.

Depths

Each station was sampled and measurements were taken at three depths, 1 m below the sea surface, mid depth and 1m above the sea bed.

Protocols

The multi-parameter measuring instrument (YSI 6820) was checked and calibrated by an HOKLAS accredited laboratory before use.  Onsite calibration was also carried out to check the responses of sensors and electrodes using certified standard solutions before each use.  Sufficient stocks of spare parts were maintained for replacements when necessary, and backup monitoring equipment was made available.

Water samples for SS measurements were collected in high density polythene bottles, packed in ice (cooled to 4° C without being frozen), and delivered to an HOKLAS accredited laboratory as soon as possible after collection.

Laboratory Analysis

All laboratory work was carried out by a HOKLAS accredited laboratory.  Water samples of about 1,000 mL were collected at the monitoring and control stations for carrying out the laboratory determinations.  The determination work started within the next working day after collection of the water samples.  The analyses followed the standard methods as described in APHA Standard Methods for the Examination of Water and Wastewater, 19th Edition, unless otherwise specified (APHA 2540D for SS).

The QA/QC details were in accordance with requirements of HOKLAS or another internationally accredited scheme (for details refer to Annex B).

3.3.3                                Action and Limit Levels

The Action and Limit levels for Zone A, which were established based on the results of Baseline Environmental Monitoring Part A, are presented in Table 3.4.

Table 3.4        Action and Limit Levels of Water Quality for Zone A

Parameter

Action Level

Limit Level

Dissolved Oxygen (DO) (1)

Surface and Mid-depth (2)

Surface and Mid-depth (2)

 

5%-ile of baseline data for surface and middle layer = 6.59 mg L-1

1%-ile of baseline data for bottom layer = 6.42 mg L-1

 

 

 

 

Bottom

Bottom

 

5%-ile of baseline data for bottom layers = 6.58 mg L-1

1%-ile of baseline for bottom layer = 6.42 mg L-1

 

 

 

Depth-averaged Suspended Solids (SS) (3) (4)

95%-ile of baseline data = 7.91 mg L-1

99%-ile of baseline data = 8.96 mg L-1

 

or 120% of control station's SS at the same tide of the same day

or 130% of control station's SS at the same tide of the same day

 

 

 

Depth-averaged Turbidity (Tby) (3) (4)

95%-ile of baseline data = 5.17 NTU

99%-ile of baseline data = 5.72 NTU

 

or 120% of control station's Tby at the same tide of the same day

or 130% of control station's Tby at the same tide of the same day

 

 

 

Notes:

(1)    For DO, non-compliance of the water quality limits occurs when monitoring result is lower than the limits.

(2)    The Action and Limit Levels for DO for Surface & Middle layer were calculated from the combined pool of baseline surface layer data and baseline middle layer data.

(3)    “Depth-averaged” is calculated by taking the arithmetic means of reading of all three depths.

(4)    For turbidity and SS, non-compliance of the water quality limits occurs when monitoring result is higher than the limits.

3.3.4                               Event and Action Plan

The Event and Action Plan for water quality monitoring which was stipulated in the EM&A Manual is presented in Table 3.5.

Table 3.5        Event Action Plan for Water Quality

Event

Contractor

Action Level Exceedance

Step 1 - repeat sampling event.

Step 2 – identify source(s) of impact and confirm whether exceedance was due to the construction works;

Step 3 – inform EPD, AFCD and LCSD and confirm notification of the non-compliance in writing;

Step 4 - discuss with cable installation contractor the most appropriate method of reducing suspended solids during cable installation (e.g. reduce cable laying speed/volume of water used during installation).

Step 5 - repeat measurements after implementation of mitigation for confirmation of compliance.

Step 6 - if non compliance continues - increase measures in Step 4 and repeat measurements in Step 5.  If non compliance occurs a third time, suspend cable laying operations.

Limit Level Exceedance

Undertake Steps 1-5 immediately, if further non compliance continues at the Limit Level, suspend cable laying operations until an effective solution is identified.


4                                            Impact Monitoring Results

For the impact monitoring, six monitoring events were scheduled between 31 July and 6 August 2009.  Aside from the 4 August, when a typhoon warning stopped marine works, monitoring events at all designated monitoring stations were performed on schedule, ie five events took place on 31 July, 1 August, 3 August, 5 August and 6 August 2009.

4.1                                      Data Collected During Mid-Ebb and/or Mid-Flood Tidal Conditions

Daily monitoring events were scheduled between 31 July and 6 August 2009 at Deep Water Bay (ie Zone A).  The monitoring data taken during the mid-ebb and/or mid-flood tidal conditions for Zone A are presented in Annex C and compared against the baseline monitoring results in Figures C1-C4, Annex C.  A summary of the exceedances is presented in Table 4.1.

Table 4.1       Summary of Exceedances occurring during the Reporting Week

 

 

Exceedance of Action and Limit Levels found at the Impact Monitoring Stations in Zone A:

Date

Parameter

Mid-Ebb Tide

Mid-Flood Tide

31 July 2009

DO (Bottom)

S1, S2, S3

n/a

1 August 2009

DO (Bottom)

S1, S2, S3, B1

n/a

 

DO (Depth-averaged)

S1, S2, S3, B1

n/a

 

Turbidity (Depth-averaged)

S3*

n/a

 

SS (Depth-averaged)

B1*

n/a

3 August 2009

DO (Bottom)

S1, S2, S3, B1

S1, S3

 

DO (Depth-averaged)

S3, B1

None

4 August 2009

 

n/a

n/a

5 August 2009

DO (Bottom)

n/a

S1, S2, S3, B1

 

DO (Depth-averaged)

n/a

S1, S2, S3, B1

6 August 2009

DO (Bottom)

S1, S2, S3, B1

S1, S2, S3, B1

 

DO (Depth-averaged)

S1, S2, S3, B1

S1, S2, S3, B1

 

SS (Depth-averaged)

None

B1

Note:

* Action Level but not Limit Level exceedance

n/a indicates that no sampling was taken at that tide (due to it falling outside working hours, or due to weather conditions). 

None means there was no exceedance for that parameter

4.1.1                                Exceedances for Dissolved Oxygen from 31 July to 6 August 2009

Except for 4 August, when no marine works and hence no monitoring took place, exceedances of the Action and Limit Levels for Dissolved Oxygen (DO) were recorded daily throughout the reporting period for bottom DO (DOB) and on all but one day for depth averaged DO (31 July 2009) (Table 4.1).

It is observed that DO trends fluctuate widely.  Similar to the results of the previous months, DOB concentrations at all the monitoring stations appeared to be lower than the baseline data, with the exception of Station B1 on 31 July.  It should be noted however that the DO levels recorded at all the impact stations were predominantly higher than, if not comparable to the DO measured at the control station R1.  Daily exceedances of Action and Limit Levels set from baseline data for DOB were observed not only at the impact monitoring stations but also at the control station.  All this implies that the background levels of DO were also relatively low.

It was concluded in previous weekly reports that the recent declining trends of dissolved oxygen and daily DO exceedances could be due to seasonal variation such as stratification occurring during the summer.  Warmer summer water temperatures speed up the uptake of oxygen through respiration by living organisms and decomposition of organic matter in the water column and sediments.  As a result, the replenishment of dissolved oxygen is less than the DO consumption leading to depletion in dissolved oxygen concentrations during the summer months. 

Also, for DO, critical conditions usually occur within the bottom waters during the summer months when the water column is stratified, with a warmer surface layer separated from deeper water by a picnocline, or density gradient.  When the density gradient within the picnocline is high, transport of oxygen from the aerated surface waters to the lower waters by mixing is significantly reduced.  Dissolved oxygen levels could also decrease in the bottom layer because photosynthesis and contact with the air may be significantly reduced.  This phenomenon is supported for the reporting week by the fact that in general DOB concentrations were lower than DO concentrations measured at the surface and mid-depth from 31 July to 6 August 2009.

At the beginning of the reporting week, the weather was sunny and hot (high solar radiation) which would favour the aforementioned thermal stratification.  Later in the week however a typhoon warning was issued and heavy rain followed.  It is believed that the thermocline would have been broken up by the heavy rain, leading to mixing of the oxygen deficient bottom waters and the slightly oxygen-richer surface waters.   The already reduced oxygen levels could be further depleted through the decomposition of organic matter washed into the marine waters during the rainstorm.  There is the potential for all DO present in the water to be rapidly removed for satisfying the oxygen demand resulting in further oxygen depletion throughout the water column in the subsequent days.  This is supported by the fact that there were exceedances at all Stations for both DOB and DO depth-averaged in the latter half of the week, while at the start of the week, some Stations still fell within the Limits.

It is important that although exceedances of the Action and Limit Levels for DO occurred, no-non-compliances of the Water Quality Objectives (ie not less than 2 mg/L for 90% of samples for bottom DO and not less than 4 mg/L for 90% of samples for depth-averaged DO) were reported.

A review of the monitoring data compared to the works practices similarly concluded that all DO exceedances are unlikely to be caused by the Project due to the fact that the marine works undertaken were diver hand jetting operations inside an enclosed silt curtain and hence these construction activities were not expected to cause decreases in the DO levels.

In view of all of the above, the DO exceedances were considered unlikely to be related to the Project works.

4.1.2                                Exceedance for Turbidity on 1 August 2009

An exceedance of the Action Level for Depth-averaged turbidity was recorded during the mid-ebb tide on 1 August 2009 at Station S3 (Table 4.1).  Upon investigation, the exceedance was considered unlikely to be related to the Project works for the following reasons:

·            During the mid-ebb tide, the turbidity level measured at Station S3 was slightly higher than the Action Level derived from the baseline data but it was well below 120% of the Control Station’s turbidity.

·            At the time of monitoring, there were no marine construction works being carried out.  A diver did go into the water to undertake inspection works, but this would have been unlikely to have disturbed the sea bed.

·            Station B1 was closer to the construction barge than S3, but the turbidity level measured at B1 (4.78 NTU) was lower than that measured at S3 (5.55 NTU).  Both stations were downstream of the construction barge.

4.1.3                                Exceedances for Depth-averaged Suspended Solids on 1 & 6 August 2009

An exceedance of the Action and Limit Levels for Depth-averaged Suspended Solids (SS) was recorded on one day (6 August) and an exceedances of Action Levels but not Limit Levels on one further day (1 August).  Both exceedances occurred at Station B1 (Table 4.1).

A review of the monitoring data and work practices concluded that all SS exceedances are unlikely to be caused by the Project due to the following:

·            At the time of monitoring, no marine works were being carried out that were likely to have disturbed the seabed; in one case, there was no marine works occurring and in the other, a diver was in the water inspecting newly laid split pipes.

·            The SS level at Station B1 did not show non-compliance during the previously measured mid-ebb or mid-flood tide.

·            On 6 August Station B1 was upstream of the marine cable works, while at sampling Stations downstream of the marine cable works, no SS exceedances were recorded.

·            The depth-averaged turbidity measured at B1 at the same mid-ebb or mid-flood tide was within its respective Action and Limit Levels.

It was, therefore, considered that the SS exceedances were more likely to be caused by localised factors or temporary tidal influence rather than the Project works.

4.2                                      Continuous In-Situ Measurement Data

Continuous in-situ measurements were taken at the impact monitoring stations within the required monitoring zone at 30- to 60- minute intervals (subject to the weather conditions and travelling time between stations) and the results and the graphical presentations were included in Annex D.

In general, the water quality in the vicinity of the Project works was stable and acceptable throughout each sampling day (31 July to 6 August) with the exception of some slight fluctuations in depth-averaged turbidity.

 

5                                            Environmental Non-CONFORMANCES

5.1                                      Summary of Environmental Exceedance

Daily Notification of Exceedances (NOEs) with detailed investigation reports were issued to EPD and AFCD during the monitoring period (ie 31 July to 6 August 2009) for recording water quality monitoring exceedances on dissolved oxygen, turbidity and suspended solids of the monitoring stations.  The exceedances were examined against the Project works.  Results of the detailed investigation indicated that none of the exceedances were attributed to the Project construction works.

5.2                                      Summary of Environmental Complaint

No complaints were received during the reporting period.

5.3                                      Summary of Environmental Summons and Prosecution

No summons or prosecution on environmental matters were received during the reporting period.

 

6                                            Future Key Issues

6.1                                      Key Issues For The Coming Week

During the following week, the repair of the cable will continue including jetting works and installation of articulated pipes.

6.2                                      Monitoring Schedule For The Coming WEEK

The tentative schedule of water quality monitoring for the coming week is presented in Annex A.  Since marine works are predicted to be complete by 11 August, the schedule for the coming week runs from 7 to 11 August.  The water sampling will be conducted at the same monitoring locations as in this reporting period.  However, the tentative schedule of the water quality monitoring is subject to continued operational progress and weather constraints.

 

7                                            Conclusions

This Weekly Impact Monitoring Report presents the EM&A work undertaken during the period from 31 July to 6 August 2009 in accordance with the EM&A Manual and the requirements under FEP-01/294/2007.

There were daily exceedances of Action and Limit Levels for dissolved oxygen, both bottom layer (on all days) and depth-averaged (on all days except 31 July).  There were only two exceedances of suspended solids, both at Station B1, once on 1 August (Action Level only) and once on 6 August.  Depth-averaged turbidity was compliant with Action and Limit levels throughout the reporting period, with the exception of one Action Level exceedance at Station S3 on 1 August.  Results of detailed investigations have indicated that none of the mentioned exceedances were attributed to the Project construction works.

No complaints and summons/prosecution were received during the reporting week.

The MT will keep track of the EM&A programme to verify compliance of environmental requirements and the proper implementation of all necessary mitigation measures.



([1])         Hong Kong Observatory (2009) http://www.hko.gov.hk/tide/eWLtide.htm