Contents

Executive Summary                                                                                     

1                      introduction                                                                          

1.1                   Purpose of the Report                                                     

1.2                   Structure of the Report                                                

2                      Project Information                                                          

2.1                   Background                                                                           

2.2                   Site Description                                                                     

2.3                   Status of Environmental Approval Documents

3                      Water Quality Monitoring Requirements                

3.1                   Monitoring Locations                                                        

3.2                   Monitoring Parameters and Frequency                 

3.3                   Monitoring Equipment and Methodology               

4                      IMPLEMENTATION STATUS OF ENVIRONMENTAL MITIGATION measures  

5                      Post-Project Monitoring Results                              

5.1                   Deep Water Bay Area                                                         

5.2                   Po Toi Area                                                                               

6                      Conclusions                                                                           

 


LIST OF TABLES

Table 2.1        Summary of Environmental Licensing, Notification, Permit and Reporting Status

Table.3.1        Co-ordinates of Starting Points and Ending Points for Zones A to E (HK Grid)

Table 3.2        Co-ordinates of All Monitoring Stations in Deep Water Bay area (Zones A and E) (HK Grid)

Table 3.3        Co-ordinates of All Monitoring Stations in Po Toi area (Zones B to D) (HK Grid)

Table 3.4        Monitoring Frequency and Parameters for Post Project Monitoring

 

LIST OF ANNEXES

 

Annex A

Impact Monitoring Schedule

Annex B

QA/QC Results of Laboratory Testing for Suspended Solids

Annex C

Impact Water Quality Monitoring Results – Deep Water Bay Area

Annex D

Impact Water Quality Monitoring Results – Po Toi Area

Annex E

Seasonal Variation of Turbidity and Suspended Solids Levels 1998-2007

 

 

Executive Summary

The cable installation works for the VSNL Intra Asia Submarine Cable System – Deep Water Bay commenced on 16 March 2009 and were completed on 11 August 2009.  Following this, Post Lay Inspection and Burial (PLIB) works commenced on 28 August 2009 and were completed on 30 August 2009 within Zone A but were ongoing outside Monitoring Zones A to E until 14 September 2009.  This is the Post-Project Environmental Monitoring and Audit (EM&A) Report presenting the results of the Post-project Monitoring carried out from 21 September to 5 October 2009 in accordance with the EM&A Manual.

Water Quality

Six monitoring events were originally scheduled between 21 and 28 September 2009 but due to bad weather at Po Toi the schedule was updated and monitoring events at all designated monitoring stations were conducted at Deep Water Bay (Zones A and E) on 21, 23 and 25 September and at Po Toi (Zones B to D) on 22, 26 September and 5 October 2009.

In general, the dissolved oxygen levels recorded during the reporting week were mostly comparable to the results obtained during the baseline monitoring period.  In general, turbidity and suspended solid levels show seasonal variation, with levels in September/October being higher than those in February/March (when baseline monitoring was carried out).  Hence turbidity and suspended solids levels recorded during the reporting period were, in general, slightly higher than those obtained during the baseline monitoring period.

Conclusion

The overall water quality at Deep Water Bay and Po Toi after the completion of the Project was found to be similar to that before the commencement of the Project works, taking into account seasonal variations.  It is concluded that no deterioration of water quality was observed other than natural fluctuation or seasonal variation and hence the impact of the Project works on the water quality at the Project sites is considered to be negligible.

 


1                                            introduction

ERM-Hong Kong, Limited (ERM) was appointed by Tata Communications (Bermuda) Ltd (formerly Videsh Sanchar Nigam Limited (VSNL)) as the Monitoring Team (MT) to implement the Environmental Monitoring and Audit (EM&A) programme for the VSNL Intra Asia Submarine Cable System – Deep Water Bay (thereinafter called the (‘Project’)).

1.1                                      Purpose of the Report

This is the Post-Project EM&A Report, which summarises the post-Project Monitoring results and audit findings for the EM&A programme during the reporting period from 21 September to 5 October 2009.  The post-Project monitoring results are used to compare with the Baseline and Impact monitoring results in order to investigate the impact of the project works on the water quality in the vicinity of the project sites at Deep Water Bay (Zones A and E) and Po Toi (Zones B to D).

1.2                                      Structure of the Report

The structure of the report is as follows:

Section 1 :  Introduction

Details the background, purpose and structure of the report.

 

Section 2 :  Project Information

Summarises background and scope of the project, the construction works undertaken and the status of Environmental Permits/Licenses during the reporting period.

 

Section 3 :  Water Quality Monitoring Requirements

Summarises the monitoring locations, parameters and frequency and monitoring equipment and methodologies.

 

Section 4 :  Implementation Status on Environmental Mitigation Measures

Summarises the implementation of environmental protection measures during the reporting period.

 

Section 5 :  Post Project Monitoring Results

Summarises the monitoring results obtained in the reporting period for A) The Deep Water Bay area (Zones A and E) and B) The Po Toi area (Zones B to D).

 

Section 6 :  Conclusions

Presents the key findings of the post Project monitoring results.

 

2                                            Project Information

2.1                                      Background

Tata Communications (Bermuda) Ltd (formerly Videsh Sanchar Nigam Limited (VSNL)) has installed a submarine telecommunications cable, which runs from Deep Water Bay and out through southeast Hong Kong offshore waters.  The cable landing site is at the western edge of Deep Water Bay beach at an existing cable landing manhole location.  From Deep Water Bay, the cable extends southwards towards the East Lamma Channel.  Near to Round Island, it turns approximately parallel to the East Lamma Channel passing to the south of Po Toi Island.  The cable then runs eastward close to the boundary of HKSAR waters and then out beyond Hong Kong territorial waters into the South China Sea.  At the southeast offshore waters, it is necessary to install a grout mattress to protect the cable where it crosses Hong Kong Electric Co., Ltd’s (HKE) gas pipeline.  A map of the proposed cable route is presented in Figure 2.1.

In August 2007, a Project Profile (PP) including an assessment of the potential environmental impacts associated with the installation of the submarine cable circuit was prepared and submitted to the Environmental Protection Department (EPD) under section 5.(1)(b) and 5.(11) of the Environmental Impact Assessment Ordinance (EIAO) for application for Permission to apply directly for an Environmental Permit (EP).  The Environmental Protection Department, subsequently issued an Environmental Permit (EP-294/2007) and Further Environmental Permit (FEP-01/294/2007).  Amendments to the permitting requirements were incorporated into the Environmental Permit to address potential environmental impacts associated with cable crossings over the HKE’s gas pipeline in southeast Hong Kong waters.  Under the requirements of Condition 3 of the EP, an EM&A programme as set out in the Environmental Monitoring and Audit Manual (EM&A Manual) is required to be implemented.  In accordance with the EM&A Manual, impact monitoring of water quality was required for the Project.

Baseline Monitoring was conducted near Deep Water Bay (Zones A and E) between 27 February 2009 and 9 March 2009 and the results were presented in the Baseline Water Quality Monitoring Report Part A.  Baseline monitoring for the Po Toi section of works (Zones B to D) was undertaken from 27 February 2009 to 13 March 2009 and the Baseline Water Quality Monitoring Report Part B presented the results of the monitoring data for Zones B to D near Po Toi Island.

Impact Monitoring was carried out at Deep Water Bay (Zone A) commencing on 25 March 2009.  The barge “CB Networker” completed the cable installation works in Hong Kong waters on 2 June 2009 and the water quality monitoring was subsequently suspended.

A cable fault was then identified in the previously laid submarine telecommunications cable in Zone A.  Hence, the marine works of this Project were resumed on 24 July 2009 to locate the cable fault and replace the cable.  Cable repair works were completed in Zone A on 11 August 2009 and the cable repair barge “Challenger 1” demobilised on 12 August 2009.

On 28 August, Post Lay Inspection and Burial (PLIB) works commenced within Zone A and these were completed in this Zone on 30 August 2009.  Further PLIB works continued in the areas outside the Monitoring Zones A to E where no water quality monitoring was required according to the EM&A Manual.

The Contractor confirmed that the marine works of the Project were completed on the 14 September 2009.  Hence, the Post-project Monitoring was carried out at the Deep Water Bay and Po Toi sites between 21 September and 5 October 2009, in accordance with the requirements of the EM&A Manual.  This report presents the data obtained from Deep Water Bay monitoring stations (Figure 2.2) and from Po Toi monitoring stations (Figure 2.3)  Results of the post-Project monitoring data have been compared against the results of the Baseline Environmental Monitoring Part A and Part B.

2.2                                      Site Description

The cable installation runs from Deep Water Bay out through southeast Hong Kong offshore waters.  The alignment of the cable is illustrated in Figure 2.1.

2.3                                      Status of Environmental Approval Documents

A summary of the relevant permits, licences, notifications and/or reports on environmental protection for this Project is presented in Table 2.1.

 

Table 2.1        Summary of Environmental Licensing, Notification, Permit and Reporting Status

Permit / Licence / Notification / Report

Reference

Validity Period

Remarks

Environmental Permit

(EP-294/2007)

Throughout the construction period

 

Granted on 23 November 2008

Further Environmental Permit

(FEP-01/294/2007)

Throughout the construction period

 

Granted on 9 July 2008

EM&A Manual

-

Throughout the construction period

 

Approved by EPD on 12 March 2009

Baseline Water Quality Monitoring Report (Part A)

-

Throughout the construction period for Zones A and E

Approved by EPD on 1 April 2009

Baseline Water Quality Monitoring Report (Part B)

-

Throughout the construction period for Zones B to D

Approved by EPD on 30 April 2009

Pre Installation Geophysical Survey Report

-

Throughout the construction period for the Grout Mattress Installation

Accepted by AFCD and EPD on 7 July 2009


3                                            Water Quality Monitoring Requirements

3.1                                      Monitoring Locations

In accordance with the EM&A Manual, for post-Project monitoring, water quality sampling was undertaken at stations situated around the cable works at the Deep Water Bay area (Zones A and E) and Po Toi area (Zones B to D).  This meant water quality sampling was undertaken throughout the reporting period at the following stations:

Deep Water Bay area:

·           Zone A: S1 and S2 are situated at the two Seawater Intake Points in Deep Water Bay.  They are within 500 m west/northwest of the cable alignment at Deep Water Bay for monitoring the effect of cable laying works in the area;

·           Zone A: S3 is a Sensitive Receiver used to monitor the water quality conditions of the Coastal Protection Areas at Middle Island;

·           Zone A: B1 is an Impact Station used to monitor the effect of the construction works on Deep Water Bay Beach;

·           Zone A: R1 is a Control Station for S1, S2, S3 and B1 at Deep Water Bay which is not supposed to be influenced by the cable laying works due to its remoteness to the construction works;

·           Zone E: C4 and C5 are Impact Stations used to monitor the effect of cable laying works on the water quality conditions for the coral communities found at Round Island and the southern side of Chung Hom Wan, respectively; and

·           Zone E: R4 is Control Station for C4 and C5 in Zone E.  It is not expected to be influenced by the construction works.

Po Toi area:

·           Zone B, C and D: C1, C2 and C3 respectively are located approximately 600 m north of the cable alignment at Po Toi for monitoring the effect of cable laying works on coral communities in the area;

·           Zone B, C and D: F1 is used to monitor the effect of the cable installation works on the Po Toi Fish Culture Zone (FCZ); and

·           Zone B, C and D: R2 and R3 are Control Stations for C1, C2, C3 and F1 at Po Toi which are not supposed to be influenced by the cable laying works due to their remoteness to the construction works.

The co-ordinates of Zones A to E are listed in Table 3.1 and the co-ordinates of all the above monitoring stations are listed in Table 3.2 for the Deep Water Bay area (Zones A and E) and Table 3.3 for the Po Toi area (Zones B to D).

Table.3.1        Co-ordinates of Starting Points and Ending Points for Zones A to E (HK Grid)

Zone

Starting Point

Ending Point

Easting

Northing

Easting

Northing

A

837029.763

811601.699

836367.572

810545.975

B

841917.597

802680.115

844161.823

801308.268

C

844161.823

801308.268

845555.155

801495.491

D

845555.155

801495.491

846970.152

801749.210

E

836469.415

809294.174

837478.871

807740.633

 

Table 3.2        Co-ordinates of All Monitoring Stations in Deep Water Bay area (Zones A and E) (HK Grid)

Station

Nature            

Corresponding Control Station

Easting

Northing

S1

Seawater Intakes

R1

836538.669

811528.535

S2

Seawater Intakes

R1

836195.047

810956.409

S3

Coastal Protection Areas

R1

836677.103

810666.744

B1

Gazetted Beach

R1

837241.114

811498.400

C4

Coral Colonies

R4

836863.233

808528.950

C5

Coral Colonies

R4

838197.242

808036.724

R1

Control Station

-

835951.109

809052.535

R4

Control Station

-

835934.876

807347.391

 

Table 3.3        Co-ordinates of All Monitoring Stations in Po Toi area (Zones B to D) (HK Grid)

 

Station

Nature            

Corresponding Control Station

Easting

Northing

C1

Coral Colonies

R2, R3

843547.437

802009.952

C2 (a)

Coral Colonies

R2, R3

844816.539

801952.827

C3

Coral Colonies

R2, R3

846179.825

802224.557

F1 (b)

Fish Culture Zone

R2, R3

843978.070

802732.503

R2

Control Station

-

842075.000

803375.038

R3 (c)

Control Station

-

847656.611

803323.108

Notes:

(a)        The original location of C2 was situated very close to the shore.  C2 is therefore moved about 80 m seaward from the original location due to safety reasons and the new location is considered representative.

(b)       The original location of F1 was situated very close to the shore.  F1 is therefore moved about 40 m seaward from the original location due to safety reasons and the new location is considered representative.

(c)      Due to rough sea conditions in the area on 26 September 2009, the locations of three monitoring stations were moved.  C2 was moved 714 m north-west of its original location and C3, 2003 m due west of its original location.  R3 was moved 2059 m north-west of its original location, close to the midpoint of Po Toi Island and Sung Kong.  These new locations were all considered representative.

3.2                                      Monitoring Parameters and Frequency

The post-Project water quality monitoring was conducted in accordance with the requirements stated in the EM&A Manual.  These are presented below.

3.2.1                                Monitoring Parameters

Parameters measured in situ were:

·       dissolved oxygen (DO) (% saturation and mg L-1);

·       temperature (°C);

·       turbidity (NTU); and

·       salinity (‰).

The only parameter measured in the laboratory was:

·       suspended solids (SS) (mgL-1).

In addition to the water quality parameters, other relevant data were measured and recorded in field logs, including the location of the sampling stations, water depth, time, weather conditions, sea conditions, tidal state, special phenomena and work activities undertaken around the monitoring and works area that may influence the monitoring results.

3.2.2                                Monitoring Frequency

Post-Project water quality monitoring was carried with each area being sampled three times in total.  At the Deep Water Bay area, these three samples were taken over the course of a week, while at Po Toi, due to bad weather, sampling lasted over 13 days.  The interval between two sets of monitoring was not less than 36 hours. 

For the Deep Water Bay area, the monitoring was undertaken at eight locations (six impact monitoring stations S1, S2, S3, B1, C1, C2 and two control monitoring stations R1 and R4), as shown in Figure 2.2. 

For the Po Toi area, the monitoring was undertaken at six locations (four impact monitoring stations C1, C2, C3, F1 and two control monitoring stations R2 and R3), as shown in Figure 2.3.

Samples were taken during mid-flood and mid-ebb tidal state on each sampling occasion.  The projected monitoring frequency and parameters for Impact Monitoring are summarised in Table 3.4.

 

Table 3.4        Monitoring Frequency and Parameters for Post Project Monitoring

Zone

Station Type

Monitoring Station

Post Project Monitoring

Monitoring Parameters

A

Control

R1

Deep Water Bay area: 3 days in a week ; mid ebb and mid flood tides

 

Po Toi area: 3 days over two weeks ; mid ebb and mid flood tides

Temperature, Turbidity, Salinity, DO, SS

Impact

S1, S2, S3 and B1

B

Control

R2 and R3

Impact

C1, F1

C

Control

R2 and R3

Impact

C2, F1

D

Control

R2 and R3

Impact

C3, F1

E

Control

C4 and C5

Impact

R4

3.3                                      Monitoring Equipment and Methodology

3.3.1                                Monitoring Equipment

Dissolved Oxygen, Temperature, Salinity, Turbidity Measuring Equipment

The instrument was a portable, weatherproof multi-parameter measuring instrument (YSI 6820) complete with cables, multi-probe sensor, comprehensive operation manuals, and was operable from a DC power source.  It was capable of measuring:

·       dissolved oxygen levels in the range of 0 – 50 mg L-1; and 0-500% saturation;

·       temperature of -5 to 50 °C;

·       turbidity levels between 0-1000 NTU (response of the sensor was checked with certified standard turbidity solutions before the start of measurement); and,

·       salinity in the range of 0-40 ppt (checked with 30 ppt Salinity solutions before the start of the measurement).

Water Depth Gauge

The water depth gauge affixed to the bottom of the water quality monitoring vessel was used.

Current Velocity and Direction

Current velocity and direction was estimated by conducting float tracking.

Positioning Device

A Global Positioning System (GPS) was used (C-Navigator World DGPS, GPS 72A) during monitoring to ensure the accurate recording of the position of the monitoring vessel before taking measurements.  The use of DGPS was used for positioning device, which was well calibrated at an appropriate checkpoint.

Water Sampling Equipment

Water samples for suspended solids measurement were collected by the use of a multi-bottle water sampling system (General Oceanics Inc., Rosette Sampler ROS02), consisting of PVC bottles of more than two litres, which could be effectively sealed with cups at both ends.  The water sampler had a positive latching system to keep it open and prevent premature closure until released by a messenger when the sampler was at the selected water depth.

3.3.2                                Monitoring Methodology

Timing & Frequency

The water quality sampling was undertaken within a 3 hour window of 1.5 hours before and 1.5 hours after mid-flood and mid-ebb tides.  Tidal range for flood and ebb tides was not less than 0.5 m for capturing representative tides. 

Reference was made to the predicted tides at Waglan Island, which is the tidal station nearest to the Project sites, published on the website of Hong Kong Observatory([1]).  Based on the predicted water levels at Waglan Island, the post-Project water quality monitoring was conducted between 21 September and 5 October, following the schedule presented in Annex A.  Note that due to rough sea conditions around the Po Toi area, monitoring in this area was delayed, prolonging the overall post-Project monitoring period.

Duplicate samples were collected from each of the monitoring events for in situ measurements and laboratory analysis.

Depths

Each station was sampled and measurements were taken at three depths, 1 m below the sea surface, mid depth and 1m above the sea bed.  For stations that were less than 3 m in depth, only the mid depth sample was taken.

Protocols

The multi-parameter measuring instrument (YSI 6820) was checked and calibrated by an HOKLAS accredited laboratory before use.  Onsite calibration was also carried out to check the responses of sensors and electrodes using certified standard solutions before each use.  Sufficient stocks of spare parts were maintained for replacements when necessary, and backup monitoring equipment was made available.

Water samples for SS measurements were collected in high density polythene bottles, packed in ice (cooled to 4° C without being frozen), and delivered to an HOKLAS accredited laboratory as soon as possible after collection.

Laboratory Analysis

All laboratory work was carried out by a HOKLAS accredited laboratory.  Water samples of about 1,000 mL were collected at the monitoring and control stations for carrying out the laboratory determinations.  The determination work started within the next working day after collection of the water samples.  The analyses followed the standard methods as described in APHA Standard Methods for the Examination of Water and Wastewater, 19th Edition, unless otherwise specified (APHA 2540D for SS).

The QA/QC details were in accordance with requirements of HOKLAS or another internationally accredited scheme (for details refer to Annex B).

 


4                                            IMPLEMENTATION STATUS OF ENVIRONMENTAL MITIGATION measures

Mitigation measures for water quality control were recommended in the Project Profile and Environmental Permit.  The Contractor implemented the following measures during cable installation:

·       Marine works within 200 m of the nearest boundary of the Deep Water Bay bathing beach scheduled to avoid the peak bathing season (1 April to 30 October inclusive).

·       The submarine cable laying works carried out by diver(s) for the initial segment that extends for about 300m seaward from the low water mark of the Deep Water Bay bathing beach.  Beyond this initial segment, the cable was laid by a jetting machine with a maximum forward speed of no more than 1 km per hour.

·       The forward speed of the installation barge was limited to a maximum of 1 km per hour.

·       A water quality monitoring programme was conducted to ensure no impacts will occur at the Ocean Park’s seawater intakes and corals at southern coast of Po Toi.

 

5                                            Post-Project Monitoring Results

5.1                                      Deep Water Bay Area

For the post-Project monitoring, three monitoring events were scheduled in the Deep Water Bay area between 21 September and 25 September 2009.  Monitoring events at all designated monitoring stations in the Deep Water Bay area were performed on schedule on 21, 23 and 25 September.

The post-Project monitoring data are presented in Annex C and compared with baseline and impact monitoring results in Figures C1-C4.

The levels of dissolved oxygen measured during the reporting week were mostly comparable to those obtained during the baseline and impact monitoring periods.  In general, a decreasing trend in dissolved oxygen levels was detected at all the impact and control stations during the period from May 2009 to September 2009 but the DO levels recorded at all the impact stations were of similar magnitude to those measured at the control stations.  The Weekly Impact Monitoring Reports discuss the seasonal variation or natural fluctuation that may account for the declining DO trends.

In general levels of turbidity measured during the reporting week were mostly comparable to those obtained during the baseline and impact monitoring periods.  The exception was during the mid-flood measurement taken on 21 September, when three stations (R1, R4, C5) showed elevated levels of turbidity.  Since two of these stations (R1 and R4) are control stations, situated at a distance not likely to be affected by the Project works, it is considered that all these measurements were due to natural variations.

Levels of suspended solids measured during the reporting week were in general comparable to those recorded during the baseline monitoring period with some exceptions.  Some measurements taken at station R1 both during mid-ebb and mid-flow were slightly elevated during the reporting period, but since this is a control station these measurements were not considered to be due to Project works.  Measurements at R4 and C5 taken during the mid-ebb tide on 21 September, was also slightly elevated.  R4 is a control station and the measurement taken at C5 was below that of both control stations R4 and R1, so the measurements were not considered to be due to the Project works.  Also on the following two days of reporting, the measurements at both R4 and C5 were back to levels comparable to baseline levels once more.

5.2                                      Po Toi Area

For the post-Project monitoring, three monitoring events were scheduled in the Po Toi area between 22 September and 28 September 2009.  Due to bad weather in the area, monitoring was re-scheduled and monitoring events were performed on 22 and 26 September and 5 October 2009.

The post-Project monitoring data are presented in Annex D and compared with baseline and impact monitoring results in Figures D1-D4.

The levels of dissolved oxygen measured during the reporting week were mostly slightly lower to those obtained during the baseline and impact monitoring periods.  In general, a decreasing trend in dissolved oxygen levels was detected at all the impact and control stations during the period from May 2009 to September 2009 but the DO levels recorded at all the impact stations were of similar magnitude to those measured at the control stations.  The Weekly Impact Monitoring Reports discuss the seasonal variation or natural fluctuation that may account for the declining DO trends.

On average, levels of turbidity and suspended solids measured during the reporting week were slightly elevated compared to those obtained during the baseline and impact monitoring periods.  The Environmental Protection Department of the Hong Kong Special Administrative Region Government (EPD) collects water quality data regularly from various fixed stations around Hong Kong waters.  Analysis of such data from monitoring stations located close to the Po Toi area (SM19) over the past ten years, shows seasonal variation in the turbidity and suspended solids measurements; on average, levels in the latter half of the year are slightly higher than those in the first half of the year (See Annex E)

Given this information, the slight increases in turbidity and suspended solids levels during the reporting period, compared to baseline and impact periods, are likely to be due to natural variation.  It is also unlikely that the increases were due to Project works, since the last Project works (cable installation) carried out in the Po Toi area occurred in June 2009, three months previously.  It is therefore considered that all these measurements were due to natural variations.

 

6                                            Conclusions

This Post-Project Monitoring Report presents the EM&A work undertaken during the period from 21 September to 5 October 2009 in accordance with the EM&A Manual and the requirements under FEP-01/294/2007.

The overall water quality in Zones A to E after the completion of the Project was found to be similar to that before the commencement of Project works, taking into account seasonal variations.

It is concluded that no deterioration of water quality was observed and hence the effect of the Project works on water quality at the Project site is considered to be negligible. 

 

 



([1])         Hong Kong Observatory (2009) http://www.hko.gov.hk/tide/eWLtide.htm