Table of contents

 

 

EXECUTIVE SUMMARY.. 1

Introduction. 1

Environmental Monitoring Works. 1

Environmental Licenses and Permits. 2

Key Information in the Reporting Month. 2

Future Key Issues. 3

1.     INTRODUCTION.. 4

Background. 4

Project Organizations. 5

Construction Activities undertaken during the Reporting Month. 5

Summary of EM&A Requirements. 6

2.     AIR QUALITY.. 7

Monitoring Requirements. 7

Observations. 7

3.     NOISE.. 8

Monitoring Requirements. 8

Observations. 8

4.     Landscape AND Visual.. 9

Monitoring Requirements. 9

Results and Observations. 9

5.     ENVIRONMENTAL AUDIT.. 10

Site Audits. 10

Status of Environmental Licensing and Permitting. 11

Status of Waste Management 12

Implementation Status of Environmental Mitigation Measures. 12

Summary of Mitigation Measures Implemented. 13

Implementation Status of Event Action Plans. 13

Summary of Complaint, Warning, Notification of any Summons and Successful Prosecution. ..13

6.     FUTURE KEY ISSUES. 14

7.     CONCLUSIONS AND RECOMMENDATIONS. 16

Conclusions. 16

Recommendations. 16

 


 

lIST OF TABLES

                                               

 

Table I      Non-compliance Recorded for the Project in the Reporting Month. 2

Table II     Summary Table for Key Information in the Reporting Month. 2

Table III    Key Project Contacts. 5

Table IV    Construction Programme Showing the Inter-Relationship with Environmental Protection/Mitigation Measures  6

Table V     Summary of Environmental Licensing and Permit Status. 11

Table VI    Observations and Recommendations of Site Inspections. 12

 

 

lIST OF FIGUREs

 

Figure 1           Site Layout Plan

 

lIST OF APPENDIces

 

A                                          Action and Limit Levels

B                                          Summary of Exceedance

C                                          Site Audit Summary

D                                          Event Action Plans

E                                           Environmental Mitigation Implementation Schedule (EMIS)

F                                           Summaries of Environmental Complaint, Warning, Summon and Notification of Successful Prosecution

G                                         Waste Generated Quantity

 

 

                                                                                             

                                                                                             


EXECUTIVE SUMMARY

Introduction

 

1.      This is the 76th Monthly Environmental Monitoring and Audit Report prepared by Cinotech Consultants Ltd. for “Contract No. KL/2014/01 - Kai Tak Development – Stage 2 Infrastructure Works for Developments at the Southern Part of the Former Runway” (Hereafter referred to as “the Project”). This contract work comprises two Schedule 2 designated projects (DP), namely the new distributor road D4 (part) and roads D3A & D4A serving the planned KTD. The DPs are part of the designated projects under Environmental Permits (EP) No.: EP-337/2009 (“New distributor roads serving the planned Kai Tak Development”) and EP-445/2013/B (“Kai Tak Development – Roads D3A & D4A”) respectively. This report documents the findings of EM&A Works conducted in July 2022.

 

2.      With reference to the same principle of EIA report of the Project, air quality monitoring station should be provided at the Air Sensitive Receivers (ASR) within 500 m from the boundary of this Project while construction noise monitoring station should be provided at the Noise Sensitive Receivers (NSR) within 300 m from the boundary of this Project. Since the opening of the Centre of Excellence in Paediatrics (Children’s Hospital) on 18 December 2018, the hospital is considered as the only relevant monitoring location and therefore the monitoring is required.

 

3.      The major site activities undertaken in the reporting month included:

·            Architectural features works at landscaped deck and ground floor open space;

·            Defect work of pedestrian streets;

·            E&M works;

·            Laying of paving blocks for footpath;

·            Planting works along footpath and at deck level, and;

·            TTA implementation, minor works at Shing Fung Road and Wang Chiu Road / Kai Cheung Road.

Environmental Monitoring Works

 

4.      Environmental monitoring for the Project was performed in accordance with the EM&A Manual and the monitoring results were checked and reviewed.  Site Inspections/Audits were conducted once per week.  The implementation of the environmental mitigation measures, Event Action Plans and environmental complaint handling procedures were also checked.

 

5.      Summary of the non-compliance in the reporting month for the Project is tabulated in Table I.

          

Table I      Non-compliance Recorded for the Project in the Reporting Month

Parameter

No. of Project-related Exceedance

Action Taken

Action Level

Limit Level

Noise

0

0

N/A

 

Environmental Monitoring for Air Quality and Construction Noise

 

6.      No monitoring for air quality and construction noise is required.  No Action/Limit Level exceedance was recorded.

Environmental Licenses and Permits

 

7.      Licenses/Permits granted to the Project include the Environmental Permits (EP) for the Project, EP-337/2009 issued on 23 April 2009 and EP-445/2013 issued on 3 May 2013 (Amended Environmental Permit (No.: EP-445/2013/A) issued on 13 August 2014; further amendment of Environmental Permit (No.: EP-445/2013/B) issued on 3 May 2022).

 

8.      Billing Account for Disposal of Construction Waste (A/C No. 7024073)

 

9.      Registration of Chemical Waste Producer (License: 5213-247-C4004-01).

 

10.  Water Discharge License (License: WT00023634-2016).

 

11.    Construction Noise Permits (Permit: GW-RE0442-20, GW-RE0639-20, GW-RE0045-21, GW-RE0717-21 & GW-RE0656-21)

 

Key Information in the Reporting Month

 

12.  Summary of key information in the reporting month is tabulated in Table II.

 

Table II           Summary Table for Key Information in the Reporting Month

Event

Event Details

Action Taken

Status

Remark

Number

Nature

Complaint received

0

---

N/A

N/A

---

Reporting Changes

0

---

N/A

N/A

---

Notifications of any summons & prosecutions received

0

---

N/A

N/A

---

Future Key Issues

 

13.  The future key environmental issues in the coming month include:

·            Architectural features works at landscaped deck and ground floor open space;

·            Defect work of pedestrian streets;

·            E&M works;

·            Laying of paving blocks for footpath;

·           Noise barrier modification

·            Planting works along footpath and at deck level, and;

·            TTA implementation, minor works at Shing Fung Road and Wang Chiu Road / Kai Cheung Road.

Reporting Changes

 

14.  Since the major parts of Works under Contract no. KL/2014/03 has been completed, the environmental monitoring works of EM&A monitoring station, KTD1a, was then handed over to the ET of Contract no. ED/2018/04 in August, 2020. In order to obtain the environmental impact monitoring data with higher representativeness based on several factors, such as distance between monitoring location and the sensitive receiver, non-project related interference, obstruction to the construction works on site and the power supply problem, the monitoring location KTD1a was relocated to the original location as proposed in the EM&A manual (AEIAR-174/2013), and renamed as KTD1 on 3 August 2020.

 


1.                INTRODUCTION

Background

 

1.1              The Kai Tak Development (KTD) is located in the south-eastern part of Kowloon Peninsula, comprising the apron and runway areas of the former Kai Tak Airport and existing waterfront areas at To Kwa Wan, Ma Tau Kok, Kowloon Bay, Kwun Tong and Cha Kwo Ling. It covers a land area of about 328 hectares. Stage 2 Infrastructure Works for Developments for Southern Part of the Former Runway is one of the construction stages of KTD. It contains two Schedule 2 DPs including new distributor roads serving the planned KTD and KTD Roads D3A & D4A. The general layout of the Project is shown in Figure 1.

 

1.2              One Environmental Permit (EP) No.: EP-337/2009 was issued on 23 April 2009 for new distributor roads serving the planned KTD and one Environmental Permit No.: EP-445/2013 was issued on 3 May 2013 for Kai Tak Development Roads D3A & D4A to Civil Engineering and Development Department (CEDD) as the Permit Holder. Pursuant to Section 13 of the EIAO, the Director of Environmental Protection Department amended the Environmental Permit No.: EP-445/2013 based on the Application No. VEP-449/2014 and the Environmental Permit (No.: EP-445/2013/A) was issued on 13 August 2014. The Environmental Permit (No.: EP-445/2013/A) was further amended and the Environmental Permit (No.: EP-445/2013/B) was issued on 3 May 2022.

 

1.3              A study of environmental impact assessment (EIA) was undertaken to consider the key issues of air quality, noise, water quality, waste, land contamination, cultural heritage and landscape and visual impact, and identify possible mitigation measures associated with the works. EIA Reports (Register No. AEIAR-130/2009 and AEIAR-170/2013) were approved by the Environmental Protection Department (EPD) on 4 March 2009 and 3 May 2013 respectively.

 

1.4              Cinotech Consultants Limited (Cinotech) was commissioned by Civil Engineering and Development Department (CEDD) to undertake the role of the Environmental Team (ET) for the Contract No. KL/2014/01 – Stage 2 Infrastructure Works for Developments at the Southern Part of the Former Runway. The construction work under KL/2014/01 comprises the construction of part of the Road D4 under the EP (EP-337/2009) and the construction of Roads D3A & D4A under the EP (EP-445/2013/B).

 

1.5              Cinotech Consultants Limited was commissioned by Civil Engineering and Development Department (CEDD) to undertake the Environmental Monitoring and Audit (EM&A) works for the Project. The construction commencement of this Contract is on 13 April 2016. This is the 76th Monthly EM&A report summarizing the EM&A works for the Project in July 2022.

 

1.6              All project information since the commencement of work under EPs including Monthly EM&A Reports is made available to the public via internet access at the website:

            https://www.epd.gov.hk/eia/english/register/index8/vep4492014_content.html

Project Organizations

 

1.7              Different parties with different levels of involvement in the project organization include:

·          Project Proponent – Civil Engineering and Development Department (CEDD).

·          The Supervising Officer and the Supervising Officer’s Representative (SO) – AECOM Asia Co. Ltd. (AECOM).

·          Environmental Team (ET) – Cinotech Consultants Limited (CCL).

·          Independent Environmental Checker (IEC) – Ka Shing Management Consultant Ltd. (KSMC).

·          Contractor – Continental Engineering Corp. and Chit Cheung Construction Co. Ltd. Joint Venture (CCJV).

 

1.8              The key contacts of the Project are shown in Table III.

 

Table III       Key Project Contacts

Party

Role

Contact Person

Position

Phone No.

Fax No.

CEDD

Project Proponent

Mr. Ricky Yu

Engineer

3579 2124

3579 4516

AECOM

Supervising Officer

Mr. Clive Cheng

CRE

3746 1801

2798 0783

Cinotech

Environmental Team

Mr. K S Lee

Environmental Team Leader

2151 2091

3107 1388

Ms. Betty Choi

Audit Team Leader

2151 2072

KSMC

Independent Environmental Checker

Dr. Douglas Wong

IEC

2618 2166

2120 7752

CCJV

Contractor

Mr. Jack Lai

Environmental Officer

2960 1398

2960 1399

Construction Activities undertaken during the Reporting Month

 

1.9              The site activities undertaken in the reporting month included:

·            Architectural features works at landscaped deck and ground floor open space;

·            Defect work of pedestrian streets;

·            E&M works;

·            Laying of paving blocks for footpath;

·            Planting works along footpath and at deck level, and;

·            TTA implementation, minor works at Shing Fung Road and Wang Chiu Road / Kai Cheung Road.

 

 


 

1.10          The construction programme showing the inter-relationship with environmental protection/mitigation measures is presented in Table IV.

 

Table IV          Construction Programme Showing the Inter-Relationship with Environmental Protection/Mitigation Measures

Construction Works

Major Environmental Impact

Control Measures

As mentioned in Section 1.8

Noise, dust impact, water quality and waste generation

Sufficient watering of the works site with active dust emitting activities;

Properly cover the stockpiles;

On-site waste sorting and implementation of trip ticket system;

Appropriate desilting/sedimentation devices provided on site for treatment before discharge;

Use of quiet plant and well-maintained construction plant;

Well maintain the drainage system to prevent the spillage of wastewater during heavy rainfall;

Provide mitigation measure to temporary use of chemicals;

Provide sufficient mitigation measures as recommended in Approved EIA Report/Lease requirement.

Summary of EM&A Requirements

 

1.11          The EM&A programme requires construction noise monitoring, air quality monitoring, landscape and visual monitoring and environmental site audit.  The EM&A requirements for each parameter are described in the following sections, including:

·          All monitoring parameters;

·          Action and Limit levels for all environmental parameters;

·          Event Action Plans;

·          Environmental requirements and mitigation measures, as recommended in the EM&A Manual under the EP.

 

1.12          The advice on the implementation status of environmental protection and pollution control/mitigation measures is summarized in Section 5 of this report.

 


2.                AIR QUALITY

Monitoring Requirements

2.1              With reference to the same principle of EIA report of the Project, air quality monitoring station should be provided at the Air Sensitive Receivers (ASR) within 500 m from the boundary of this Project. Since the opening of the Centre of Excellence in Paediatrics (Children’s Hospital) on 18 December 2018, the hospital is considered as the only relevant monitoring location and therefore the monitoring is required.

2.2              As the monitoring works for the hospital is covered by the Contract KL/2014/03 (Kai Tak Development Stage 3 Infrastructure Works for Developments at the Southern Part of the Former Runway) at the monitoring station (KTD1), the corresponding monitoring results for July 2022 should be accessed in the EM&A report for the reporting month. Appendix A shows the established Action and Limit Levels for the environmental monitoring works.

 

Observations

2.3              No monitoring for air quality is required for this report.  No Action/Limit Level exceedance at KTD1 was recorded. The summary of exceedance record in reporting month is shown in Appendix B.

2.4              Site audits were carried out on a weekly basis to monitor and audit the timely implementation of air quality mitigation measures within the site boundaries of this Project.  The summaries of site audits are attached in Appendix C.

 

 

 

 

3.                NOISE

Monitoring Requirements

3.1              With reference to the same principle of EIA report of the Project, construction noise monitoring station should be provided at the Noise Sensitive Receivers (NSR) within 300 m from the boundary of this Project. Since the opening of the Centre of Excellence in Paediatrics (Children’s Hospital) on 18 December 2018, the hospital is considered as the only relevant monitoring location and therefore the monitoring is required.

3.2              As the monitoring works for the hospital is covered by the Contract KL/2014/03 (Kai Tak Development Stage 3 Infrastructure Works for Developments at the Southern Part of the Former Runway) at the monitoring station (KTD1), the corresponding monitoring results for July 2022 should be accessed in the EM&A report for the reporting month. Appendix A shows the established Action and Limit Levels for the environmental monitoring works.

 

Observations

3.3              No monitoring for construction noise is required for this report.  No Action/Limit Level exceedance at KTD1 was recorded. The summary of exceedance record in reporting month is shown in Appendix B.

3.4              Site audits were carried out on a weekly basis to monitor and audit the timely implementation of construction noise mitigation measures within the site boundaries of this Project.  The summaries of site audits are attached in Appendix C.

 

 

 

 


4.                Landscape AND Visual

Monitoring Requirements

 

4.1              According to EM&A Manual of the Kai Tak Development EIA Study, ET shall monitor and audit the contractor’s operation during the construction period on a weekly basis, and to report on the contractor’s compliance.

Results and Observations

 

4.2              Site audits were carried out on a weekly basis to monitor and audit the timely implementation of landscape and visual mitigation measures within the site boundaries of this Project.  The summaries of site audits are attached in Appendix C. 

 

4.3              No non-compliance of the landscape and visual impact was recorded in the reporting month.

 

4.4              Should non-compliance of the landscape and visual impact occur, action in accordance with the action plan presented in Appendix D shall be performed.

 


5.              ENVIRONMENTAL AUDIT

Site Audits

                                

5.1              Site audits were carried out on a weekly basis to monitor the timely implementation of proper environmental management practices and mitigation measures in the Project site.  The summaries of site audits are attached in Appendix C. 

 

5.2              Site audits were conducted by representatives of the Contractor, Supervising Officer and ET on 7, 15, 22 & 27 July 2022 in the reporting month. IEC joint site inspection was conducted on 27 July 2022. No non-compliance was observed during the site audits.

Status of Environmental Licensing and Permitting

 

5.3              All permits/licenses obtained for the Project are summarized in Table V.

 

Table V                       Summary of Environmental Licensing and Permit Status

Permit No.

Valid Period

Details

Status

From

To

Environmental Permit (EP)

EP-337/2009

23 Apr 2009

N/A

Construction of new distributor roads serving the planned Kai Tak development.

Valid

EP-445/2013/A

13 Aug 2014

N/A

Construction of Kai Tak Development roads D3A and D4A

Valid

Effluent Discharge License

WT00023634-2016

--

31 Mar 2021

Wastewater from the construction site including effluent treated by screen and sedimentation tank; There are no more need for the license after 31 March 2021 as the project is close to completion and no significant waste water is being generated from site.

Expired on
31
Mar 2021

Registration of Chemical Waste Producer

5213-247-C4004-01

--

N/A

Chemical Waste Types:

Surplus paint, waste contaminated by paint, diesel, waste contaminated by diesel, spent lubricating oil and waste, soil contaminated by lubricating oil.

Valid

Construction Noise Permit (CNP)

GW-RE0442-20

14 Jun 2020

13 Dec 2020

Construction Noise Permit for the use of powered mechanical equipment for carrying out construction work other than percussive pilling and performing prescribed construction work.

Construction Noise Permit for the use of powered mechanical equipment for carrying out construction work other than percussive pilling and performing prescribed construction work.

Expired on
13
Dec 2020

GW-RE0639-20

3 Aug 2020

19 Jan 2021

Expired on 19 Feb 2021

GW-RE0045-21

20 Jan 2021

19 Jul 2021

Expired on 19 Jul 2021

GW-RE0656-21

9 Jul 2021

30 Sep 2021

Expired on 30 Sep 2021

GW-RE0717-21

30 Jul 2021

19 Jan 2022

Expired on 19 Jan 2022

Status of Waste Management

 

5.4              The amount of wastes generated by the major site activities of this Project during the reporting month is shown in Appendix G.

 

5.5              In respect of the dump truck cover, the Contractor is reminded to take record photos and inspection to ensure that all dump trucks have fully covered the skip before leaving the site.

Implementation Status of Environmental Mitigation Measures

 

5.6              During site inspections in the reporting month, no non-conformance was identified.  ET weekly site inspections were carried out during the reporting month and the observations and recommendations are summarized in Table VI.

Table VI                      Observations and Recommendations of Site Inspections

Parameters

Date

Observations and Recommendations

Follow-up

Water Quality

--

--

--

Air Quality

--

--

--

Noise

--

--

--

Waste/
Chemical Management

--

--

--

Landscape and Visual

--

--

--

Permits/
Licenses

--

--

--


 

Summary of Mitigation Measures Implemented

 

5.7          An updated summary of the EMIS is provided in Appendix E.

Implementation Status of Event Action Plans

 

5.8              The Event Action Plans for noise and landscape and visual are presented in Appendix D. No Event Action Plan for air quality is considered necessary.

Construction Dust

5.9          No Action/Limit Level exceedance was recorded in the reporting month.

Construction Noise

5.10      No Action/Limit Level exceedance was recorded in the reporting month.

Landscape and visual

5.11      No non-compliance was recorded in the reporting month.

 

Summary of Complaint, Warning, Notification of any Summons and Successful Prosecution

 

5.12          The summaries of environmental complaint, warning, summon and notification of successful prosecution for the Project is presented in Appendix F.

 


 

6.              FUTURE KEY ISSUES

 

6.1              Major site activities undertaken for the coming two months include:

 

·            Architectural features works at landscaped deck and ground floor open space;

·            Defect work of pedestrian streets;

·            E&M works;

·            Laying of paving blocks for footpath;

·           Noise barrier modification

·            Planting works along footpath and at deck level, and;

·            TTA implementation, minor works at Shing Fung Road and Wang Chiu Road / Kai Cheung Road.

 

 

6.2              Key environmental issues in the coming month include:

 

·                Wastewater and runoff discharge from site;

·                Silt, mud and sand along u-channels and sedimentation tanks;

·                Review and implementation of temporary drainage system for the surface runoff;

·                Noise from operation of the equipment, especially for rock-breaking activities, piling works and machinery on-site;

·                Dust generation from stockpiles of dusty materials, exposed site area, excavation works and rock breaking activities;

·                Dust generating activity and on haul road;

·                Storage of construction materials on site;

·                Storage of chemicals/fuel and chemical waste/waste oil on site;

·                Accumulation of general and construction waste on site


 

6.3                   The tentative program of major site activities and the impact prediction and control measures for the coming two months, i.e. August and September 2022 are summarized as follows:

 

Construction Works

Major Impact Prediction

Control Measures

 

 

 

 

 

 

 

 

 

 

As mentioned in Section 6.1

Air quality impact (dust)

a)       Frequent watering of haul road and unpaved/exposed areas;

b)      Frequent watering or covering stockpiles with tarpaulin or similar means; and

c)       Watering of any earth moving activities.

Water quality impact (surface run-off)

a)       Diversion of the collected effluent to de-silting facilities for treatment prior to discharge to public storm water drains;

b)      Provision of adequate de-silting facilities for treating surface run-off and other collected effluents prior to discharge;

c)       Provision of perimeter protection such as sealing of hoarding footings to avoid run-off from entering the existing storm water drainage system via public road; and

d)      Provision of measures to prevent discharge into the stream.

Noise Impact

a)       Scheduling of noisy construction activities if necessary to avoid persistent noisy operation;

b)      Controlling the number of plants use on site;

c)       Regular maintenance of machines; and

d)      Use of acoustic barriers if necessary.

Waste/

Chemical Management

a)      Maintenance involving activities with potential for leakage and spillage should only be undertaken within the areas appropriately equipped to control these discharges.

b)      Chemical wastes should be hold by suitable containers with clear label and stored at a safe location.

 


 

7.              CONCLUSIONS AND RECOMMENDATIONS

Conclusions

 

7.1              The Environmental Monitoring and Audit (EM&A) Report presents the EM&A works undertaken in July 2022.

 

Air Quality and Construction Noise

 

7.2              No regular monitoring air quality and noise monitoring is required for the Project. No Action/Limit Level exceedance was recorded.

Landscape and visual

7.3              No non-compliance was recorded in the reporting month.

 

Complaint and Prosecution

 

7.4              No environmental complaints and environmental prosecution were received in the reporting month.

 

7.5              The ET will keep track on the EM&A programme to ensure compliance of environmental requirements and the proper implementation of all necessary mitigation measures.

 

Recommendations

 

7.6              According to the environmental audit performed in the reporting month, the following recommendations were made:

 

Waste/ chemical management
·    To avoid the accumulation of general refuse.