Contents

                        executive Summary                                                             

1                      Introduction                                                                          

1.1                   Purpose of the Report                                                     

1.2                   Structure of the Report                                                

2                      Project Information                                                          

2.1                   Project Background                                                        

2.2                   General Site Description                                                

2.3                   Project Organization and Management Structure        

2.4                   Construction Activities Undertaken during the Reporting Period   

2.5                   Status of Environmental Approval Documents 

3                      EM&A RequiremEnts                                                             

3.1                   Marine Water Quality Monitoring                              

3.2                   Air-borne Noise Monitoring                                           

4                      Implementation Status on Environmental Mitigation Measures  

5                      Monitoring Results                                                            

5.1                   Site Inspections & Audits                                                 

5.2                   Marine Water Quality Monitoring                              

5.3                   Air-borne Noise Monitoring                                           

5.4                   Waste Management EM&A                                                 

6                      Environmental Non-comformance                             

6.1                   Summary of Environmental Non-Compliance        

6.2                   Summary of Environmental Complaint                    

6.3                   Summary of Environmental Summon and Successful Prosecution     

7                      Future Key Issues                                                                

7.1                   Construction Activities for the Coming Quarter   

7.2                   Solid and Liquid Waste Management Status          

8                      Conclusions                                                                           

 

 

 

Executive Summary

The construction works of the installation of submarine gas pipelines and associated facilities from To Kwa Wan to North Point for former Kai Tak Airport Development (¡§the Project¡¨) commenced on 13 June 2012.  This is the 7th Quarterly Environmental Monitoring and Audit (EM&A) Report presenting the EM&A works carried out during the quarterly period from 1 December 2013 to 28 February 2014 in accordance with the EM&A Manual of the Project ([1]).

During the reporting period, environmental site inspections/ audits were carried out weekly by the representatives of the Contractor and the Environmental Team (ET).  Joint site inspections were conducted on 30 December 2013, 28 January 2014 and 25 February 2014 by the Contractor, the ET, the Resident Engineer (RE) and the Independent Environmental Checker (IEC).  Environmental monitoring activities on marine water quality and air-borne noise have been undertaken in accordance with the requirements of the EM&A programme.  Exceedances of Action and Limit Levels for water quality were recorded in thirty-seven (37) monitoring events.  Following the review of monitoring data and marine works details in accordance with the procedures stipulated in the Event and Action Plan of EM&A Manual, these exceedances were considered to be due to natural variation in water quality characteristic of Hong Kong waters and were unlikely to be due to the Project¡¦s marine works activities.  Environmental performance of the Project complied with the environmental requirements and all necessary mitigation measures were properly implemented.

No non-compliance with EIA recommendations, EP conditions and other requirements associated with the construction of the Project were recorded in this reporting period.  No environmental complaint or environmental summons was received in this quarterly reporting period.




 

1                                             Introduction

ERM-Hong Kong, Limited (ERM) and Mott MacDonald Hong Kong Limited were appointed by the Hong Kong and China Gas Company Limited and McDow-Kaden JV as the Environmental Team (ET) and the Independent Environmental Checker (IEC), respectively, to undertake the Environmental Monitoring and Audit (EM&A) activities for the installation of submarine gas pipelines and associated facilities from To Kwa Wan to North Point for former Kai Tak Airport Development (¡§the Project¡¨).

1.1                                      Purpose of the Report

This is the 7th Quarterly EM&A Report which summarises the impact monitoring results and inspection/audit findings for the EM&A programme during the reporting period from 1 December 2013 to 28 February 2014.

1.2                                      Structure of the Report

The remainder of the report is structured as follows:

Section 2 :  Project Information

summarises the background and scope of the Project, works locations, construction programme, construction works undertaken, project organisation and management structure, and the status of Environmental Permit (EP)/licences over the construction phase of the Project.

Section 3 :  EM&A Requirements

summarises the environmental monitoring and audit requirements including monitoring programmes, monitoring methodologies, monitoring parameters, monitoring frequency, monitoring locations, Action and Limit Levels, Event/Action Plans, environmental mitigation measures as recommended in the approved Environmental Impact Assessment (EIA) report, EP and relevant environmental requirements stated in the Contract Specifications.

Section 4 :  Implementation Status on Environmental Mitigation Measures

summarises the implementation of environmental mitigation measures as recommended in the approved EIA report, EM&A Manual, EP and relevant environmental requirements stated in the Contract Specifications.


Section 5 :  Monitoring Results

summarises the monitoring results obtained in the reporting period and the findings of the weekly site inspection including solid and liquid waste management undertaken within the reporting period.

Section 6 :  Environmental Non-conformance

summarises and review any non-compliance of environmental performance standard, environmental complaints and environmental summons received within the reporting period.

Section 7 :  Future Key Issues

summarises the impact forecast and monitoring schedule for the next reporting period.

Section 8 :  Conclusions

 

2                                             Project Information

2.1                                      Project Background

The Project proposed by the Hong Kong and China Gas Company Limited comprises the construction of a new gas pipeline network from To Kwa Wan to North Point so as to replace the existing one affected by the proposed Cruise Terminal dredging works adjacent to the former Kai Tak runway and the proposed Central Kowloon Route crossing the Kowloon Bay at To Kwa Wan. 

The EIA report (Register No.: AEIAR-153/2010) for the Project was approved by the Director of Environmental Protection (DEP) on 2 August 2010 under the Environmental Impact Assessment Ordinance (EIAO).  Subsequent to the approval of the EIA, an Environmental Permit (EP) (Permit No. EP-401/2010) for the Project was granted by the DEP on 6 October 2010.

2.2                                      General Site Description

The Project involves the construction of the twin submarine gas pipelines across the Victoria Harbour from To Kwa Wan to North Point and the construction of the land gas pipelines and pigging stations for pigging operation at both To Kwa Wan and North Point.  The locations of the project areas and stations are presented in Annex A.

2.3                                      Project Organization and Management Structure

2.3.1                               Project Organization

The EM&A programme will require the involvement of the Hong Kong and China Gas Company Limited, an Environmental Team (ET), an Independent Environmental Checker (IEC) and the Contractor.  The roles and responsibilities of the various parties involved in the EM&A process have been described in the EM&A Manual for this Project and the organization of these parties is presented in Annex B. 

2.3.2                               Key Contact Information

Key contact information of the Project Organization is provided in Annex B.

2.4                                      Construction Activities Undertaken during the Reporting Period

A summary of the major construction activities undertaken in the reporting period is shown in Table 2.1.  The locations of the construction activities are shown in Annex A.  The construction programme of the Project is presented in Annex C.

Table 2.1        Summary of Construction Activities Undertaken in the Reporting Period

Construction Activities Undertaken

Marine works (Submarine Pipeline):

¡P       Completion of the intermediate test of submarine pipeline;

¡P       Completion of the hydrostatic pressure testing on the submarine pipeline;

¡P       Completion of the backfilling 75mm aggregate and conducted corresponding hydrographic survey on 14 December 2013;

¡P       Commencement of G75 rock backfilling from CH1000 to CH1200 approximately; and

¡P       Commencement of armour rock backfilling from CH0000 to CH0750 and from CH2500 to CH3030 approximately.

 

Landmains (To Kwa Wan and North Point):

¡P       Completion of reinstating the affected portion of Imperial Parking.  All landmain within the vicinity of Imperial Parking has been completed;

¡P       Completion of pipe laying at Chi Kiang Street at CH0300 to CH 0310 and at CH0310 to CH0325;

¡P       Completion of pipe laying at San Ma Tau Street at CH1111 to CH1114;

¡P       Completion of reinstating San Ma Tau Street at CH1107 to CH1114; and

¡P       Ongoing trial pit excavation at Hoi Yu Street at CH(NPLL):0000 to CH(NPLL):0015.

¡P       Completion of reinstatement of carriageway at San Ma Tau Street at CH1103 to CH1107;

¡P       Completion of reinstatement of carriageway at North Point Police Station at CH3134 to CH3162; and

¡P       Completion of excavation and reinstatement of trial pit nos. 39 and 42 at Hoi Yu Street.

Works Area (To Kwa Wan):

¡P       Completion of the intermediate test of pipeline;

¡P       Completion of anodes and associate facilities installation at the deep well; and

¡P      Completion of placing 75 mm aggregate to the riser pipe within To Kwa Wan cofferdam.

Works Area (North Point):

¡P       Trial pit excavation at CH NPLL 0010;

¡P       Completion of the intermediate test of pipeline; and

¡P      Backfilling between CH3134 to CH3160.

2.5                                      Status of Environmental Approval Documents

A summary of the valid permits, licences and notifications on environmental protection for this Project is presented in Table 2.2.

Table 2.2        Summary of Environmental Licensing, Notification and Permit Status

Permit/ Licences/ Notification

Reference

Validity Period

Remarks

Environmental Permit

EP-401/2010

Throughout the Contract

Permit granted on 6 October 2010  

Notification of Commencement of Works

Ref No. 1123/01.01/12/0233/L

Throughout the Contract

-

Water Discharge License (North Point)

WT00012521-2012

Till 31 March 2017

Wastewater discharge licence was issued by EPD on 22 March 2012

Water Discharge License (To Kwa Wan)

WT00012299-2012

Till 30 April 2017

Wastewater discharge licence was issued by EPD on 25 April 2012

Construction Noise Permit (Marine works)

GW-RE0486-12

Till 17 December 2012; Expired; new permit granted

Issued on 20 June 2012

Construction Noise Permit (Marine works)

GW-RE0976-12

Till 9 March 2013; Expired; new permit granted

Issued on 13 November 2012

Construction Noise Permit (Marine works)

GW-RE0193-13

Till 9 April 2013; Expired; new permit granted

Issued on 1 March 2013

Construction Noise Permit (Marine works)

GW-RE0313-13

Till 9 August 2013; Expired; new permit granted

Issued on 27 March 2013

Construction Noise Permit (Marine works)

GW-RE0570-13

Till 25 July 2013; Expired; new permit granted

Issued on 15 June 2013

Construction Noise Permit (Marine works)

GW-RS0761-13

Till 11 September 2013

Issued on 10 July 2013

Construction Noise Permit (Marine works)

GW-RE1014-13

Till 16 December 2013

Issued on 18 September 2013

Construction Noise Permit (Marine works)

GW-RS1115-13

Till 31 December 2013

Issued on 10 October 2013

Construction Noise Permit (Marine works)

GW-RE0069-14

Till 30 April 2014

Issued on 20 January 2014

Chemical Waste Producer Registration

5213-244-M2830-01

Throughout the Contract

Licence approved on 17 February 2012

 

Marine Dumping Permit (Sediment Type 1, Cheung Chau South)

EP/MD/12-125

Till 14 November 2012; Expired; new permit granted

Issued on 15 May 2012

Marine Dumping Permit (Sediment Type 1, Cheung Chau South)

EP/MD/13-102

Till 17 June 2013; Expired; new permit granted

Issued on 17 December 2012

Marine Dumping Permit (Sediment Type 1, Cheung Chau South)

EP/MD/14-028

Till 25 December 2013

Issued on 26 June 2013

Marine Dumping Permit (Sediment Type 1, East Ninepin)

EP/MD/13-012

Till 30 September 2012; Expired

Issued on 29 May 2012

Marine Dumping Permit (Sediment Type 2, East Sha Chau)

EP/MD/13-023

Till 17 July 2012;

Expired; new permit granted

Issued on 15 June 2012

Marine Dumping Permit (Sediment Type 2, East Sha Chau)

EP/MD/13-042

Till 17 August 2012; Expired; new permit granted

Issued on 17 July 2012

Marine Dumping Permit (Sediment Type 2, East Sha Chau)

EP/MD/13-054

Till 20 September 2012; Expired; new permit granted

Issued on 20 August 2012

Marine Dumping Permit (Sediment Type 2, East Sha Chau)

EP/MD/13-078

Till 8 November 2012; Expired; new permit granted

Issued on 8 October 2012

Marine Dumping Permit (Sediment Type 2, East Sha Chau)

EP/MD/13-090

Till 8 December 2012; Expired; new permit granted

Issued on 8 November 2012

Marine Dumping Permit (Sediment Type 2, East Sha Chau)

EP/MD/13-136

Till 21 April 2013; Expired; new permit granted

Issued on 21 March 2013

Marine Dumping Permit (Sediment Type 2, East Sha Chau)

EP/MD/14-004

Till 31 May 2013; Expired

Issued on 30 April 2013

Marine Dumping Permit (Sediment Type 3, East Sha Chau)

EP/MD/12-127

Till 8 September 2012; Expired; new permit granted

Issued on 8 August 2012

Marine Dumping Permit (Sediment Type 3, East Sha Chau)

EP/MD/13-067

Till 24 October 2012; Expired;

Issued on 25 September 2012

3                                             EM&A RequiremEnts

3.1                                      Marine Water Quality Monitoring

3.1.1                               Water Quality Parameters

The parameters measured in situ were:

¡P           Dissolved Oxygen (DO) (% saturation and mg L-1)

¡P           Salinity (ppt)

¡P           Temperature (ºC)

¡P           Turbidity (NTU)

The only parameter to be measured in the laboratory was:

¡P           Suspended solids (SS) (mg L-1)

In addition to the water quality parameters, other relevant data were measured and recorded in Water Quality Monitoring Logs, including monitoring location, time, tidal stages, weather conditions and any special phenomenon or work underway at the construction site that may influence the monitoring results.

3.1.2                               Monitoring Equipment

Table 3.1 summaries the equipment used for the water quality monitoring.

Table 3.1        Equipment used during the Water Quality Monitoring Programme

Equipment

Model

Global Positioning Device

Garmin etrex 10

Water Depth Detector (Echo sounder)

Speedtech Instrument SM-5A

Water Sampler

1510 Kemmerer Water Sampler

Salinity, DO, Temperature Measuring Meter

YSI Pro 2030

Turbidity Meter

HACH Model 2100Q Turbid Meter

 

3.1.3                               Sampling / Testing Protocol

All in situ monitoring instruments were checked, calibrated and certified by the analytical laboratory before use ([2]).  Responses of sensors and electrodes were checked with certified standard solutions before each use. 

Wet bulb calibration for a DO probe was carried out at least once per monitoring day.  A zero check in distilled water was performed with the turbidity probe at least once per monitoring day.  The probe was calibrated with a solution of known NTU.  In addition, the turbidity probe was calibrated at least twice per month to establish the relationship between turbidity readings (in NTU) and levels of suspended solids (in mg L-1).

On-site calibration of equipment was also carried out following the ¡§Guide to On-Site Test Methods for the Analysis of Waters¡¨, BS 1427:1993 to check the responses of sensors and electrodes using certified standard solutions before each use.  Sufficient stocks of spare parts were maintained for replacements when necessary.  Backup monitoring equipment was made available so that monitoring can proceed uninterrupted even when equipment is under maintenance, calibration etc.

Water samples for SS measurements were collected in high density polythene, packed in ice (cooled to 4 ºC without being frozen) and delivered to the analytical laboratory as soon as possible after collection.

3.1.4                               Laboratory Measurement and Analysis

Analysis of SS was carried out in a HOKLAS accredited laboratory ([3]).  Water samples of about 1 L were collected at the monitoring stations for carrying out the laboratory suspended solids determination.  The SS determination work started within 24 hours after the collection of the water samples.  The SS analyses followed the standard method APHA 2540D with a detection limit of 1 mg L-1 as described in APHA Standard Methods for the Examination of Water and Wastewater, 21st Edition, unless specified.

Quality Assurance/ Quality Control (QA/ QC) details (such as blank, spike recovery, number of duplicate samples per batch etc) were provided in Monthly EM&A Reports in accordance with requirements of HOKLAS.

3.1.5                               Sampling Depths & Replication

Each station was sampled and measurements/ water samples were taken at three depths, namely, 1 m below water surface, mid-depth and 1 m above sea bed, except where the water depth was less than 6 m, the mid-depth station may be omitted.  For stations that were less than 3 m in depth, only the mid-depth sample was taken.

For in situ measurements, duplicate readings were made at each water depth at each station.  Duplicate water samples were collected at each water depth at each station.

3.1.6                               Monitoring Locations and Frequency

Impact water quality monitoring was conducted during the marine works period at the monitoring stations listed in Table 3.2 and shown in Annex D1.


Table 3.2        Water Quality Monitoring Stations

Monitoring Station

Area

Easting

Northing

WM1

Tai Wan WSD Seawater Intake

837818.8258

818059.9297

WM2

City Garden

838278.6734

817209.9656

WM3

Provident Centre

838443.5777

817233.5234

WM4

North Point Government Offices

839536.1868

817215.6195

WM5

Quarry Bay WSD Seawater Intake

839781.4231

817107.8097

WM6

Taikoo Place

840026.6594

817000

C1

Control Station

836625.9264

817422.6424

C2

Control Station

836747.9445

816670.1762

C3

Control Station

840810.5828

817825.8986

C4

Control Station

840432.5877

816920.1674

In accordance with the EM&A Manual, marine water quality monitoring were conducted at six Water Sensitive Receivers (WM1, WM2, WM3, WM4, WM5 and WM6) as well as four Control stations (C1, C2, C3 and C4) (Table 3.2) at a frequency of three times a week during the marine works period for the Project.  Monitoring was undertaken at mid-flood and mid-ebb tides during each monitoring day.  The interval between two sets of consecutive monitoring was not less than 36 hours.

For scheduling, reference were made to the predicted tides at Quarry Bay, which is the tidal station nearest to the Project Site, published on the website of the Hong Kong Observatory ([4]).  Schedule for impact monitoring has been submitted to the Contractor, Independent Environmental Checker (IEC), Engineer Representative (ER) and Environmental Protection Department (EPD) prior to the commencement of the monitoring works.

3.1.7                               Water Quality Compliance

Water quality monitoring was evaluated against Action and Limit Levels.  The proposed Action and Limit Levels which are determined from the baseline water quality monitoring results are shown in Table 3.3.

In the event that the levels are exceeded, appropriate actions in the Event and Action Plan (Annex F1) should be undertaken and a review of works will be carried out by the Contractor(s).


Table 3.3        Action and Limit Levels for Water Quality (e)

Parameters

Action Level

Limit Level

DO in mg L-1

(Surface, Middle & Bottom)

WSD Seawater Intakes
2 mg L-1

 

Other Impact Monitoring Stations
5 percentile of baseline data, i.e. 7.79 mg L-1

Surface and Middle
WSD Seawater Intake
2 mg L-1

 

Other Impact Monitoring Stations
4 mg L-1 or 1 percentile of baseline data, i.e. 7.46 mg L-1

 

Bottom

 

Impact Monitoring Stations
2 mg L-1 or 1 percentile of baseline data, i.e. 7.66 mg L-1

 

SS in mg L-1

(depth-averaged)

WSD Seawater Intakes
10 mg L-1

 

Other Impact Monitoring Stations

95 percentile of baseline data, i.e. 5.13 mg L-1
or

120% of upstream control station at the same tide of the same day

 

WSD Seawater Intake
10 mg L-1

 

Other Impact Monitoring Stations
99 percentile of baseline data, i.e. 5.53 mg L-1

or
130% of upstream control station at the same tide of the same day

 

Turbidity (depth-averaged)

WSD Seawater Intakes

10 NTU

 

Other Impact Monitoring Stations

95 percentile of baseline data, i.e. 3.71 NTU

or

120% of upstream control station at the same tide of the same day

 

WSD Seawater Intakes

10 NTU

 

Other Impact Monitoring Stations

99 percentile of baseline data, i.e. 4.03 NTU

or

130% of upstream control station at the same tide of the same day

 

Notes:

(a)     ¡§Depth-averaged¡¨ is calculated by taking the arithmetic means of the readings of the three depths.

(b)     For DO measurement, non-compliance occurs when monitoring result is lower than the limits.

(c)     For SS and turbidity, non-compliance of water quality results when monitoring results is higher than the limits.

(d)     All the figures given in the table are used for reference only the EPD may amend the figures whenever necessary.

(e)     The levels of SS, Turbidity and DO were confirmed to be similar amongst monitoring stations by statistical analysis.  Therefore, the calculation of Action and Limit Levels was based on baseline monitoring data collected from all monitoring stations and the same set of Action and Limit Levels will be adopted for the Impact Monitoring Stations (ie not including the WSD Seawater Intakes and Control Stations).

3.2                                      Air-borne Noise Monitoring

3.2.1                               Monitoring Location

In accordance with the EM&A Manual, monitoring of construction noise impact should be conducted at the designated monitoring stations.  The construction noise monitoring location for this Project is listed in Table 3.6 and is shown in Annexes E1 and E2.

Table 3.6        Noise Monitoring Location

Monitoring Station

Area

Description

SCH02

To Kwa Wan

CCC Kei To Secondary School

FSQ

North Point

North Point Fire Services Married Quarters

 

3.2.2                               Monitoring Parameter and Frequency

Weekly construction noise monitoring was conducted in accordance with the requirements stipulated in the EM&A Manual.  Thirteen sets of noise monitoring were carried out within this quarterly reporting period.

The construction noise levels were measured in terms of A-weighted equivalent continuous sound pressure level (Leq) in decibels dB(A). Leq (30min) were used as the monitoring parameter for the period in between 0700 ¡V 1900 hours on normal weekdays.  In order to obtain supplementary information for data auditing, two statistical sound levels L10 and L90 (ie the levels exceeded for 10 and 90 percent of the time, respectively), were also recorded during the monitoring for reference.  The measured noise levels were logged every 5 minutes throughout the impact monitoring period.

3.2.3                               Action and Limit Levels

The Action and Limit levels for noise monitoring during different monitoring periods are summarised in Table 3.7.

Table 3.7        Summary of Action and Limit Levels for Construction Noise

Time Period

Action Level

Limit Level (dB(A))

0700-1900 hrs on normal weekdays

When one documented compliant is received

75*

1900-2300 hrs on normal weekdays

When one documented compliant is received

70

Restricted hours (2300-0700 hrs)

When one documented compliant is received

55

Note:

*   70 dB(A) for schools and 65 dB(A) during school examination periods.

3.2.4                               Monitoring Equipment and Methodology

Construction noise measurements were conducted in accordance with the calibration and measurement procedures as stated in Annex ¡V General Calibration and Measurement Procedures of Technical Memorandum on Noise from Construction Work other than Percussive Piling (GW-TM) issued under the Noise Control Ordinance (NCO) (Cap. 400).

The sound level meters and calibrator used for the noise measurement, as listed in Table 3.8, complies with IEC 651: 1979 and 804:1985 (Type 1) specification.  The calibration certificates of the sound level meters and calibrator were shown in Monthly EM&A Reports.

Table 3.8        Noise Monitoring Equipment

Monitoring Station

Monitoring Equipment (Sound Level Meter and Calibrator)

SCH02

Rion NL-18 (S/N 00360030), NC-73 (S/N 10997142)

FSQ

Rion NL-31 (S/N 00410224), NC-73 (S/N 10997142)

Immediately prior to and following the noise measurements, the accuracy of the measurement equipment was checked using an acoustic calibrator generating a known sound pressure level at a known frequency. 

3.2.5                               Event and Action Plan

The Event and Action Plan (EAP) for noise monitoring is presented in Annex F2.

4                                             Implementation Status on Environmental Mitigation Measures

The Contractor has implemented environmental mitigation measures and requirements as stated in the EIA Report, EP and EM&A Manual.  The implementation status during the reporting period is summarised in Annex G.

 

5                                             Monitoring Results

5.1                                      Site Inspections & Audits

Weekly site inspections were conducted by representatives of the Contractor and the ET on 6, 14, 18 and 27 December 2013; 9, 16 and 23 January 2014; and 7, 13 and 21 February 2014.  In addition, joint site inspections were conducted by the Contractor, the ET, the Resident Engineer (RE) and the IEC on 30 December 2013 as well as 28 January and 25 February 2014. 

Major observations during the reporting period were summarised as follows:

 

6 December 2013

 

¡P      North Point Land-based Site:

o   A chemical waste drum was not placed on top of a drip tray.  The Contractor was reminded to place it properly in a drip tray to prevent any chemicals or oil from contaminating the surrounding soil.

14 December 2013

 

¡P      To Kwa Wan Construction Site:

o   Excavated materials were not fully covered by tarpaulin sheet.  The Contractor was reminded to cover it fully by the end of the working day.

 

¡P      North Point Land-based Site:

o   A chemical waste container was not placed on a drip tray.  The Contractor was reminded to place it properly on a drip tray to prevent any chemicals or oil from contaminating the surrounding soil.

o   Excavated materials were not fully covered by tarpaulin sheet.  The Contractor was reminded to cover it fully by the end of the working day.

18 December 2013

¡P      To Kwa Wan Construction Site:

o   Excavated materials were not fully covered by tarpaulin sheet.  The Contractor was reminded to cover it fully by the end of the working day.

o   Trash was observed in non-designated areas of the works area.  The Contractor was reminded to dump trash onto the designated locations and keep the works area clean.


¡P      North Point Land-based Site:

o   Excavated materials were not fully covered by tarpaulin sheet.  The Contractor was reminded to cover it fully by the end of the working day.

 

27 December 2013

 

¡P      To Kwa Wan Construction Site:

o   Excavated materials were not fully covered by tarpaulin sheet.  The Contractor was reminded to cover it fully by the end of the working day.

o   Stagnant water was observed inside a drip tray.  The Contractor was reminded to clear away the stagnant water appropriately.

o   Stockpile of excavated materials was found close to the edge of the works area next to the sea, with the potential to be directly deposited into the sea.  The Contractor was recommended to erect barriers or other mitigation measures as appropriate to avoid direct deposition of excavated materials into the sea.

o   Sandbags were recommended to put along the seafront of the works area to prevent excavated materials nearby from running into the sea.

 

¡P      North Point Land-based Site:

o   Trash was observed inside the silt curtain of the cofferdam.  The Contractor was reminded to clean up the area regularly to maintain good hygiene.

o   Stagnant water was accumulated in a trench of the works area.  Mosquito repellent was advised to apply regularly.

 

30 December 2013

 

¡P      To Kwa Wan Construction Site:

o   Oil stain was observed on pavement leaked from excavation.  The Contractor was advised to carry out appropriate actions accordingly.

o   Pipes and various equipment were seen to be placed very close to the tree in TTA.  The Contractor was advised to maintain an appropriate clear zone from any trees.

 

¡P      North Point Land-based Site:

o   A chemical container was not placed on a drip tray.  The Contractor was reminded to place it properly or liaise with relevant parties.

o   Stagnant water was accumulated in a trench of the works area.  Mosquito repellent was advised to apply regularly.

 

9 January 2014

 

¡P      To Kwa Wan Land-based Site:

o   Excavated materials were not fully covered by tarpaulin sheet.  The Contractor was reminded to cover it fully by the end of the working day.

o   An oil drum was found not placed in a drip tray.  The Contractor was reminded to place it appropriately to avoid contamination of the surrounding soil by oil.

16 January 2014

 

¡P      To Kwa Wan Land-based Site:

o   Trash was observed in the works area.  The Contractor was reminded to dump trash in designated areas only and to maintain good house-keeping practice.

o   Excavated materials were not fully covered by tarpaulin sheet.  The Contractor was reminded to cover it fully by tarpaulin sheet or to check if they could be cleared from the site.

23 January 2014

¡P      To Kwa Wan Land-based Site:

o   Excavated materials were not fully covered by tarpaulin sheet.  The Contractor was reminded to cover it fully by tarpaulin sheet or to check if they could be cleared from the site.

o   Nozzle was found placed outside the drip tray.  Immediate rectification was done by the Contractor by placing it appropriately inside the drip tray to ensure no oil or grease would contaminate the surrounding soil.

o   Large patch of oil stain was found on the soil in the construction site.  The Contractor was reminded to treat them as chemical waste and dispose of appropriately.

o   Stagnant water was found accumulating next to the cofferdam.  The Contractor was advised to spray mosquito repellant more regularly and to fill it flat with sand to avoid water from accumulating.

o   Large amount of stagnant water was accumulated in one of the sedimentation tanks on site.  The Contractor was urged to empty it as soon as possible.

o   Plug was found missing for one of the drip trays.  The Contractor was reminded to replace it as soon as possible.

 

28 January 2014

 

¡P      To Kwa Wan Land-based Site:

o   Runoff was generated from rock-cutting of seawall blocks.  The Contractor was advised to carry out rock-cutting at a more appropriate location to avoid direct discharge of water from construction site to the sea.  More sandbags were needed to be placed at the cofferdam to reduce any direct discharge into the surrounding waters.  Immediate rectification had been done by the Contractor by using sedimentation tanks to treat the runoff. 

o   It was observed that a sheet pile had been removed at the work front of the land-based site.  The Contractor was advised to place more sandbags or carry out other appropriate measures to avoid any construction materials from entering the sea.

 

7 February 2014

 

¡P      Construction works were not undertaken in both To Kwa Wan and North Point construction sites during site inspection.

13 February 2014

 

¡P      To Kwa Wan Land-based Site:

o   Excavated materials were not covered by tarpaulin sheet.  The Contractor was advised to cover them fully at the end of the working day.

o   More sand bags were advised to put at the periphery of the cofferdam to prevent any mud or rubbles from running into the sea directly.

o   Stagnant water was found accumulating in the drip tray containing the chemical waste drum.   The Contractor was reminded to clear stagnant water regularly.

21 February 2014

¡P      To Kwa Wan Land-based Site:

o   Large amount of floating rubbish was found accumulated in between the silt curtain at the cofferdam.  The Contractor was urged to clear them in timely manner.

o   Stagnant water was accumulated in the drip tray of various chemical waste drums.  The Contractor was urged to clear away the stagnant water as soon as possible.

o   The Contractor was recommended to put more sand bags along the seafront of the works site to prevent any debris from running into the sea directly.

 

25 February 2014

 

¡P      To Kwa Wan Land-based Site:

o   Stagnant water was observed in a number of drip trays at site.  The Contractor was reminded to clear them in timely manner.

o   A plank or more sandbags should be put at the seafront of TKW works areas to prevent any direct runoff of rubbles.

o   Environmental Permit was not displayed at the site entrance.  The Contractor was reminded to display it properly.

o   Ground water was accumulated at the site.  The Contractor was suggested to fill the trench up to avoid direct discharge / runoff of groundwater into the sea.

 

 

5.2                                      Marine Water Quality Monitoring

In accordance with the requirements described in the EM&A Manual, marine water quality monitoring was conducted during periods when marine works were scheduled to be undertaken.  Impact monitoring was undertaken three times per week from 1 December 2013 to 28 February 2014, except during the period of 1 to 3 February 2014 when no marine works were undertaken.  During the period of impact monitoring, weather condition was generally fine.

Monitoring results are presented graphically in Annex D2 ¡V D6 and key observations are described below.

DO levels from surface, mid-depth and bottom waters were generally similar amongst Control, Impact and WSD Seawater Intake stations, and DO levels were variable throughout the monitoring period which represented natural background fluctuation in water quality.

Quarterly mean DO levels from surface, mid-depth and bottom waters of Impact Stations were significantly lower than those recorded in Baseline Water Quality Monitoring in March 2012 (p < 0.001).  Quarterly mean DO levels from surface, mid-depth and bottom waters of Control Stations were also significantly lower than those recorded in Baseline Water Quality Monitoring in March 2012 (p < 0.001).  When comparing quarterly mean DO levels from surface, mid-depth and bottom waters between Impact Stations and Control Stations, no significant difference was found (p > 0.05).  Therefore, it is considered that the significantly lower DO levels recorded in this quarterly period (ie compared to the baseline levels) are more likely to be representing natural background fluctuation in water quality rather than indicating any unacceptable water quality impacts from the Project since the lower DO levels were recorded at the Impact Stations as well as the Control Stations, which are far away from the marine works locations that should not be affected by the marine works. 

Similar to DO levels, turbidity and SS levels were generally similar amongst all stations and variable throughout the monitoring period.  High levels of turbidity and SS were occasionally recorded during both mid-ebb and mid-flood tides.  Such fluctuations were also observed during baseline monitoring and are considered to be sporadic events and characteristic of water quality in this area of Hong Kong.

Quarterly mean turbidity and SS levels of Impact Stations were significantly higher than those recorded in Baseline Water Quality Monitoring in March 2012 (p < 0.001).  Quarterly mean turbidity and SS levels of Control Stations were also significantly higher than those recorded in Baseline Water Quality Monitoring in March 2012 (p < 0.001).  

Comparison of quarterly mean depth-averaged turbidity levels between Impact and Control Stations indicated that turbidity levels at Control Stations were similar to those recorded at Impact Stations (p > 0.05).  Therefore, it is considered that the significantly higher turbidity levels recorded in this quarterly period (ie compared to the baseline levels) are more likely to be representing natural background fluctuation in water quality rather than indicating any unacceptable water quality impacts from the Project since the higher turbidity levels were recorded at the Impact Stations as well as the Control Stations, which are far away from the marine works locations that should not be affected by the marine works. 

Comparison of quarterly mean depth-averaged SS levels between Impact and Control Stations indicated that SS levels at Control Stations were significantly higher than those recorded at Impact Stations (p < 0.001).  Therefore, it is considered that the significantly higher SS levels recorded in this quarterly period (ie compared to the baseline levels) are more likely to be representing natural background fluctuation in water quality rather than indicating any unacceptable water quality impacts from the Project since the higher SS levels were recorded at the Control Stations, which are far away from the marine works locations that should not be affected by the marine works.

A total of thirty-seven (37) exceedances were recorded and dated on 3, 5, 7, 10, 12, 14, 17, 19, 21, 24, 26, 28 and 31 December 2013; 2, 4, 7, 9, 11, 14, 16, 18, 21, 23, 25, 28 and 30 January 2014; and 4, 6, 8, 11, 13, 15, 18, 20, 22, 25 and 27 February 2014.  Exceedances in the Action and Limit Levels of surface, mid-depth and bottom DO were observed.  It is considered that the exceedances in DO levels are more likely to be representing natural background fluctuation in water quality rather than indicating any unacceptable water quality impacts from the Project since the levels of DO at the Impact Stations where exceedances were recorded were similar to those at the Control Stations.  In addition, some exceedances were recorded when no marine works were being undertaken for the Project (eg during mid-flood tide on 7 December 2013; 4 and 8 February 2014, during mid-ebb tide on 10, 14 and 26 December 2013; 7 and 9 January 2014; 6 and 27 February 2014 and during both mid-ebb and mid-flood tides on 24 December 2013; 18 and 30 January 2014; 15, 18 and 20 February 2014).

Exceedances in the Action and Limit Levels of depth-averaged turbidity and SS levels were also recorded.  As explained above, high level of turbidity and SS in this area are considered to be sporadic and characteristic of water quality in this area of Hong Kong.  The observed exceedances were thus not considered to be of environmental concern.

Mitigation measures for marine works were implemented properly in accordance with requirements stipulated in the EIA Report, EP and EM&A Manual.  Following the review of monitoring data and marine works details in accordance with the procedures stipulated in the Event and Action Plan of the EM&A Manual, these exceedances were considered to be due to natural background variation in water quality characteristic and were unlikely to be due to the Project¡¦s marine works activities.

5.3                                      Air-borne Noise Monitoring

30-minute construction noise measurements were carried out on 4, 11, 18 and 27 December 2013; 3, 8, 15, 21 and 29 January 2014; and 7, 12 and 19 February 2014 at monitoring station FSQ and on 5, 12, 19 and 24 December 2013; 2, 9, 16, 23 and 30 January 2014; and 6, 13, 20 and 27 February 2014 at monitoring station SCH02 during normal working hours in weekdays of the quarterly period.  No exceedances of Action and Limit Levels for noise monitoring during normal working hours were recorded. 

The monitoring results together with graphical presentations are presented in Annex E3 ¡V E8.  The local impacts observed near the monitoring stations of SCH02 and FSQ were due to traffic noise from Sung On Street and Island Eastern Corridor, respectively.

5.4                                      Waste Management EM&A

Waste generated from this Project includes inert construction and demolition (C&D) materials, non-inert C&D materials.  Reference has been made to the Monthly Summary Waste Flow Table prepared by the Contractor (Annex H). 

The waste statistics provided in this section represent the cumulative quantity of wastes generated from all sites in this Project.  With reference to relevant handling records and trip tickets of this Project, the quantities of different types of waste generated in the reporting months of this quarterly period are summarised in Table 5.1.  The inert C&D materials and general refuse generated from the Project were disposed of at Tseung Kwan O Area 137 Fill Bank and SENT Landfill, respectively.

Table 5.1        Quantities of Waste Generated from the Project for all Sites

Month / Year

Quantity

C&D Materials (inert) (a)

C&D Materials (non-inert) (b)

Chemical Waste

Marine Deposit

Type 1

Type 2

Type 3

December 2013

231.54 tonnes(c)

2.91 tonnes (d)

0 L

0 m3

0 m3

0 m3

January 2014

231.54 tonnes(e)

3.46 tonnes (f)

0 L

0 m3

0 m3

0 m3

February 2014

115.00 tonnes(g)

4.25 tonnes (h)

0 L

0 m3

0 m3

0 m3

Notes:

(a)   Inert C&D materials include bricks, concrete, building debris, rubble and excavated soil. 

(b)   The non-inert C&D materials consisted of general refuse and vegetation/ rubbish.

(c)    231.54 tonnes of inert C&D Materials were generated in December 2013.  21.09 tonnes were reused in the Contract.  210.45 tonnes have been disposed of as Public Fill at Tseung Kwan O Area 137 Fill Bank.

(d)   The non-inert C&D materials consisted of 2.91 tonnes of general refuse generated in December 2013.

(e)   231.54 tonnes of inert C&D Materials were generated in January 2014.  126.6 tonnes were reused in the Contract.  104.94 tonnes have been disposed of as Public Fill at Tseung Kwan O Area 137 Fill Bank.

(f)    The non-inert C&D materials consisted of 3.46 tonnes of general refuse generated in January 2014.

(g)   115 tonnes of inert C&D Materials were generated in February 2014.  75.92 tonnes were reused in the Contract.  30 tonnes were stored as stockpile at site.  9.08 tonnes have been disposed of as Public Fill at Tseung Kwan O Area 137 Fill Bank.

(h)   The non-inert C&D materials consisted of 4.25 tonnes of general refuse generated in February 2014.

6                                             Environmental Non-comformance

6.1                                      Summary of Environmental Non-Compliance

No non-compliance of EIA/ EM&A/ EP/ legislative requirements was recorded during the reporting period.

6.2                                      Summary of Environmental Complaint

No complaint was received during the reporting period.  The cumulative compliant/summons/prosecution log is shown in Annex I.

6.3                                      Summary of Environmental Summon and Successful Prosecution

No summons/ prosecution was received during the reporting period.  The cumulative compliant/summons/prosecution log is shown in Annex I.

 

7                                             Future Key Issues

7.1                                      Construction Activities for the Coming Quarter

Works to be undertaken for the coming reporting quarter are summarised in Table 7.1.

Table 7.1        Construction Works to be undertaken in the Coming Quarter

Work to be taken

¡P       Partial installation of ICCP system;

¡P       Armour rock backfilling;

¡P       Seawall reinstatement; and

¡P      Pipeline laying.

Potential environmental impacts arising from the above construction activities are mainly associated with dust, construction noise, site runoff, marine water quality and waste management issues.  The most updated construction programme for the Project is presented in Annex C.

7.2                                      Solid and Liquid Waste Management Status

As the major construction works in the coming quarter are armour rock backfilling and seawall reinstatement, waste generated from this Project for the coming quarter will include inert and non-inert C&D materials.  Part of the inert C&D materials will be stockpiled on site for reuse and the remaining will be disposed of at Tseung Kwan O Area 137 Fill Bank.  Chemical waste will be stored at designated area and collected by a licensed collector.  Surface runoff, sewage and wastewater will be reduced using proper site management such as the use of sedimentation tanks with sufficient capacity, vehicle and plant cleaning before leaving a construction site, etc (detailed in Annex G).  General refuse generated from the Project will be disposed of SENT Landfill.

8                                             Conclusions

This 7th Quarterly EM&A Report presents the EM&A programme undertaken during the reporting period from 1 December 2013 to 28 February 2014 in accordance with EM&A Manual and requirements of the EP (EP-401/2010). 

Marine works were undertaken during this quarterly period and construction phase water quality monitoring was conducted in accordance with the requirements described in the EM&A Manual.  Exceedances of Action and Limit Levels for water quality were recorded in thirty-seven (37) monitoring events from 1 December 2013 to 28 February 2014.  It is considered that the exceedances were sporadic events and represented natural background fluctuation in water quality.

30-minute construction noise measurements were carried out at the monitoring stations SCH02 and FSQ during normal weekdays of the reporting period.  No exceedance of Action or Limit Level was recorded during the reporting period.

Weekly site inspections were conducted in the reporting period.  Joint site inspections were conducted on 30 December 2013, 28 January 2014 and 25 February 2014 by the Contractor, the ET, the RE and the IEC.  Most of the mitigation measures recommended in the EIA/ EM&A manual/ EP were implemented by the Contractor.  Follow-up actions for the observed environmental deficiency during the site inspections were taken as reported by the Contractor and observed in the next weekly site inspection conducted.

No non-compliance event was recorded during the reporting period.

No complaint and summons/prosecution was received during the reporting period.

The EM&A programme is considered effective in reflecting the environmental conditions at the site.  The site inspection results also indicated that the Project has no unacceptable environmental impacts and the mitigation measures were effectively implemented.  The ET will keep track of the EM&A programme to ensure compliance of environmental requirements and the proper implementation of all necessary mitigation measures in the coming periods.

Change to the monitoring programme is not considered to be necessary at this stage.  The monitoring programme will be evaluated as appropriate in the next reporting period.


 



([1])        Mott MacDonald (2010).  Installation of Submarine Gas Pipelines and Associated Facilities from To Kwa Wan to North Point for Former Kai Tak Airport Development: Environmental Monitoring and Audit Manual.

([2])        Baseline water quality monitoring was undertaken by the HOKLAS accredited laboratory ETS-Testconsult Ltd.

([3])        Marine water quality monitoring was undertaken by the HOKLAS accredited laboratory ETS-Testconsult Ltd.  

([4])       Hong Kong Observatory (2012) http://www.hko.gov.hk/tide/eQUBtide.htm [Accessed in March 2012]