Contents

                        Executive Summary                                                             

1                      Introduction                                                                          

1.1                   Purpose of the Report                                                     

1.2                   Structure of the Report                                                

2                      Project Information                                                          

2.1                   Background                                                                           

2.2                   Site Description                                                                    

2.3                   Status of Environmental Approval Documents 

3                      Water Quality Monitoring Requirements               

3.1                   Monitoring Locations                                                       

3.2                   Monitoring Parameters                                                   

3.3                   Monitoring Equipment and Methodology               

4                      Implementation Status of Environmental Mitigation Measures  

5                      Post Project Monitoring Results                              

6                      Conclusion                                                                             

 


LIST OF TABLES

Table 2.1        Summary of Environmental Licensing, Notification, Permit and Reporting Status

Table 3.1        Water Quality Impact Stations

Table 3.2        Equipment Used during the Post Project Water Quality Monitoring

 

 

LIST OF ANNEXES

Annex A

Post Project Water Quality Monitoring Schedule

Annex B

Calibration Reports of Multi-parameter Sensor

Annex C

QA/QC Results for Suspended Solids Testing

Annex D

Post Project Water Quality Monitoring Results

 

 

Executive Summary

The submarine cable installation works for the Asia Submarine-cable Express (ASE) cable system commenced in January 2014 and were completed in February 2014.  This is the Post Project Water Quality Monitoring Report (Zone A) presenting results and findings of the post project water quality monitoring conducted during the period from 10 to 15 March 2014 in accordance with the Updated Environmental Monitoring and Audit Manual (Updated EM&A Manual).

Water Quality

Three monitoring events (days) were scheduled between 10 and 15 March 2014, at monitoring stations located in Zone A, to replicate monitoring activities conducted for baseline data gathering in accordance with the  Updated EM&A Manual.  Monitoring events at all designated monitoring stations in Zone A were performed on schedule.

In general, the Dissolved Oxygen (DO) levels recorded during the post project monitoring period were recorded mostly higher than results obtained during the baseline update monitoring period.  Turbidity and Suspended Solid (SS) levels observed in the post project monitoring period were observed lower than the results recorded during the baseline update monitoring period at all designated stations.  After detailed analyses, it is considered that the overall changes in DO, Turbidity and SS were driven by natural fluctuations. 

Conclusion

Upon completion of the cable installation, the overall water quality at the impact stations in Zone A was found similar to that at the control station and was recorded higher in DO and lower in Turbidity and SS when compared with the baseline data.  Given the fact that the control station is sufficiently far away from the cable alignment and water quality at this station could not be affected by the Project, it is concluded that the overall changes in DO, Turbidity and SS levels during the post-project monitoring period at all designated stations including the control station are likely to represent a natural phenomenon.  It is considered that no deterioration of water quality was observed and the impacts from the Project works on water quality are negligible.

 


1                                             Introduction

ERM-Hong Kong, Limited (ERM) was appointed by NTT Com Asia (NTTCA) as the Environmental Team (ET) to implement the Environmental Monitoring and Audit (EM&A) programme for the re-installation of a damaged section of the Asia-Submarine-cable Express (ASE) telecommunication cable (thereinafter called the ¡§Project¡¨).  The ASE cable is approximately 7,200 km in length, connecting Japan and Singapore with branches to the Philippines, Hong Kong SAR (HKSAR) and Malaysia.

1.1                                      Purpose of the Report

This is the Post Project Water Quality Monitoring Report (Zone A), which summarises the results of post project water quality monitoring as part of the EM&A programme during the reporting period from 10 to 15 March 2014.  The post project monitoring results have been compared to the baseline water quality update monitoring results in order to investigate any impact of the Project marine works on water quality in the vicinity of the Project site.

1.2                                      Structure of the Report

The structure of the Report is as follows:

Section 1 :  Introduction

Provides details of the background, purpose and report structure.

 

Section 2 :  Project Information

Summarises background and scope of the project, the repair works undertaken and the status of Environmental Permits/Licenses during the reporting period.

 

Section 3 :  Water Quality Monitoring Requirements

Summarises the monitoring parameters, monitoring programmes, monitoring methodologies, monitoring frequency, and monitoring locations.

 

Section 4 :  Implementation Status of Environmental Mitigation Measures

Summarises the implementation of environmental protection measures during the reporting period.

 

Section 5 :  Post Project Monitoring Results

Summarises the monitoring results obtained in the reporting period for Zone A.

 

Section 6 :  Conclusions

Presents the key findings of the post project monitoring results.

 

2                                             Project Information

2.1                                      Background

In 2012/2013, NTT Com Asia (NTTCA) installed a telecommunication cable (Asia Submarine-cable Express (ASE) cable) of approximately 7,200 km in length, connecting Japan and Singapore with branches to the Philippines, Hong Kong SAR (HKSAR) and Malaysia, with marine works in HK waters initially completed in January 2013.  NTTCA was also responsible for securing the approval to land the ASE cable in Tseung Kwan O, Hong Kong SAR (HKSAR), the landing site for a number of submarine cables, and the landing site is at a Beach Manhole (BMH) after which the cable ultimately connects with a Data Centre in Tseung Kwan O (TKO) Industrial Estate.  .  From Tseung Kwan O, the cable extends westward approaching the Tathong Channel.  Near to Cape Collinson, the cable is approximately parallel to the Tathong Channel until north of Waglan Island where it travels eastward to the boundary of HKSAR waters and enters the South China Sea.  The total length of cable in Hong Kong SAR waters is approximately 33.5 km.  A map of the cable route is presented in Figure 2.1.

A Project Profile (PP-452/2011) which includes an assessment of the potential environmental impacts associated with the installation of the submarine telecommunications cable system was prepared and submitted to the Environmental Protection Department (EPD) under section 5.(1) (b) and 5.(11) of the Environmental Impact Assessment Ordinance (EIAO) for the application for Permission to apply directly for Environmental Permit (EP).  EPD subsequently issued an Environmental Permit (EP- 433/2011). 

Pursuant to Condition 2.4 of EP- 433/2011, an environmental monitoring and audit (EM&A) programme, as set out in the Environmental Monitoring and Audit Manual (EM&A Manual([1])) is required for this Project.  Baseline data were collected prior to the start of cable installation works in 2012 and EM&A was conducted throughout the cable installation and after its completion in early 2013. as required in the EM&A Manual. 

Upon inspection in October 2013 the ASE cable was found to be damaged and a section within Zone A (see Figure 2.2) required re-installation.  The EM&A programme are therefore required to resume for the cable installation works in Hong Kong Waters and the EM&A Manual was updated to reflect these new repair works and produce the Updated EM&A Manual. 

New baseline water quality ¡¥update¡¦ monitoring was conducted prior to the start of re-installation works, in early November 2013, and results are summarised in the ¡¥Baseline Water Quality Monitoring Update Report (Zone A)¡¦of December 2013. 

Impact monitoring started on 12 January 2014, when the cable re-installation works commenced in Zone A.  The initial cable installation works were completed on 5 February 2014 and the impact water quality monitoring ceased subsequently.  The impact water quality monitoring results were summarized in the following reports:

¡P             2014 First Weekly Impact Water Quality Monitoring Report (Zone A);

¡P             2014 Second Weekly Impact Water Quality Monitoring Report (Zone A);

¡P             2014 Third Weekly Impact Water Quality Monitoring Report (Zone A); and

¡P             2014 Forth Weekly Impact Water Quality Monitoring Report (Zone A).

All marine works for the cable repair works were completed in early February 2014 and final confirmation of completion of the work after testing of the cable was given on Tuesday 4 March 2014.  In accordance with the Updated EM&A Manual, post project water quality monitoring should comprise sampling on three occasions (days) within three weeks of completion of the marine installation works.  

This Post Project Water Quality Monitoring Report (Zone A) presents the results and findings from the 2014 post project monitoring, conducted in the monitoring period 10-15 March 2014.  It should be noted that cable repair works were only carried out in Zone A (Cape Collinson) and results of the post project monitoring data have therefore been compared against the results of the baseline water quality update monitoring in Zone A.

2.2                                      Site Description

The cable installation works for the damaged section of the ASE cable were conducted near TKO in Zone A (Figure 2.2).

2.3                                      Status of Environmental Approval Documents

A summary of the relevant permits, licences and reports on marine water quality for this Project is presented in Table 2.1.

Table 2.1        Summary of Environmental Licensing, Notification, Permit and Reporting Status

Permit / Licence / Notification / Report

Reference

Validity Period

Remarks

Environmental Permit

EP 433/2011

Throughout the construction and operation stages

Granted on 20 December 2011

EM&A Manual

-

Throughout the construction and operation stages

 

Submitted on 18 September 2012.  Superseded by Updated EM&A Manual

Updated EM&A Manual

-

Throughout the construction and operation stages

Submitted in December 2013

Baseline Water Quality Monitoring Update Report (Zone A)

-

n/a

Submitted on 5 December 2013

2014 First Weekly Impact Water Quality Monitoring Report (Zone A)

 

n/a

Submitted on 23 January 2014

2014 Second Weekly Impact Water Quality Monitoring Report (Zone A)

 

n/a

Submitted on 30 January 2014

2014 Third Weekly Impact Water Quality Monitoring Report (Zone A)

 

n/a

Submitted on 6 February 2014

2014 Forth Weekly Impact Water Quality Monitoring Report (Zone A)

 

n/a

Submitted on 12 February 2014


3                                             Water Quality Monitoring Requirements

3.1                                      Monitoring Locations

In accordance with the Updated EM&A Manual, water quality monitoring samples were collected at eleven (11) stations, the same stations as baseline monitoring situated around the cable installation works in Zone A.  The locations of the sampling stations within Zone A are shown in Figure 2.2.

¡P      E7 is the Impact Station located at Fat Tong Chau to monitor the impacts of cable installation works on the coral communities in the proximity;

¡P      E8 is an Impact Station to monitor the impacts of cable installation works on the coral communities along Junk Bay ¡V South West;

¡P      E9 is an Impact Station to monitor the impacts of cable installation works on the coral communities at Cape Collison (the Gradient Station is not set due to the short distance of this Impact Station to nearby proposed cable works which may affect the Project marine installation works);

¡P      F1 is an Impact Station to monitor the impacts of cable installation works on the Tung Lung Chau Fish Culture Zone;

¡P      S1 is an Impact Station situated at the WSD Seawater Intake Point in Junk Bay.  It is located within 500 m north of the cable alignment at Junk Bay and set up to monitor the effect of Project marine installation works in the area; 

¡P      S2 is an Impact Station to monitor the impacts of cable installation works on the WSD Seawater Intake at Siu Sai Wan;

¡P      S3 is an Impact Station to monitor the impacts of cable installation works on the Pamela Youde Nethersole Eastern Hospital Cooling Water Intake at Heng Fa Chuen;

¡P      G1 is a Gradient Station between S1 and the cable alignment;

¡P      G2 is a Gradient Station between S2 and the cable alignment;

¡P      G3 is a Gradient Station between F1 and the cable alignment; and

¡P      C1 is a Control Station (approximately 3 km from the proposed cable alignment) for Zone A.  It is not supposed to be influenced by the Project marine installation works due to its remoteness from the works.

The co-ordinates of the above monitoring stations in Zone A are listed in Table 3.1.

 

Table 3.1        Water Quality Monitoring Stations

Monitoring Station

Nature

Easting

Northing

E7

Impact Station (Coral Community)

843779

814520

E8

Impact Station (Coral Community)

843111

815126

E9

Impact Station (Coral Community)

843557

811853

F1

Impact Station (Fish Culture Zone)

847196

811056

S1

Impact Station (Seawater Intakes)

847639

805900

S2

Impact Station (Seawater Intakes)

849587

805696

S3

Impact Station (Seawater Intakes)

845474

810605

G1

Gradient Station

845297

816282

G2

Gradient Station

844071

814784

G3

Gradient Station

846099

812826

C1

Control Station

842022

816547

3.2                                      Monitoring Parameters

The post project water quality monitoring was conducted in accordance with the requirements stated in the Updated EM&A Manual.  Monitoring parameters are presented as below.

Parameters measured in situ were:

¡P      Dissolved Oxygen (DO) (% saturation and mg L-1);

¡P      Temperature (¢XC);

¡P      Turbidity (NTU); and

¡P      Salinity (‰).

The only parameter measured in the laboratory was:

¡P      Suspended Solids (SS) (mgL-1).

In addition to the water quality parameters, other relevant data were measured and recorded in field logs, including the location of the sampling stations, water depth, time, weather conditions, sea conditions, special phenomena and work activities undertaken around the monitoring and works area that may influence the monitoring results.

3.3                                      Monitoring Equipment and Methodology

3.3.1                               Monitoring Equipment

Table 3.2 summaries the equipment used for the post project water quality monitoring.

Table 3.2        Equipment Used during the Post Project Water Quality Monitoring

Equipment

Model

Global Positioning Device

Garmin etrex 10

Water Depth Gauge

Speedtech Instrument SM-5

Water Sampling Equipment

1520 Kemmerer Water Sampler

Salinity, DO, Temperature Measuring Meter

YSI Pro 2030

Current Velocity and Direction

Flow Probe FP11

Turbidity Meter

HACH Model 2100Q Turbid Meter

3.3.2                               Monitoring Methodology

Timing & Frequency

The water monitoring was carried out on three occasions (days) and the intervals between two sets of monitoring were not less than 36 hours.  The water quality sampling was undertaken within a 4 hour window of 2 hour before and 2 hour after mid flood and mid-ebb tides.  The tidal range selected for the post project monitoring was at least 0.5 m for both flood and ebb tides as far as practicable.

Reference were made to the predicted tides at Tai Miu Wan, which is the tidal station nearest to the Project Site, published on the website of the Hong Kong Observatory ([2]).  Based on the predicted tidal levels at Tai Miu Wan, the post-project water quality monitoring was conducted between 10 and 15 March 2014, following the schedule presented in Annex A. 

Sampling Depths & Replication

Each station was sampled and measurements/ water samples were taken at three depths, namely, 1 m below water surface, mid-depth and 1 m above sea bed, except where the water depth less than 6 m, the mid-depth station may be omitted.  For stations that are less than 3 m in depth, only the mid-depth sample was taken.

For in situ measurements, duplicate readings were made at each water depth at each station.  Duplicate water samples were collected at each water depth at each station.

Sampling/ Testing Protocols

All in situ monitoring instruments were checked, calibrated and certified by a laboratory accredited under HOKLAS or any other international accreditation scheme before use (see calibration reports in Annex B), and subsequently will be re-calibrated at monthly intervals throughout all stages of the water quality monitoring.  Responses of sensors and electrodes were checked with certified standard solutions before each use.

For the on-site calibration of field equipment, the BS 1427: 1993, Guide to Field and On-Site Test Methods for the Analysis of Waters was observed.  Sufficient stocks of spare parts were maintained for replacements when necessary.  Backup monitoring equipment was made available.

Water samples for SS measurements were collected in high density polythene bottles, packed in ice (cooled to 4¢XC without being frozen), and delivered to a HOKLAS laboratory as soon as possible after collection.

Two replicate samples were collected from each of the monitoring events for in situ measurement and lab analysis.

3.3.3                               Laboratory Analysis

All laboratory work was carried out in a HOKLAS accredited laboratory.  Water samples of about 1,000 mL were collected at the monitoring and control stations for carrying out the laboratory determinations.  The determination work started within the next working day after collection of the water samples.  The SS laboratory measurements were provided within 2 days of the sampling event (48 hours).  The analyses followed the standard methods as described in APHA Standard Methods for the Examination of Water and Wastewater, 19th Edition, unless otherwise specified (APHA 2540D for SS).

The QA/QC details were in accordance with requirements of HOKLAS or another internationally accredited scheme (Annex B).

4                                             Implementation Status of Environmental Mitigation Measures

Mitigation measures for water quality control were recommended in the Project Profile (PP-452/2011) and Environmental Permit (EP- 433/2011).  The Contractor implemented the following select and relevant mitigation measures during cable re-installation works:

¡P      The forward speed of the installation barge was limited to a maximum of 1 km/ hour;

¡P      Water quality monitoring was carried out to verify that the project works were not resulting in any impacts to water quality, marine ecology and fisheries; and

¡P      Prevention of leakage from construction equipment to reduce the runoff entering the marine waters was incorporated as part of good working practices.

 

 


5                                             Post Project Monitoring Results

A total of three (3) monitoring events (days) were scheduled in the monitoring period from 10 to 15 March 2014 (Annex A).  Monitoring occasions at all designated monitoring stations within Zone A (conducted on 10, 13 and 15 March 2014) were performed on schedule.  No major activities influencing the water quality were identified during the reporting period.

The post project monitoring data are presented in Annex D and have been compared with baseline update monitoring results.

The levels of DO measured during the post project monitoring period at different sampling depths were generally higher than those obtained during the baseline update monitoring period (Figure D1-D3).  Elevation of DO concentration was detected at all the impact stations and the control station C1 (situated a long distance from the submarine cable alignment and not likely to be affected by the Project works) during the post project monitoring period.  DO levels recorded at the impact stations were of similar magnitude to those measured at the control station C1. 

Levels of Turbidity and SS measured during the post project monitoring period were generally lower compared to those measured during the baseline update monitoring period (Figure D4-D5).  This occurred to all the monitoring stations including the control station C1, which is situated a long distance from the submarine cable alignment and not likely to be affected by the Project works.  Turbidity and SS levels recorded at all the impact stations were generally of similar magnitude to those measured at the control station C1 during post project monitoring period.  Replicated data at impact and control stations indicates that the situation was due to natural fluctuations. 

Given the above information, particularly with regard to the control station, the overall changes in DO, Turbidity and SS levels during the post project monitoring period at all designated stations compared to baseline data are likely to represent a natural phenomenon. 

6                                             Conclusion

This Post Project Water Quality Monitoring Report (Zone A) presents the EM&A work undertaken during the period from 10 to 15 March 2014 in accordance with the Updated EM&A Manual and the requirements under Environmental Permit (EP- 433/2011).

Post project water quality monitoring in Zone A was conducted within 3 weeks of confirmation that the marine cable repair works had been completed.  The overall water quality at the impact stations in Zone A was found to be similar to that at the control station with higher DO levels and lower Turbidity and SS levels recorded compared to the updated baseline data.  Given the fact that the control station is sufficiently far away from the cable alignment and water quality at this station could not be affected by the Project, it is concluded that the overall changes in DO, Turbidity and SS levels during the post-project monitoring period at all designated stations including the control station are likely to represent natural variation.

It is considered that no deterioration of water quality was observed between post project and baseline monitoring for this cable repair work and therefore the Project works had negligible impact on water quality.


 



([1])        ERM (2012) EM&A Manual for Asia Submarine-cable Express (ASE) ¡V Tseung Kwan O.

([2])        Hong Kong Observatory (2013) http://www.hko.gov.hk/tide/eQUBtide.htm [Accessed in February 2013]