9               FUTURE KEY ISSUES

 

9.1         Major site activities undertaken for the coming months include:

 

Portion A

1.          General Cleaning

 

Portion B

1.          Internal Finishing & E&M Works for Subway A 

2.          Installation of Steel Roof,

3.          Construction of Resting Station R6

4.          Construction of Cycle Track

5.          Construction of Drainage

 

Portion C

1.          Planting,

2.          Installation of water point

 

 

Portion D

1.          Construction of Planter Wall PWD1

2.          Backfilling for Retaining Wall 15D, 15E, 16A & PWD1

3.          Construction of Drainage Pipe / Channel

4.          Construction of Road Kerb

5.          Laying Bituminous Pavement for Cycle Track

6.          Installation of Bicycle Parapet

 

Portion E

1.          Construction of Retaining RW D3, D5 & Access Ramp

2.          Realignment of San Tam Road and Mai Po Lung Road

3.          Construction of Road Kerb

4.          Laying Bituminous for Cycle Track

5.          Installation of Bicycle Parapet and Railing

6.          Construction of Footpath

7.          Construction of Drainage Pipe / Channel

8.          CCTV for Drainage Pipe

 

Portion F

1.          Construction of Boundary Wall and Retaining Wall RW 44

2.          Backfilling for Retaining Wall

3.          Construction of Road Kerb

4.          Laying Bituminous for Cycle Track

5.          Installation of Bicycle Parapet and Railing

6.          Construction of Footpath

7.          Construction of Drainage Pipe / Channel

8.          Installation of Traffic Aids

9.          CCTV for Drainage Pipe

 

 

Portion G

1.          Installation of Traffic Aids

2.          Colour Dressing for Cycle Track

 

Portion H

1.          Construction of Retaining Wall RW DW1 & DW2

2.          Backfilling for Retaining Wall

3.          Construction of Road Kerb

4.          Laying Bituminous for Cycle Track

5.          Installation of Bicycle Parapet and Railing

6.          Construction of Drainage Pipe / Channel

7.          Construction of Cross Ducting for Traffic Signal

8.          Realignment of Castle Peak Road

 

Portion I

1.          Internal Finishing & E&M Works for Subway D

2.          Installation of Steel Roof,

3.          Installation of Flooding Warning System

4.          Reinstate the Existing Slope and Carriageway, Removal of Temporary Steel Bridge of TTA

5.          Construction of Drainage / Channel

 

Portion J

1.          Construction of Drainage / Channel

2.          Construction of Road Kerb

3.          Laying Bituminous Pavement for Cycle Track

4.          Installation of Bicycle Parapet and Type II Railing

 

Portion K

1.          Installation of Traffic Aids

 

Portion M

1.          Installation of Lighting for Bridge E

2.          Laying Bituminous Pavement for Cycle Track

3.          Installation of Bicycle Parapet / Railing

4.          Construction of Road Kerb

 

Portion N

1.          Construction of Decking for Bridge B

2.          Construction of Retaining Wall

 

 


 

 

9.2         Key environmental issues in the coming months include:

 

·                      Wastewater and runoff generation on-site;

·                     Regular removal of silt, mud and sand along u-channels and inside sedimentation tanks;

·                     Review and implementation of temporary drainage system for the surface runoff;

·                     Noise from operation of the equipment, especially for excavation works and machinery on-site;

·                     Dust generation from stockpiles of dusty materials, exposed site area, excavation works and other dust-generating activities;

·                     Water spraying for dust generating activities and on haul road;

·                     Proper storage of construction materials on-site;

·                     Storage of chemicals/fuel and chemical waste/waste oil on-site;

·                     Accumulation of general refuse and construction waste on-site; and

·                     Protection measures for retained trees.

9.3              The tentative program of major site activities and the impact prediction and control measures for the coming months, i.e. February to March 2020, are summarized as follows:

 

Construction Works

Major Impact Prediction

Control Measures

As mentioned in Section 9.1

Air quality impact (dust)

(a)    Frequent watering of haul road and unpaved/exposed areas;

(b)   Frequent watering or covering stockpiles with tarpaulin or similar means; and

(c)    Watering of any earth moving activities.

Water quality impact (surface run-off)

(d)   Diversion of the collected effluent to de-silting facilities for treatment in compliance with valid Discharge License prior to discharge to public storm water drains;

(e)    Provision of adequate de-silting facilities for treating surface run-off and other collected effluents prior to discharge;

(f)    Provision of perimeter protection such as sealing of hoarding footings to avoid run-off from entering the existing storm water drainage system via public road; and

(g)    Provision of measures to prevent discharge into the stream.

Noise impact

(h)   Scheduling of noisy construction activities if necessary to avoid persistent noisy operation;

(i)     Controlling the number of plants use on site;

(j)     Regular maintenance of machines

(k)   Use of quiet PMEs on-site; and

(l)     Use of acoustic barriers and noise enclosure if necessary.

Landscape and Visual

 

(m) Proper setup of precautionary area for retained trees.

 

Monitoring Schedule for the Next Month

 

9.4              The tentative environmental monitoring schedules for the next month are shown in Appendix D.