Proposed Road Improvement Works in
West Kowloon Reclamation Development – Phase 1
Environmental Monitoring & Audit Report
01/01/2018 – 31/1/2018
Environmental Pioneers & Solutions Limited
Flat A, 8/F, Chaiwan Industrial Centre,
20 Lee Chung Street, Chai Wan, Hong Kong
Tel: 2556 9172 Fax: 2856 2010
1.2 Construction Programme and Activities
1.4 Status of Environmental Licences, Notification and Permits
2.4 Monitoring Methodology and Parameters
2.5 Maintenance and Calibration.
2.6 Quality Assurance / Quality Control Results and Detection Limits
2.7 Action and Limit Level for 1-hr TSP and 24-hr TSP
2.8 Monitoring Results and Observations
2.9 Monitoring Schedule for Next Reporting Month
3.4 Monitoring Methodology and Parameters
3.5 Maintenance and Calibration.
3.6 Quality Assurance / Quality Control Results and Detection Limits
3.7 Action and Limit Level for Construction Noise
3.8 Monitoring Results and Observations
3.9 Monitoring Schedule for Next Reporting Month
4 Solid and Liquid Waste Management Status
6 Environmental Site Inspection
6.2 Implementation Status of Environmental Mitigation Measures
7 Environmental Non-Conformance
7.1 Summary of Environmental Exceedances
7.2 Summary of Environmental Non-Compliance
7.3 Summary of Environmental Complaint
7.4 Summary of Notification of Summons and Successful Prosecution
9 Comment, Recommendations and Conclusions
LIST OF APPENDICES
Appendix A: Construction Programme and Project Layout Plan
Appendix B: Project Organization Chart
Appendix C: Monitoring Locations
Appendix D: Calibration Certification
Appendix E: TSP Monitoring Data
Appendix F1: Noise Monitoring Data
Appendix G: Waste Management Record
Appendix H: Environmental Mitigation Implementation Schedule
LIST OF TABLES
Table 1.4.1: Summary of the Status of Environmental Licences, Notification and Permits
Table 2.1.1: Air Quality Monitoring Locations
Table 2.1.2: Air Quality Monitoring Locations
Table 2.3.1: Air Quality Monitoring Equipment
Table 2.7.1: Established TSP Actions and Limit Level
Table 2.7.2: Event and action Plan for Air Quality
Table 2.8.1: Summary of average 1-hr TSP monitoring data
Table 2.8.2: Summary of average 24-hr TSP monitoring data
Table 3.1.1: Noise Monitoring Locations
Table 3.3.1: Equipment List for Noise Monitoring
Table 3.7.1: Action and Limit Levels for Construction Noise at all Sensitive Receivers
Table 3.7.2: Event / Action Plan for Construction Noise
Table 3.8.1: Summary of average noise monitoring data
Table 4.1: Quantities of Waste Disposed from the Project
Table 5.1: Proposed Monitoring Program
Table 5.2: Event / Action Plan for Landsscape and Visual Impact
Table 6.1: Summary results of site inspections findings
Executive Summary
This is the twentieth-fourth monthly Environmental Monitoring and Audit (EM&A) Report for Proposed Road Improvement Works in West Kowloon Reclamation Development – Phase 1. The project commenced on 6 February 2016. This report documents the finding of EM&A Works conducted from 1 January 2018 to 31 January 2018.
Environmental Monitoring and Audit Progress
Air Quality Monitoring
1-hr Total Suspended Particulates (TSP) monitoring and 24-hr TSP monitoring were carried out on 4, 10, 16, 22 and 27 January 2018.
Noise Monitoring
30-min LAeq noise monitoring was carried out on 4, 10, 16, 22 and 27 January 2018.
Waste Management
According to Contractor’s waste flow data, 3371.25 tonnes of inert C&D materials and 31.67 tonnes of general refuse were generated and disposed.
Landscape and Visual Impact
Bi-weekly inspections were conducted on 12 and 26 January 2018. Most of the necessary mitigation measures have been implemented. Details of the audit findings and implementation status are presented in Section 6.
Environmental Site Inspection
Joint weekly inspections were conducted by representatives of the Contract Administrator, Engineer, Contractor and ET on 4, 8, 15, 24 and 29 January 2018. The representative of the IEC conducted the site inspection on 24 January 2018. Details of the audit findings and implementation status are presented in Section 6.
Environmental Exceedance / Non-compliance / Compliant / Summons and Successful Prosecution
No exceedance of action level and limit level was recorded for TSP. Five exceedances were recorded at NM4 on 4, 10, 16, 22 and 27 January 2018 for Noise. No Non-compliance event, environmental complaint, notification of summons and successful prosecution against the Project were received in this reporting month.
Variation in Construction Method
No variation in construction method from the proposed construction programme was made and affected the EM&A.
Future Key Issues
The major construction works to be undertaken in the next reporting month include:
· Portion I – Pile Cap, Pier and Bridge Deck Construction Works
· Portion HA – Pile Cap, Pier and Bridge Deck Construction Works
· Portion J – Street Furniture Installation
· Portion Q – Road Works (excavation and utilities diversion)
1.1 The Project
This is a road improvement project in West Kowloon Reclamation Development (WKRD) for completing the developments and the commissioning of the new transport facilities.
Apart from the additional traffic impacts arising from the major development and transport facilities in WKRD, several major junctions in the area are currently operating with insufficient capacity causing serious congestion to some existing major road corridors such as Jordan Road (JRD), Ferry Street (FST) and Canton Road (CRD).
To enhance the road network of the area, Transport Department commissioned the“West Kowloon Reclamation Development Traffic Study” which identified and recommended Core and Additional Schemes together with the improvement works at the junction of CRD/FST/JRD. Implementation of these schemes would enable most of the key road junctions in the study area to operate with spare capacity, and the traffic queue length would also be reduced avoiding blockage to the upstream junctions
The Environmental Team (ET), Environmental Pioneers & Solutions Limited (EPSL), was appointed by Vibro Construction Co. Ltd. to undertake the Environmental Monitoring and Audit (EM&A) programme during construction phase of the Proposed Road Improvement Works in West Kowloon Reclamation Development – Phase 1. The project proponent is Highways Department. This is a Designated Project under the Environmental Impact Assessment Ordinance (Cap.499). The No. of Environment Permit is EP-455/2013.
The construction works and EM&A programme of this project was commenced on 6 February 2016. The construction programme and project layout plan are shown in Appendix A.
1.2 Construction Programme and Activities
A summary of the major construction activities undertaken in this reporting period is shown as follows.
· Portion I – Pile Cap, Pier and Bridge Deck Construction Works
· Portion HA – Pile Cap, Pier and Bridge Deck Construction Works
· Portion J – Street Furniture Installation
· Portion Q – Road Works (excavation and utilities diversion)
1.3 Project Organization
The project organization chart and contact details are shown in Appendix B.
1.4 Status of Environmental Licences, Notification and Permits
A summary of the relevant permits, licences, and notifications on environmental protection for this Project is presented in Table 1.4.1.
Table 1.4.1 Summary of the Status of Environmental Licences, Notification and Permits
Valid Period |
Status |
Remark |
||
From |
To |
|||
Notification pursuant to Air Pollution Control (Construction Dust) Regulation |
||||
Ref. No. 386894 |
23/03/2015 |
N/A |
Valid |
/ |
Effluent Discharge License |
||||
WT00021818-2015 |
18/06/2015 |
30/06/2020 |
Valid |
Portion I |
WT00021822-2015 |
18/06/2015 |
30/06/2020 |
Valid |
Portion HA |
WT00021825-2015 |
18/06/2015 |
30/06/2020 |
Valid |
Portion J |
WT00021826-2015 |
18/06/2015 |
30/06/2020 |
Valid |
Portion Q |
WT00021903-2015 |
26/06/2015 |
30/06/2020 |
Valid |
Works area 1 |
Waste Disposal (Charges for Disposal of Construction Waste) Regulation |
||||
Billing Account No.7022012 |
31/03/2015 |
N/A |
Valid |
/ |
Registration of Chemical Waste Producer |
||||
WPN5213-229-V2215-01 |
01/06/2015 |
N/A |
Valid |
/ |
Construction Noise Permit |
||||
GW-RE1183-15 |
04/12/2015 |
03/06/2016 |
Expire |
Portion HA |
GW-RE0469-16 |
04/06/2016 |
03/12/2016 |
Expire |
Portion HA |
GW-RE0330-17 |
25/04/2017 |
23/10/2017 |
Expire |
Portion HA |
PP-RE0029-17 |
18/10/2017 |
16/04/2018 |
Valid |
Portion HA |
According to the EM&A Manual Section 3.5, four impact monitoring locations have been established for air quality monitoring, which are summarized in Table 2.1.1.
Table 2.1.1 Air Quality Monitoring Locations
Identification No. |
Monitoring Location |
Description |
Parameter |
AM1 |
Marine Department New Yau Ma Tei Public Cargo Working Area Administrative Building |
Ground Floor Face to Hoi Po Road |
1-hr TSP 24-hr TSP |
AM2 |
Garden Building |
Ground Floor Face to Canton Road |
1-hr TSP 24-hr TSP |
AM3 |
The Cullinan I |
Ground Floor Face to Nga Cheung Road |
1-hr TSP 24-hr TSP |
AM4 |
Lai Chack Middle School |
Ground Floor Face to Canton Road |
1-hr TSP 24-hr TSP |
Due to the rejection from the representatives/ property management of the premises, high volume samplers are not feasible to be installed at AM3 and AM4 for the 24-hr TSP monitoring. Alternative locations AM3-B and AM4-A are proposed accordingly. The monitoring locations are summarized in Table 2.1.2. The details of monitoring location plan are shown in Appendix C.
Alternative monitoring location AM4-A is adjacent to the construction site of Xiqu Centre. Power supply for AM4-A was temporarily provided by the Main Contractor of Xiqu Centre, Hip Hing Engineering Co. Ltd.. Due to the outside surface works and drainage works of Xiqu Centre, the power distribution box under Hip Hing Engineering Co. Ltd. was relocated. The power supply to AM4-A has been cut off from early August 2017. 24hr-TSP monitoring at AM4-A was ceased from August 2017. The Contractor and ET are keeping in search of another alternative location to install the HVS and the power supply for AM4-A. On the other hand, major road works (excavation and utilities diversion) are approximately to be completed in Portion Q (close to AM4-A). The Contractor will review the construction works with ET and ER to deliberate on the possibility of suspending 24-hr TSP monitoring at AM4/AM4-A.
Table 2.1.2 Air Quality Monitoring Locations
ID No. |
Monitoring Location |
Description |
Coordinates |
Parameter |
AM1 |
Marine Department New Yau Ma Tei Public Cargo Working Area Administrative Building |
Ground Floor Face to Hoi Po Road |
22°18’44.8”N 114°09’37.4”E |
1-hr TSP
|
AM2 |
Garden Building |
Ground Floor Face to Canton Road |
22°18’12.7”N 114°10’05.7”E |
1-hr TSP
|
AM3 |
The Cullinan I |
Ground Floor Face to Nga Cheung Road |
22°18’22.0”N 114°09’39.3”E |
1-hr TSP
|
AM4 |
Lai Chack Middle School |
Ground Floor Face to Canton Road |
22°18’05.4”N 114°10’05.3”E |
1-hr TSP
|
AM1 |
Marine Department New Yau Ma Tei Public Cargo Working Area Administrative Building |
Rooftop Face to Hoi Po Road |
22°18’44.8”N 114°09’37.4”E |
24-hr TSP |
AM2 |
Garden Building |
Ground Floor Face to Canton Road |
22°18’12.7”N 114°10’05.7”E |
24-hr TSP |
AM3-B*1 |
The Cullinan II (W Hong Kong) |
Ground Floor Face to The Cullinan II |
22°18’16.3”N 114°09’34.5”E |
24-hr TSP |
AM4-A |
Tsim Sha Tsui Fire Station |
Ground Floor Face to Canton Road |
22°18’05.5”N 114°10’04.0”E |
24-hr TSP |
Remark:
*1 Monitoring station was amended from AM3-A to AM3-B from October 2016. AM3-B is located at the site boundary of Scheme I. There is no obstacle between the site (dust emission source) and monitoring point. It is more representative for monitoring the dust impact caused by the construction activities.
For 1-hr TSP monitoring, the sampling frequency is at least three times in every six days when the highest dust impact occurs.
For 24-hr TSP monitoring, the sampling frequency is once in every six days when the highest dust impact occurs.
Monitoring was carried out on 4, 10, 16, 22 and 27 January 2018.
2.3 Monitoring Equipment
1-hr TSP monitoring was carried out by the portable dust meters. A comparison test for the portable dust meters with the HVS was carried out to ensure the accuracy for direct reading of the portable dust meter. 24-hr TSP monitoring was carried out by the high volume samplers. The monitoring equipment is listed in Table 2.3.1 and Calibration Certificates of the equipment are shown in Appendix D.
Table 2.3.1 Air Quality Monitoring Equipment
Equipment |
Manufacturer & Model No. |
Serial No. |
Latest Calibration Date |
Next Calibration Date |
Portable Dust Meter |
TSI AM520 |
5201707001 |
24/02/2017 |
23/02/2018 |
5201707002 |
24/02/2017 |
23/02/2018 |
||
5201707003 |
24/02/2017 |
23/02/2018 |
||
5201707004 |
24/02/2017 |
23/02/2018 |
||
High Volume Sampler |
Tisch TE-5170 |
0001 |
06/12/2017 |
05/02/2018 |
0002 |
06/12/2017 |
05/02/2018 |
||
0003 |
06/12/2017 |
05/02/2018 |
||
Calibration Kit |
Tisch TE-5028A |
2137 |
01/02/2017 |
31/01/2018 |
3371 |
30/05/2017 |
29/05/2018 |
2.4 Monitoring Methodology and Parameters
Measurements of 1-hr TSP monitoring were taken by a Dust Trak aerosol monitor or its equivalent that is a portable and battery-operated laser photometer capable of performing real time 1-hr TSP measurements.
Field monitoring procedures are as follows:
· The monitoring station was set at a point 1m from the exterior of the sensitive receivers building façade and set at a position 1.2m above the ground.
· The battery condition was checked to ensure good functioning of the dust monitor.
· Zero Cal was conducted to the dust monitor to each test for ensuring more accurate data.
· Logging setup and Instrument setup such as log interval, test length, number of test and impactor adaptor will set as follows:
- log interval : 1min
- test length : 60mins
- number of test : 3
- Impactor adaptor: 100µ
· Start the monitoring lasting 3 hours for each monitoring location
· At the end of the monitoring period, the Average, Maximum and Minimum of each TSP test shall be recorded. In addition on a standard record sheet.
Measurements of 24-hr TSP monitoring were taken by High Volume Samplers (HVSs).
HVSs fitted with appropriate sampling inlets were employed for air quality monitoring. Each sampler was composed of a motor, a filter holder, a flow controller and a sampling inlet and its performance specification complies with that required by USEPA Standard Title 40, Code of Federation Regulations Chapter 1 (Part 50).
Installation of HVSs:
· A horizontal platform with appropriate support to secure the samplers against gusty wind should be provided;
· No two samplers should be placed less than 2 meters apart;
· The distance between the sampler and an obstacle, such as buildings, must be at least twice the height that the obstacle protrudes above the sampler;
· A minimum of 2 meters of separation from walls, parapets and penthouses is required for rooftop samplers;
· A minimum of 2 meters separation from any supporting structure, measured horizontally is required;
· No furnace or incinerator flue is nearby;
· Airflow around the sampler is unrestricted;
· The sampler is more than 20 meters from the dripline;
· Any wire fence and gate, to protect the sampler, should not cause any obstruction during monitoring;
· Permission must be obtained to set up the samplers and to obtain access to the monitoring stations; and
· A secured supply of electricity is needed to operate the samplers.
Data of wind speed and wind direction was extracted from King’s Park Meteorological Station of Hong Kong Observatory. The collection of wind data meets the prescribed criteria in S.3.4.3 of the EM&A Manual.
Other relevant data such as monitoring location, time, weather conditions and any other special phenomena at the construction site were recorded during the measurement period.
2.5 Maintenance and Calibration
Dust Trak aerosol monitors were calibrated by the manufacturer or a HOKLAS Laboratory for every year and on-site Zero Cal before every monitoring. HVSs were calibrated after installation and re-calibrated on bi-monthly basis.
2.6 Quality Assurance / Quality Control Results and Detection Limits
The portable dust meter was calibrated annually by the manufacturer or a HOKLAS laboratory. HVSs were first been calibrated after installation and repeated on bi-monthly basis. Calibration Kit for HVSs was calibrated annually by the manufacturer or a HOKLAS laboratory. The detection limits of the HVSs meet with the prescribed standard. Calibration details and current Calibration Certificates are shown in Appendix D.
2.7 Action and Limit Level for 1-hr TSP and 24-hr TSP
The Action and Limit levels for air
quality impact monitoring results at all monitoring locations are summarized in
Table
2.7.1,
which would be applied for compliance assessment of air quality for this
project. If the air quality monitoring results at any monitoring stations
exceeded the criteria, the actions in accordance with the Event and Action Plan
in Table
2.7.2 shall
be taken.
Table 2.7.1 Established TSP Actions and Limit Level
Monitoring Locations |
Monitoring Parameter |
Action Level (µg/m3) |
Limit Level (µg/m3) |
AM1 |
1-hr TSP |
288 |
500 |
AM2 |
299 |
500 |
|
AM3 |
299 |
500 |
|
AM4 |
303 |
500 |
|
AM1 |
24-hr TSP |
157 |
260 |
AM2 |
183 |
260 |
|
AM3-B |
177 |
260 |
|
AM4-A |
176 |
260 |
Table 2.7.2 Event and action Plan for Air Quality
2.8 Monitoring Results and Observations
1-hr TSP monitoring was conducted at four monitoring
locations. The monitoring results are summarized in Table 2.8.1. 24-hr TSP monitoring was
conducted at three monitoring locations. The monitoring results are summarized
in Table
2.8.2. Detailed
impact monitoring data of 1-hr TSP, 24-hr TSP and meteorological data are shown
in Appendix
E.
Table 2.8.1 Summary of average 1-hr TSP monitoring data
Monitoring Locations |
Average 1-hr TSP (µg/m3) |
Range 1-hr TSP (µg/m3) |
Action Level (µg/m3) |
Limit Level (µg/m3) |
AM1 |
63 |
23 – 153 |
288 |
500 |
AM2 |
87 |
57 – 131 |
299 |
500 |
AM3 |
60 |
23 – 156 |
299 |
500 |
AM4 |
82 |
65 – 111 |
303 |
500 |
Table 2.8.2 Summary of average 24-hr TSP monitoring data
Monitoring Locations |
Average 24-hr TSP (µg/m3) |
Range 24-hr TSP (µg/m3) |
Action Level (µg/m3) |
Limit Level (µg/m3) |
AM1 |
75 |
55 – 99 |
157 |
260 |
AM2 |
68 |
47 – 96 |
183 |
260 |
AM3-B |
75 |
46 – 113 |
177 |
260 |
AM4-A |
- |
- |
176 |
260 |
In accordance with the established action and limited levels for impact monitoring, there was no exceedance recorded in the reporting period.
During the monitoring period, vehicle emissions were identified as one of the dust sources for AM1, AM2, AM3, AM4 and AM3-B. TSP levels of AM2 and AM4 may be affected by the construction activities from other construction sites near Canton Road.
2.9 Monitoring Schedule for Next Reporting Month
The monitoring schedule for next reporting month is scheduled on 2, 8, 14, 20 and 26 February 2018.
3.1 Monitoring Locations
According to the EM&A Manual Section 4.5, five impact monitoring locations have been established for noise impact monitoring during the construction phase of the project, which are summarized in Table 3.1.1. The details of monitoring location plan are shown in Appendix C.
Table 3.1.1 Noise Monitoring Locations
Identification No. |
Noise Monitoring Location |
Description |
Measurement Type |
NM1 |
Sorrento - Tower 1 |
Podium Level Face to Nga Cheung Road |
Façade |
NM2 |
Yau Ma Ti Catholic Primary School (Hoi Wang Road ) |
Ground Floor Face to Hoi Ting Road |
Façade |
NM3 |
The Cullinan I |
Ground Floor Face to Nga Cheung Road |
Façade |
NM4 |
Lai Chack Middle School |
Ground Floor Face to Canton Road |
Façade |
NM5 |
Yue Tak Building |
Ground Floor Face to Jordan Road |
Façade |
3.2 Monitoring Frequency
The regular monitoring for each location was performed on a weekly basis.
Monitoring was carried out on 4, 10, 16, 22 and 27 January 2018
Noise monitoring was conducted by using SVANTEK 958 / SVANTEK 971 which complied with the International Electrotechnical Commission Publications 61672:2002 (Type 1), 60651:1979 (Type 1) and 60804:1985 (Type 1) Specifications as referred to the Technical Memorandum to the Noise Control Ordinance. The equipment was calibrated and verified by certified laboratory to ensure they can perform to the same level of accuracy as stated in the manufacturer’s specification. Before and after the baseline measurement, the reading of sound level meter was checked with the acoustic calibrator and the measurements were accepted as valid if the calibration levels before and after the noise measurement agreed to within 1.0 dB. The measurement equipment is listed in Table 3.3.1 and Calibration Certificates of the equipment are shown in Appendix D.
Table 3.3.1 Equipment List for Noise Monitoring
Equipment |
Manufacturer & Model No. |
Precision Grade |
Serial No. |
Latest Calibration Date |
Next Calibration Date |
Sound level meter |
BSWA 806 |
IEC61672 Type 1 |
34461 |
16/03/2017 |
15/03/2018 |
SVANTEK 971 |
IEC61672 Type 1 |
56272 |
11/12/2017 |
10/12/2018 |
|
Acoustical calibrator |
SVANTEK ST-120 |
IEC 942 Type 1 |
150305805 |
19/11/2017 |
18/11/2018 |
SVANTEK SV30A |
IEC 942 Type 1 |
7908 |
09/12/2017 |
08/12/2018 |
3.4 Monitoring Methodology and Parameters
The construction noise level was measured in terms of the A-weighted equivalent continuous sound pressure level, LAeq. LAeq (30minutes) was used as the monitoring parameter for the impact monitoring in the time period between 0700 to 1900 hours on normal weekdays.
In case of non-compliance with the construction noise criteria, more frequent monitoring, as specified in the Action plan in Table 3.6.2, shall be carried out. This additional monitoring shall be carried out until the recorded noise levels are rectified or proved to be irrelevant to the construction activities.
Field monitoring procedures are as follows:
· The monitoring station was set at a point 1m from the exterior of the sensitive receivers building façade and set at a position 1.2m above the ground.
· The battery condition was checked to ensure good functioning of the meter.
· Parameters such as frequency weighting, the time weighting and the measurement time will set as follows:
- frequency weighting : A
- time weighting : Fast
· Prior to and after noise measurement, the meter shall be calibrated using the calibrator for 94.0 dB at 1000 Hz. If the difference in the calibration level before and after measurement is more than 1.0 dB, the measurement will considered invalid and repeat of noise measurement is required after re-calibration or repair of the equipment.
· The wind speed at the monitoring station shall be checked with the portable wind meter.
· Noise monitoring should be cancelled in the presence of fog, rain, and wind with a steady speed exceeding 5 m/s, or wind with gusts exceeding 10 m/s. Noise measurement should be paused during periods of high intrusive noise if possible and observation shall be recorded when intrusive noise is not avoided.
· At the end of the monitoring period, the Leq, L10 and L90 shall be recorded. In addition, site conditions and noise sources should be recorded on a standard record sheet.
3.5 Maintenance and Calibration
Monitoring equipment was calibrated by the HOKLAS Laboratory for every year and on-site calibrated before and after every monitoring.
3.6 Quality Assurance / Quality Control Results and Detection Limits
The sound level meter and calibrator were calibrated annually by the HOKLAS laboratory. The detection limits of the sound level meter meet with the prescribed standard. Calibration details and current Calibration Certificates are shown in Appendix D.
3.7 Action and Limit Level for Construction Noise
The Action and Limit levels for construction noise are defined in Table 3.7.1. Should exceedance of the criteria occur, action in accordance with the Action Plan in Table 3.7.2 shall be carried out.
Table 3.7.1 Action and Limit Levels for Construction Noise at all Sensitive Receivers
Monitoring Locations |
Building Type |
Time Period |
Action Level |
Limit Level |
NM1 |
Residential |
Daytime 0700 – 1900 hrs on normal weekdays |
When one documented complaint is received |
75 dB(A) |
NM2 |
Education |
70 dB(A) / 65dB(A)* |
||
NM3 |
Residential |
75 dB(A) |
||
NM4 |
Education |
70 dB(A) / 65dB(A)* |
||
NM5 |
Residential |
75 dB(A) |
*Remark: 70dB(A) and 65dB(A) for schools during normal teaching periods and school examination periods, respectively.
Table 3.7.2 Event / Action Plan for Construction Noise
3.8 Monitoring Results and Observations
Noise impact monitoring was conducted at five monitoring locations. The monitoring results are summarized in Table 3.8.1. Detailed impact monitoring data of noise are shown in Appendix F1.
Table 3.8.1 Summary of average noise monitoring data
Monitoring Locations |
Monitoring Date |
Baseline Level (dB(A)) |
LAeq*1 (dB(A)) |
Re-M*2 LAeq (dB(A)) |
Action Level (dB(A)) |
Limit Level (dB(A)) |
NM1 |
4/1/2018 |
75.1 |
65.6 |
N/A |
When one documented complaint is received |
75 dB(A) |
10/1/2018 |
61.2 |
N/A |
||||
16/1/2018 |
62.1 |
N/A |
||||
22/1/2018 |
63.2 |
N/A |
||||
27/1/2018 |
65.7 |
N/A |
||||
NM2 |
4/1/2018 |
66.5 |
67.2 |
N/A |
When one documented complaint is received |
70 dB(A) *3 |
10/1/2018 |
67.0 |
N/A |
70 dB(A) *3 |
|||
16/1/2018 |
66.8 |
N/A |
70 dB(A) *3 |
|||
22/1/2018 |
67.8 |
N/A |
70 dB(A) *3 |
|||
27/1/2018 |
68.1 |
N/A |
70 dB(A) *3 |
|||
NM3 |
4/1/2018 |
74.5 |
73.8 |
N/A |
When one documented complaint is received |
75 dB(A) |
10/1/2018 |
74.1 |
N/A |
||||
16/1/2018 |
74.7 |
N/A |
||||
22/1/2018 |
74.0 |
N/A |
||||
27/1/2018 |
74.4 |
N/A |
||||
NM4 |
4/1/2018 |
73.3 |
74.0 |
74.8 |
When one documented complaint is received |
70 dB(A) *3 |
10/1/2018 |
74.5 |
74.2 |
70 dB(A) *3 |
|||
16/1/2018 |
74.8 |
74.6 |
65 dB(A) *4 |
|||
22/1/2018 |
73.9 |
74.3 |
65 dB(A) *4 |
|||
27/1/2018 |
74.2 |
74.1 |
70 dB(A) *3 |
|||
NM5 |
4/1/2018 |
71.8 |
72.5 |
N/A |
When one documented complaint is received |
75 dB(A) |
10/1/2018 |
71.6 |
N/A |
||||
16/1/2018 |
71.8 |
N/A |
||||
22/1/2018 |
72.2 |
N/A |
||||
27/1/2018 |
71.5 |
N/A |
Remark:
*1 Measured result would be rounded down before comparison with the limit level
*2 Repeat noise measurement when exceedance is recorded
*3 70dB(A) for schools during normal teaching periods. School schedule is shown in Appendix F2
*4 65dB(A) for schools examination periods. School schedule is shown in Appendix F2
In accordance with the established action and limited levels for impact monitoring, Five exceedances were recorded at NM4 on 4, 10, 16, 22 and 27 January 2018. Noise measurement was repeated for confirming the findings and identifying the noise source for each exceedance according to the event and action plan.
The noise source for causing exceedances at NM4 was from the traffic of Canton Road. The NM4 was directly affected by the noise generated from the traffic. The recorded monitoring results at the NM4 were near the baseline noise level. The exceedances were not caused by the construction works of this project.
During the monitoring period, traffic noise was identified as one of the noise source for NM1, NM2, NM3, NM4 and NM5. Noise levels of NM1 and NM3 may be influenced by the construction activities from other construction sites near Nga Cheung Road. Noise level of NM2 may be influenced by construction activities from other construction sites near Hoi Ting Road. Noise levels of NM4 and NM5 may be influenced by the construction activities from other construction sites near Canton Road.
3.9 Monitoring Schedule for Next Reporting Month
The monitoring schedule for next reporting month is scheduled on 2, 8, 14, 20 and 26 February 2018.
4 Solid and Liquid Waste Management Status
With reference to relevant handling records and trip tickets of this Project, the quantities of different types of waste generated in the reporting month are summarised in Table 4.1. During this reporting month, inert C&D materials and general refuse were generated and disposed. No mixed waste was generated. No chemical waste was generated and collected by licensed collector. No paper, plastic and metal was recycled. Detail of waste management data is presented in Appendix G.
Table 4.1 Quantities of Waste Disposed from the Project
Reporting Month |
Quantity |
||||||
C&D Materials (inert) (a) |
C&D Materials (non-inert) (b) |
||||||
General Refuse |
Mixed Waste |
Chemical Waste |
Recycled materials |
||||
Paper/ cardboard |
Plastics |
Metals |
|||||
(in ‘000kg) |
(in ‘000kg) |
(in ‘000kg) |
(in ‘000kg) |
(in ‘000kg) |
(in ‘000kg) |
(in ‘000kg) |
|
Jan 2018 |
3371.25 |
31.67 |
0 |
0 |
0 |
0 |
0 |
Notes: (a) Inert C&D materials include bricks, concrete, building debris, rubble and excavated soil. (b) Non-inert C&D materials include steel, paper/cardboard packaging waste, plastics and other wastes such as general refuse and vegetative wastes. Steel metal generated from the Project are grouped into non-inert C&D materials as the materials were not disposed of with other inert C&D materials. |
Waste materials were generated during this reporting period, such as excavated waste, demolition waste and general refuse. Contractor handled, stored and disposed in accordance with good waste management practice and EPD’s regulation and requirements.
In accordance with the EM&A Manual, the landscape and visual mitigation measures shall be implemented to minimize the landscape and visual impacts during the construction works. The proposed monitoring program for landscape and visual impact is detailed in Table 5.1.
Table 5.1 Proposed Monitoring Program
Stage |
Monitoring Task |
Frequency |
Report |
Approval |
Construction stage |
Mitigation measures implementation |
Bi-weekly |
Landscape and Visual Impact Assessment Checklist |
Registered Landscape Architect & ET Leader |
Bi-weekly site inspections were conducted by representatives of the Engineer, Contractor and ET on 12 and 26 January 2018. The observations, reminders and recommendations made during the site inspections are summarized in Section 6, Table 6.1.
The implementation status of the proposed mitigation measures for landscape and visual impacts is given in Appendix H. Should non-conformity on one occur, action in accordance with the Action Plan in Table 5.2 shall be carried out.
Table 5.2 Event / Action Plan for Landsscape and Visual Impact
6 Environmental Site Inspection
Site audit was carried out by ET on weekly basis to monitor the timely implementation of proper environmental management practices and mitigation measures in the Project site.
Joint weekly inspections were conducted by representatives of the Contract Administrator, Engineer, Contractor and ET on 4, 8, 15, 24 and 29 January 2018. The representative of the IEC conducted the site inspection on 24 January 2018. Observations were recorded and summarized in Table 6.1.
During site inspection in the reporting month, no non-compliance was identified.
6.2 Implementation Status of Environmental Mitigation Measures
According to the EM&A Manual of the Project, the mitigation measures detailed in the documents shall be implemented during the construction phase. Updated status summary of the Environmental Mitigation Implementation Schedule is provided in Appendix H.
The observations, reminders and recommendations made during the audit sessions are summarized in Table 6.1.
Table 6.1 Summary results of site inspections findings.
Date |
Findings |
Identification |
Advice from ET |
Action taken |
Closing date |
20 Dec 17 29 Dec 17 4 Jan 18 8 Jan 18 15 Jan 18 24 Jan 18 29 Jan 18 |
Wastewater from vehicle washing was accumulated near the drainage channel. |
Observation |
Contractor was advised to remove the kerb for directing wastewater. |
The follow-up status will be reported in the next reporting period. |
N/A |
20 Dec 17 29 Dec 17 4 Jan 18 8 Jan 18 |
Oil container was observed without drip tray. |
Observation |
Contractor was advised to provide drip tray for the chemical container as secondary containment. |
Oil container was removed. |
15 Jan 18 |
20 Dec 17 29 Dec 17 4 Jan 18 8 Jan 18 |
A container for metal storage was observed placing on the stockpile of soil materials. |
Observation |
Contractor was advised to relocate the container in designated storage area and cover the stockpile of soil materials. |
Container for metal storage was maintained and placed in proper area. |
15 Jan 18 |
4 Jan 18 |
Oil leakage was observed on the ground. |
Observation |
Contractor was advised to clean up the oil leakage and properly maintain the on-site equipment. |
Oil leakage was cleaned up. |
8 Jan 18 |
4 Jan 18 |
Site drainage system was not properly maintained. |
Observation |
Contractor was advised to frequently remove the silt and grit from the drainage channels. |
Site drainage system was cleaned for removing the silt and grit. |
8 Jan 18 |
15 Jan 18 |
C&D waste and general refuse were not properly sorted and stored. |
Observation |
Contractor was advised to sort the waste and provide different containers for maintaining waste storage. |
Different types of containers were provided for C&D waste and general refuse sorting and storage. |
24 Jan 18 |
15 Jan 18 |
Soil materials were not covered. |
Observation |
Contractor was advised to cover or remove the soil materials. |
Soil materials were removed from site. |
24 Jan 18 |
24 Jan 18 29 Jan 18 |
Dusty soil materials were not properly covered. |
Observation |
Contractor was advised to completely cover the dusty materials for preventing air pollution. |
The follow-up status will be reported in the next reporting period. |
N/A |
24 Jan 18 29 Jan 18 |
A chemical container was not properly stored. |
Observation |
Contractor was advised to store the chemical container in designated chemical storage area. |
The follow-up status will be reported in the next reporting period. |
N/A |
24 Jan 18 |
Chemicals were not properly stored. |
Observation |
Contractor was advised to store the chemical container in designated chemical storage area. |
Chemicals were removed. |
29 Jan 18 |
24 Jan 18 |
Dusty soil materials were not covered. |
Observation |
Contractor was advised to cover the dusty materials for preventing air pollution. |
Soil materials were removed from site. |
29 Jan 18 |
24 Jan 18 |
Stockpiles of construction materials were piled near the tree protection areas. |
Observation |
Contractor was advised to store the construction materials in designated storage area and prevent any damage to the retained trees during the construction activities. |
Stockpiles of construction materials were removed from the tree protection zone. |
29 Jan 18 |
24 Jan 18 |
Existing drainage system was not properly protected. |
Observation |
Contractor was advised to cover and protect the drainage system for preventing debris and wastewater entering the drainage gully. |
Existing drainage system was covered and protected. |
29 Jan 18 |
Landscape and Visual Impact |
|||||
2 Jun 17 16 Jun 17 30 Jun 17 14 Jul 17 28 Jul 17 11 Aug 17 25 Aug 17 8 Sep 17 22 Sep 17 6 Oct 17 20 Oct 17 3 Nov 17 17 Nov 17 28 Nov 17 15 Dec 17 29 Dec 17 12 Jan 18 26 Jan 18 |
Tree crown of T11(T), T12(T) and T17(T) were tied. |
Observation |
Contractor was advised to remove the ties. |
The Contractor requested Planting sub-contractor to carry out follow up actions as soon as possible.
The follow-up status will be reported in the next reporting period. |
N/A |
12 Jul 16 29 Jul 16 26 Aug 16 9 Sep 16 23 Sep 16 7 Oct 16 25 Oct 16 4 Nov 16 18 Nov 16 2 Dec 16 17 Dec 16 31 Dec 16 12 Jan 17 25 Jan 17 10 Feb 17 23 Feb 17 10 Mar 17 24 Mar 17 7 Apr 17 21 Apr 17 5 May 17 19 May 17 2 Jun 17 16 Jun 17 30 Jun 17 14 Jul 17 28 Jul 17 11 Aug 17 25 Aug 17 8 Sep 17 22 Sep 17 6 Oct 17 20 Oct 17 3 Nov 17 17 Nov 17 28 Nov 17 15 Dec 17 29 Dec 17 12 Jan 18 26 Jan 18 |
Tree crown of T24 was conflicted with existing trees. |
Observation |
Contractor was advised to conduct crown pruning for the existing tree which next to T24. |
The Contractor requested Planting sub-contractor to carry out follow up actions as soon as possible
The follow-up status will be reported in the next reporting period. |
N/A |
20 Oct 17 3 Nov 17 17 Nov 17 28 Nov 17 15 Dec 17 29 Dec 17 12 Jan 18 26 Jan 18 |
Excess soil was piled within root zone of WKI 850®, WKI 851® and WKI 852® |
Observation |
Contractor was advised to remove the excess soil. |
The follow-up status will be reported in the next reporting period. |
N/A |
3 Nov 17 17 Nov 17 28 Nov 17 15 Dec 17 29 Dec 17 12 Jan 18 26 Jan 18 |
Construction materials were piled within the TPZ. |
Observation |
Contractor was reminded to relocate the construction materials which were piled within the TPZ |
The follow-up status will be reported in the next reporting period. |
N/A |
12 Jan 18 26 Jan 18 |
Construction works were started within Scheme J, Scheme HA and Scheme Q. |
Reminder |
Contractor was reminded to provide TPZ with robust fence at the dripline of all retained trees in order to avoid damage to the trees and their root zones. No works were allowed to undertake within the TPZ. |
N/A |
N/A |
12 Jan 18 26 Jan 18 |
For the retain trees in Scheme Q (WKI420, WKI421, WKI423, WKI424 and WKI425), nearby building and hoarding were demolished. Part of the root zone of the retained trees (near fire station) was fenced off by other parties. Concrete kerb was built on the root zone of WKI423(R), WKI424(R) and WKI425(R) by others parties. |
Reminder |
Contractor should remind Lanon Development Ltd to provide robust TPZ for the trees and to avoid damaging the root zone under the dripline. |
N/A |
N/A |
7 Environmental Non-Conformance
7.1 Summary of Environmental Exceedances
No exceedance of action level and limit level was recorded for TSP. Five exceedances were recorded at NM4 on 4, 10, 16, 22 and 27 January 2018 for Noise.
7.2 Summary of Environmental Non-Compliance
No environmental non-compliance was recorded in the reporting month.
7.3 Summary of Environmental Complaint
No environment project-related complaint was received in the reporting period.
7.4 Summary of Notification of Summons and Successful Prosecution
There was no successful environmental prosecution or notification of summons received since the Project commencement.
The cumulative log for environmental exceedance, non-compliance, complaint and summon and successful prosecution since the commencement of the Project is presented in Appendix I.
The major construction activities in the coming month will include:
· Portion I – Pile Cap, Pier and Bridge Deck Construction Works
· Portion HA –Pile Cap, Pier and Bridge Deck Construction Works
· Portion J – Street Furniture Installation
· Portion Q – Road Works (excavation and utilities diversion)
Potential environmental impacts arising from the above construction activities are mainly associated with dust, construction noise, water quality and waste management. The Contractor has been reminded to properly implement dust, construction noise and water quality control measures as well as proper waste management in order to minimize the potential environmental impacts due to the construction works of the Project.
9 Comment, Recommendations and Conclusions
The recommended mitigation measures accordance with the EM&A Manual had been effectively implemented to minimize the environmental impacts due to the construction. The contractor had implemented the mitigation measures to control the dust and noise impacts. No dust and noise impacts obviously affected to the environment and sensitive receivers. The follow up actions were not quickly implemented for environmental observations made during the site inspections. The environmental performance during the reporting period was considered satisfactory.
According to the environmental audit performed in the reporting month, the following recommendation was made:
Air Quality
To completely cover the dusty materials for preventing air pollution.
To cover or remove the soil materials.
Water / Wastewater
To frequently remove the silt and grit from the drainage channels.
To cover and protect the drainage system for preventing debris and wastewater entering the drainage gully.
To remove the kerb for directing wastewater.
Chemicals / Chemical waste
To clean up the oil leakage and properly maintain the on-site equipment.
To store the chemical container in designated chemical storage area.
Waste Management / Materials Storage / Others
To sort the waste and provide different containers for maintaining waste storage.
To store the construction materials in designated storage area and prevent any damage to the retained trees during the construction activities.
This is the monthly Environmental Monitoring and Audit (EM&A) Report presenting the EM&A works undertaken from 1 January 2018 to 31 January 2018 in accordance with the EM&A Manual.
No exceedance of action level and limit level was recorded for TSP. Five exceedances were recorded at NM4 on 4, 10, 16, 22 and 27 January 2018 for Noise. No Non-compliance event, environmental complaint, notification of summons and successful prosecution against the Project were received in this reporting month.
5 nos. of environmental site inspections and 2 nos. of landscape and visual inspections were carried out in this reporting month. Recommendations on remedial actions were given to the Contractor for the deficiencies identified during the site audit.
ET has reminded the contractor to provided environmental pollution control measures, waste management measures and good site practice.
The ET will keep tracking of the EM&A programme to ensure compliance of environmental requirements and the proper implementation of all the necessary mitigation measures.
Appendix A: Construction Programme and Project Layout Plan
Appendix B: Project Organization Chart
Appendix C: Monitoring Locations
Appendix D: Calibration Certification
Appendix E: TSP Monitoring Data
Appendix F1: Noise Monitoring Data
Appendix F2: School Schedule
Appendix G: Waste Management Record
Appendix H: Environmental Mitigation Implementation Schedule