1.1 Purpose of the Report
1.2 Structure of the Report
2.1 Background
2.2 General Site Description
2.3 Construction Programme and Activities
2.4 Project Organisation
2.5 Status of Environmental Licences, Notification and Permits
3 Environmental
Monitoring Requirement
3.1 Water Quality Monitoring
4 Implementation
Status of The environmental protection requirements
5.1 Waste Management
6 Environmental
Site Inspection
7 Environmental
Non-conformance
7.1 Summary of Monitoring Exceedance
7.2 Summary of environmental non-compliance
7.3 Summary of Environmental Complaint
7.4 Summary of Environmental Summon and successful prosecution
8 UPCOMING
WORKS FOR THE NEXT REPORTING PERIOD
8.1 Construction Activities for the Coming Month
8.2 Construction Programme for the Next Month
LIST OF ANNEXES
EXECUTIVE
SUMMARY
The construction works of CCGT Unit No. 1 of the Additional Gas-fired Generation Units
Project at the Black Point Power Station
commenced on 5 December 2016. This is the eighth monthly Environmental
Monitoring and Audit (EM&A) report presenting the EM&A works carried
out during the period from 1 July to 31 July 2017
in accordance with the EM&A Manual and the requirements of EP-507/2016 and
FEP-01/507/2016.
Summary of the Construction Works undertaken during the Reporting Month
The major construction works undertaken during the reporting month
include:
Construction Activities undertaken |
l
Relocation of
E&M service and remove building service in warehouse; l
Excavation
and lateral support for drainage works; l
Bulk
excavation for pile cap; l
Modification
of existing fire hydrant; l
Manhole
construction; l
Firefighting
pipe modification; l
Mobilization
and site establishment; and l
Underground
utility survey. |
Environmental Site Inspection
Joint
weekly site inspections were conducted by representatives of the Contractor,
CAPCO Project Team and ET on 6, 13, 20 and 27 July 2017. The representative of the IEC joined the site
inspection on 20 July 2017. Details of the audit findings and
implementation status are presented in Section 6.
Environmental Exceedance/Non-conformance/Complaint/Summons and
Prosecution
No non-compliance event was recorded during the reporting month.
No complaint was received during the reporting period.
No
summon or prosecution was received in this reporting period.
Upcoming Works for the
Next Reporting Period
The major construction works to be
undertaken in the next reporting month include:
Construction Activities to be undertaken |
|
|
The
Castle Peak Power Company Limited (CAPCO) is a joint venture between CLP Power
Hong Kong Limited (CLP) and China Southern Power Grid Company Limited with CLP
as the operator. ERM-Hong Kong, Limited (ERM) and Mott MacDonald Hong Kong Limited were appointed
by CAPCO as the Environmental Team (ET) and the Independent Environmental Checker (IEC),
respectively, to undertake the Environmental Monitoring and Audit (EM&A)
activities for the installation of CCGT Unit No. 1 of the Additional Gas-fired Generation Units Project at the Black Point Power
Station (BPPS) (“the Project”).
This is the eighth EM&A report which
summarises the audit findings during the reporting period from 1 July to 31
July 2017.
Section 1 : Introduction
It details the purpose and
structure of the report.
Section 2 : Project Information
It summarises the background and scope of
the project, site description, project organisation and contact details,
construction programme, construction works undertaken and status of the
Environmental Permits/Licenses during the reporting period.
Section 3
: Environmental Monitoring
Requirement
It briefly introduces the
environmental monitoring requirements for the Project.
Section 4
: Implementation Status of
the Environmental Protection
Requirements
It summarises the implementation of environmental protection measures
during the reporting period.
Section 5
: Monitoring Results
It summarises the
monitoring results obtained in the reporting period.
Section 6
: Environmental Site
Inspection
It summarises the audit
findings of the weekly site inspections undertaken within the reporting period.
Section 7
: Environmental
Non-conformance
It summarises any monitoring exceedance,
environmental complaints and summons within the reporting period.
Section 8
: Upcoming Works for the
Next Reporting Period
It summarises the construction activities and the forecast of
environmental impact for the next reporting month.
Section 9
: Conclusions
The scope of the Project involves the phased
construction and operation of up to two additional combined cycle gas turbine
(CCGT) units (with an installed capacity of up to 600 MW each) at the
BPPS. The additional generation units
will be of CCGT configuration using natural gas as the primary fuel. It is a Designated Project under the Environmental Impact Assessment Ordinance
(Cap. 499) (EIAO). The
current EM&A
Programme only includes the CCGT Unit No. 1.
An
EIA of the Additional Gas-fired Generation Units Project was prepared in
accordance with the EIA Study Brief (No. ESB-286/2015) and the Technical
Memorandum of the Environmental Impact Assessment Process (EIAO-TM)
and submitted under the EIAO in February 2016.
Subsequent to the approval of the EIA (EIAO Register Number
AEIAR-197/2016), an Environmental Permit (EP-507/2016) (EP) for CCGT Unit
No. 1 was granted by the Director of Environmental Protection (DEP) on 14 June
2016. A Further Environmental Permit
(FEP-01/507/2016) (FEP) was granted to the Contractor, Chun Wo
Foundations Limited, of the CCGT Unit No. 1 on 9 December 2016.
The proposed location for the Project is within the
existing boundaries of the BPPS site.
The size of the land reserved for the additional generation units and
the associated facilities (the Project Site) is about 40,000 m2. Construction works for CCGT Unit No. 1 is
currently ongoing at the Project Site.
The works area for the Project is shown in
Annex A.
A summary of the major construction activities undertaken in this
reporting period is shown in Table 2.1. The construction programme is presented in Annex B.
Table 2.1 Summary of the Construction
Activities Undertaken during the Reporting Month
Construction Activities
undertaken |
l
Relocation of
E&M service and remove building service in warehouse; l
Excavation and
lateral support for drainage works; l
Bulk
excavation for pile cap; l
Modification
of existing fire hydrant; l
Manhole
construction; l
Firefighting
pipe modification; l
Mobilization
and site establishment; and l
Underground
utility survey. |
The project organizational chart and
contact details are shown in Annex C.
A summary of the valid permits, licences, and/or notifications
on environmental protection for this Project is presented in Table 2.2.
Table 2.2 Summary of the Status of Valid Environmental Licence,
Notification, Permit and Documentations
Permit/ Licences/ Notification |
Reference |
Validity Period |
Remarks |
Environmental
Permit |
EP-507/2016 |
Throughout the
Contract |
Permit granted on
14 Jun 2016 |
Further
Environmental Permit |
FEP-01/507/2016 |
Throughout the
Contract |
Permit granted on 9
Dec 2016 |
Notification Pursuant to Section 3(1) of
the Air
Pollution Control (Construction Dust) Regulation |
410023 |
Throughout the
Contract |
Notification received on 15 Nov
2016 |
|
417676 |
Throughout the
Contract |
Notification received on 8 Jun 2017 |
Wastewater Discharge Licence |
WT00026627-2016 |
To 31 Jan 2022 |
Licence granted on 13 Jan 2017 |
Chemical Waste Producer Registration |
5213-432-C3243-13 |
Throughout the
Contract |
Registration approved
on 9 Jan 2017 |
|
5211-432-L2954-02 |
Throughout the
Contract |
Registration
approved on 4 Jul 2017 |
Billing Account for Disposal of Construction Waste |
7026814 |
Throughout the Contract |
Approved on 30 Dec 2016 |
|
7028155 |
Throughout the contract |
Approved on 23 June 2017 |
|
7028380 |
Throughout the contract |
Approved on 26 Jul 2017 |
Construction Noise Permit |
GW-RW0039-17 |
3 Feb 2017 – 31 Jul 2017 |
Permit granted on 1 Feb 2017 |
|
PP-RW0001-17 |
6 Feb 2017 – 5 Aug 2017 |
Permit granted on 3 Feb 2017 |
|
GW-RW0347-17 |
24 Jul 2017 - 30 Nov 2017 |
Permit granted on 14 Jul 2017 |
In accordance with the EM&A Manual, monitoring works is required at a
frequency of once per week on first year of commissioning of the CCGT Unit No.1. The monitoring details including monitoring requirement, locations of monitoring stations will be confirmed and approved by EPD before commissioning of the CCGT Unit No.1.
The Contractors have implemented all the environmental mitigation
measures and requirements as stated in the EIA Report, Environmental Permit
(EP) and EM&A Manual for the installation of CCGT Unit No.1. The implementation status of the
environmental mitigation measures for this Project during the reporting period
is summarised in Annex D. The status of the required submissions under
the EP and EM&A Manual for the Project is presented in Table 4.1.
Table 4.1 Status of Required
Submission under the
Project
EP Condition |
Submission |
Submission Date |
Condition
3.2 under Environmental Permit No. EP-507/2016 and FEP-01/507/2016. |
7th Monthly
EM&A Report |
12 July 2017 |
The waste generated from this Project includes inert construction
and demolition (C&D) materials, and non-inert C&D materials. Non-inert C&D materials are made up of
general refuse and recyclable wastes such as plastics and paper/cardboard
packaging waste. Steel materials
generated from the project are also grouped into non-inert C&D materials as
the materials were not disposed of with other inert C&D materials. With reference to relevant handling records
and trip tickets of this Project, the quantities of different types of waste
generated in the reporting month are summarised in Table 5.1. Details of waste management data are
presented in Annex E.
Table 5.1 Quantities of Waste Generated from the
Project
Reporting Month |
Quantity |
|||||
Inert C&D Materials (a)
(b) |
Chemical Waste (d) |
Non-inert C&D
Materials |
||||
General Refuse (c) |
Recycled materials |
|||||
Paper/cardboard |
Plastics |
Metals |
||||
|
(in '000m3) |
(in'000 kg) |
(in '000m3) |
(in'000 kg) |
(in'000 kg) |
(in'000 kg) |
July
2017 |
6.815 |
0 |
0 |
0 |
0 |
0 |
Notes: (a) Inert
C&D materials include bricks, concrete, building debris, rubble and
excavated spoil. (b) The
inert C&D materials generated from the Project were sent to Tuen Mun Area 38 Fill Bank during the reporting month. (c) The
general refuse generated from the Project was sent to WENT landfill during the reporting month. (d)
Chemical waste includes waste oil.
It is assumed density of waste oil to be 0.8 kg/L. |
Joint weekly site
inspections were conducted by representatives of the Contractor, CAPCO Project
Team and ET on 6, 13, 20 and 27 July 2017.
The representative of the IEC joined the site inspection on
20 July 2017.
No non-compliance was recorded during the site inspections.
Findings and recommendations
for the site inspection in this reporting month are summarised as follows:
6 July 2017
· There were no major observations.
13 July 2017
· There were no major observations.
20 July 2017
· The Contractor (Chun Wo) was reminded to plug
the drip tray for the generator to prevent potential chemical leakage.
Regarding the planter audit, CAPCO was recommended to:
· conduct close monitoring for BPT800 and BPT946; and
· replace BPT773,
BPT786, BPT794 and BPT805 after construction period.
27 July 2017
· The Contractor (Chun Wo) was reminded to spray
the stockpiles and dusty materials with water to maintain the entire surface
wet.
All follow-up actions
requested by ET and IEC during the site inspections were undertaken as
reported by CAPCO and the Contractors.
The abovementioned environmental issues had been addressed and mitigated
during the reporting period.
No environmental monitoring is required
during construction of CCGT Unit No. 1.
No non-compliance event was recorded during the reporting month.
No environmental complaint was received during the reporting
month.
No summon or prosecution was received during the
reporting month.
Works to be undertaken in the next
reporting month are summarised in Table 8.1.
Table 8.1 Construction Works to be undertaken in the Next Reporting Month
Construction Activities to be
undertaken |
|
|
Potential environmental impacts arising from the above
construction activities are mainly associated with dust, wastewater treatment
and waste management.
The construction programme for the Project for the next reporting
month is presented in Annex
B.
This 8th monthly Environmental
Monitoring and Audit (EM&A) Report presents the EM&A works undertaken
during the period from 1 July to 31 July 2017 in accordance with the EM&A Manual and the requirements of EP-507/2016 and
FEP-01/507/2016.
No non-compliance event was recorded during the reporting month.
No environmental complaint, summon
or prosecution was received during the reporting month.
The Contractors have implemented possible and feasible mitigation
measures to mitigate the potential environmental impacts during
construction. The ET will continue to
keep track of the EM&A programme to ensure compliance of environmental
requirements and the effectiveness and efficiency of the mitigation measures
implemented. If necessary, the
Contractors will provide more mitigation measures to further alleviate the
impacts.