CONTENTS

 

Executive Summary. 1

1                 Introduction. 2

1.1       Background. 2

1.2       Scope of Report 2

1.3       Project Organization. 2

1.4       Summary of Construction Works. 3

1.5       Summary of EM&A Programme Requirements. 3

2                 Water Quality Monitoring. 4

2.1       Monitoring Requirements. 4

2.2       Monitoring Equipment 4

2.3       Monitoring Locations. 4

2.4       Monitoring Parameters, Frequency and Duration. 5

2.5       Monitoring Methodology. 5

2.6       Monitoring Schedule for the Reporting Month. 5

2.7       Action/Limit Levels. 5

2.8       Results and Observations. 5

3                 Silt Curtain monitoring and audit 10

3.1       Monitoring Requirements. 10

3.2       Monitoring Equipment 10

3.3       Monitoring Locations. 10

3.4       Monitoring Parameters, Frequency and Duration. 10

3.5       Monitoring Methodology. 10

3.6       Limit Level 11

3.7       Results and Observations. 11

4                 Marine mammal observation. 12

4.1       Monitoring Requirements. 12

4.2       Monitoring Equipment 12

4.3       Monitoring Locations and Frequency. 12

4.4       Results and Observations. 12

5                 Conclusions and Recommendations. 12

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

LIST OF TABLES

 

Table 1.1     Contact Information of Key Personnel

Table 2.1     Water Quality Monitoring Equipment

Table 2.2     Locations of Impact Water Quality Monitoring Stations

Table 2.3     Water Quality Monitoring Parameters, Frequency and Duration

Table 2.4     Summary of Water Quality Monitoring Results in the Reporting Period

Table 3.1     Silt Curtain Monitoring Equipment

Table 3.2     Water Quality Monitoring Parameters, Frequency and Duration

Table 3.3     Summary of Silt Curtain Monitoring Results in the Reporting Period

Table 4.1     Marine Mammal Observation Equipment

 

 

 

LIST OF FIGURES

 

Figure 1.1           Alignment of AAE-1 Cable System within Hong Kong

Figure 2.1           Locations of Water Quality Monitoring Station

 

 

 

 LIST OF APPENDICES

 

Appendix A       Project Organization

Appendix B       Environmental Mitigation Measures Implementation Schedule

Appendix C       Calibration Certificates of Monitoring Equipment

Appendix D      EM&A Monitoring Schedules

Appendix E       Summary of Action / Limit Level

Appendix F       Water Quality Monitoring Results

Appendix G      Event Action Plan

 

Executive Summary

 

The EM&A programme for the Project commenced on 11 July 2017. The impact environmental monitoring include water quality monitoring, silt curtain monitoring and marine mammal observations.

 

This report documents the findings of EM&A works conducted in the period from 1 to 31 July 2017.

Breaches of Action and Limit Levels for Water Quality Monitoring

One (1) Action Level exceedance of Suspended Solids at E3 at Mid-Flood tide on 12 July 2017 was recorded in the reporting month. This exceedance was considered not likely to be caused by this Contractˇ¦s activities after investigation.

 

Four (4) Action Level exceedances of Dissolved Oxygen at surface & middle level at L1 (Mid-Flood, 11 July 2017), E3 (Mid-Flood, 11 July 2017), G1 (Mid-Ebb, 12 July 2017) and G2 (Mid-Ebb, 20 July 2017) were recorded in the reporting month. These exceedances were considered not likely to be caused by this Contractˇ¦s activities after investigation.

 

One hundred and twenty (120) Action Level exceedances of Dissolved Oxygen at bottom level of all monitoring locations at both Mid-Ebb and Mid-Flood tide every monitoring day were recorded in the reporting month. These exceedances were considered not likely to be caused by this Contractˇ¦s activities after investigation.

 

No exceedance of Limit Level of water quality was recorded in the reporting month.

Breaches of Action and Limit Levels for Silt Curtain Monitoring

No exceedance of Limit Level of silt curtain monitoring was recorded in the reporting month.

Marine Mammal Observation

No cetacean was observed in the exclusion zone for 30 minutes before the installation works start on 11, 12, 13 and 20 July 2017.

Complaint, Notification of Summons and Successful Prosecution

No environmental complaint, notification of summons and successful prosecution was received in the reporting month.

 

 

 


1              Introduction

1.1          Background

1.1.1       The AAE-1 Cable System (the Project) will be one of the first cable systems connecting Hong Kong, Singapore, Middle East, Africa and Europe, providing an alternative low latency route between the Far East and Europe. The entire AAE-1 Cable, spanning approximately 25,000 km from Hong Kong to France. Within Hong Kong, the length of the AAE-1 Cable is approximately 27.65km, as shown in Figure 1.1.

1.1.2       AAE-1 is to be constructed by the AAE-1 Consortium, which includes PCCW Global (HK) Ltd (PCCWG), who is responsible for the installation of the Project within Hong Kong.

1.1.3       A Project Profile was prepared to assess potential environmental impacts associated with the installation of the submarine telecommunications cable system within Hong Kong. The Project Profile was submitted to the Environmental Protection Department (EPD) under section 5(1)(b) and 5(11) of the Environmental Impact Assessment Ordinance (EIAO) for application for permission to apply directly for an Environmental Permit (EP) (Application No. DIR-244/2016). Permission granted by EPD via an approval letter dated 2 March 2016 (Ref. EP2/H18/C/10).

1.1.4       The Project Profile recommended carrying out precautionary water quality monitoring to ensure no adverse impacts to the water quality, marine ecology and fisheries. Also, as a precautionary measure, a 250m ˇ§marine mammal exclusion zoneˇ¨ around the cable laying barge shall established during the cable installation works to prevent marine mammals from being adversely affected.

1.2          Scope of Report

1.2.1       This is the first monthly Environmental Monitoring and Audit (EM&A) Report and this report presents a summary of the environmental monitoring and audit works, list of activities and mitigation measures of the Project in July 2017.

 

1.3           Project Organization

1.3.1       The project organization is shown in Appendix A. The key personnel contact names and numbers are summarized in Table 1.1.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Table 1.1          Contact Information of Key Personnel

Party

Position

Name

Telephone

Fax

IEC

 (SMEC Asia Limited)

Independent Environmental Checker

Vivian Chan

3995 8100

3995 8101

Contractor

(Hong Kong Marine Contractors Limited)

Project Director

Colman Chan

6193 4729

2693 2984 / 31053985

Operation Director

Dominic Chan

6193 4736

Administrative Director

Kevin Chan

6193 4737

ET

(AECOM)

ET Leader

Y W Fung

3922 9366

2371 7609

 

1.4          Summary of Construction Works

1.4.1       Details of the construction works carried out by the Contractor in this reporting period are listed below:

-                   Horizontal Directional Drilling (HDD)

-                   Surface laying by diver

-                   Cable burial works

1.4.2       The environmental mitigation measures implementation schedule are presented in Appendix B.

1.5          Summary of EM&A Programme Requirements

1.5.1       The EM&A programme required environmental monitoring for water quality monitoring, silt curtain monitoring and marine mammal observations. The EM&A requirements for each parameter described in the following sections include:

-                   All monitoring parameters;

-                   Monitoring schedules for the reporting period;

-                   Action and Limit levels for all environmental parameters;

-                   Event / Action Plan;

-                   Environmental mitigation measures, as recommended in the Project Profile; and

-                   Environmental requirement in contract documents.


2              Water Quality Monitoring

2.1          Monitoring Requirements

2.1.1       In accordance with the Updated EM&A Manual, the impact water quality monitoring was conducted each day during which cable burial will be carried out from Ch.500m to Ch.10km in the Project.

2.2          Monitoring Equipment

2.2.1       The brand and model of water quality monitoring equipment is given in Table 2.1.

Table 2.1          Water Quality Monitoring Equipment

Equipment

Brand and Model

Dissolved Oxygen Meter

YSI 6820

 

Water Temperature Meter

Salinity Meter

Turbiditimeter

Water Sampler

Kahlsico Water Sampler

Echo Sounder

Eagle Cuda-168

Global Positioning System

JRC DGPS 224 Model JLR-4341 with J-NAV 500 Model NWZ4551

Current Velocity and Direction Meter

Falmouth Scientific ACM-PLUS-200

2.3          Monitoring Locations

2.3.1       In accordance with the Updated EM&A Manual, the stations for impact water quality monitoring are presented in Table 2.2 and shown in Figure 2.1.

Table 2.2          Locations of Impact Water Quality Monitoring Stations

Type of Station

Station

Location

Easting

Northing

Water Quality Monitoring Station

L1

Shek O Headland SSSI

844603.15

809861.64

E1

Cape Dˇ¦Aguilar Marine Reserve

844778.20

808054.89

E2

Cape Dˇ¦Aguilar Marine Reserve

845185.03

807739.10

E3

Cape Dˇ¦Aguilar Marine Reserve

845355.75

807285.37

E4

Coral Communities at the Coast of Sung Kong

847839.10

805957.97

E5

Coral Communities at the Coast of Waglan Island

849742.30

805816.65

E6

Coral Communities at the Coast of Po Toi

845546.99

804968.77

E7

Coral Communities at the Coast of Beaufort Island

844690.12

805570.31

B1

Shek O Gazetted Bathing Beach

844039.63

809802.72

G1

Gradient Station

847740.12

806441.12

G2

Gradient Station

849648.03

806387.80

G3

Gradient Station

844719.38

809049.95

G4

Gradient Station

845294.36

806542.02

G5

Gradient Station

846049.55

806023.13

Control Station

C1

Control Station

848340.92

803652.59

 

2.4          Monitoring Parameters, Frequency and Duration

2.4.1       The monitoring parameters, frequency and duration of water quality monitoring are summarized in Table 2.3.

Table 2.3          Water Quality Monitoring Parameters, Frequency and Duration

Parameter

Frequency and Duration

Turbidity, Suspended Solids, Dissolved Oxygen, Temperature and Salinity

Each day during which cable burial will be carried out,

at mid-flood and mid-ebb tides

 

2.5          Monitoring Methodology

2.5.1       The water quality monitoring procedures are presented in the following:

Ÿ All monitoring equipment were checked and calibrated before use.  Responses of sensors and electrodes were also checked with certified standard solutions before each use.

Ÿ The interval between 2 sets of monitoring was not less than 36 hours.

Ÿ Duplicate in-situ measurements and water sampling were carried out in each sampling event.

Ÿ Measurements were taken at 3 water depths, namely, 1m below water surface, mid-depth and 1m above sea bed, except where the water depth less than 6m, the mid-depth station may be omitted. Should the water depth be less than 3m, only the mid-depth station was monitored.

Ÿ Analysis of suspended solids was carried out by ALS Technichem (HK) Pty Ltd.  Sufficient water samples were collected at the monitoring stations for carrying out the laboratory analysis. The analysis followed the standard methods as described in APHA Standard Methods for the Examination of Water and Wastewater, 19th Edition (APHA 2540D for SS).

Ÿ Water samples for suspended solids measurements were collected in high density polythene bottles, packed in ice (cooled to 4oC without being frozen), and delivered to a HOKLAS laboratory as soon as possible after collection.

Ÿ All monitoring equipment were certified by a laboratory accredited under HOKLAS. Calibration certificates of all monitoring equipment are provided in Appendix C.

2.6          Monitoring Schedule for the Reporting Month

2.6.1       The schedule for environmental monitoring in July 2017 is provided in Appendix D.

2.7          Action/Limit Levels

2.7.1       A baseline water quality monitoring for 15 locations were carried out 3 days per week for 4 weeks between 9 May 2017 and 3 June 2017.  Action and Limit Levels for water quality were established and summarized in Table 2.4 and Appendix E.

2.8          Results and Observations

2.8.1       The water quality monitoring was conducted on 11, 12, 13 and 20 July 2017. The monitoring results are summarized in Table 2.4. Detailed water quality monitoring data are presented in Appendix F.

2.8.2       One (1) Action Level exceedance of Suspended Solids at E3 at Mid-Flood tide on 12 July 2017 was recorded in the reporting month.

2.8.3       Exceedance was recorded at 10:36 am. According to the map below, the distance between the Cable Laying Barge (at 10:22 am) and E3 (at 10:36 am) is approximately 525m, which is larger than that from E2 (at 10:19 am) of approximately 299m. This indicates that E2 is likely to be higher potentially influenced by the Projectˇ¦s activities with a smaller distance from the Cable Laying Barge. However, the Suspended Solids recorded at E2 complied with the Action/Limit Level, thus which is smaller than that recorded at E3.

2.8.4       The current velocity and direction recorded at E3 were 18.8 cm/s and 145.9 degree respectively, water quality impact was unlikely to be caused by this Projectˇ¦s activities.

2.8.5       This exceedance was considered not likely to be caused by this Projectˇ¦s activities after investigation.  

 

Text Box:         Cable Laying Barge at 10:22 am on 12 July 2017
        Cable Laying Barge at 11:30 am on 12 July 2017
              Route of the Cable Laying Barge from 
              10 July 2017 to 12 July 2017
Rectangular Callout: E2 
ˇV	Sample Taken Date:    12 July 2017
ˇV	Sample Taken Time:   10:19am
ˇV	Distance:                      299 m
ˇV	Current Velocity:         16.7 cm/s
ˇV	Direction:                     154.5

Rectangular Callout: E3 
ˇV	Sample Taken Date:    12 July 2017
ˇV	Sample Taken Time:   10:36am
ˇV	Distance:                      525 m
ˇV	Current Velocity:         18.8 cm/s
ˇV	Direction:                     145.9

 

2.8.6       Four (4) Action Level exceedances of Dissolved Oxygen at surface & middle level at L1 (Mid-Flood, 11 July 2017), E3 (Mid-Flood, 11 July 2017), G1 (Mid-Ebb, 12 July 2017) and G2 (Mid-Ebb, 20 July 2017) were recorded in the reporting month. Exceedances were in the range of 6.02 ˇV 6.22 mg/L, which exceeded slightly the Action Level of 6.26 mg/L.

2.8.7       The distance between the Cable Laying Barge at the nearest time and L1 (at 9:35 on 11 July 2017), E3 (at 10:28 on 11 July 2017), G1 (at 16:30 on 12 July 2017) and G2 (at 12:19 on 20 July 2017) are approximately 1604m, 1124m, 2290m and 868m respectively. These exceedances were considered not likely to be caused by this Projectˇ¦s activities due to the large distance between the monitoring locations and the Cable Laying Barge.

Text Box:        Cable Laying Barge at 07:31on 11 July 2017
       Cable Laying Barge at 13:18 on 12 July 2017
       Cable Laying Barge at 09:13 on 20 July 2017
             Route of the Cable Laying Barge from 
             10 July 2017 to 20 July 2017
Rectangular Callout: G2 
ˇV	Sample Taken Date:    20 July 2017
ˇV	Sample Taken Time:   12:19am
ˇV	Distance:                      868 m
ˇV	Current Velocity:         26.4 cm/s
ˇV	Direction:                     69.5

Rectangular Callout: G1 
ˇV	Sample Taken Date:    12 July 2017
ˇV	Sample Taken Time:   16:30pm
ˇV	Distance:                      2290 m
ˇV	Current Velocity:         17.8 cm/s
ˇV	Direction:                     85.7

Rectangular Callout: E3 
ˇV	Sample Taken Date:    11 July 2017
ˇV	Sample Taken Time:   10:28am
ˇV	Distance:                      1124 m
ˇV	Current Velocity:         13.0 cm/s
ˇV	Direction:                     171.5

Rectangular Callout: L1 
ˇV	Sample Taken Date:    11 July 2017 
ˇV	Sample Taken Time:   09:35am
ˇV	Distance:                      1604 m
ˇV	Current Velocity:         12.7 cm/s
ˇV	Direction:                     79.8

2.8.8       One hundred and twenty (120) Action Level exceedances of Dissolved Oxygen at bottom level of all monitoring locations at both Mid-Ebb and Mid-Flood tide every monitoring day (11 ˇV 13, 20 July 2017) were recorded in the reporting month. Exceedances were in the range of 4.0 ˇV 6.0 mg/L, which exceeded slightly the Action Level of 6.10 mg/L.

2.8.9       The concentrations of Dissolved Oxygen at bottom level at Control Station (C1) were in the range of 4.02 ˇV 5.12 mg/L, which exceed the Action Level. This indicates that low concentration of Dissolved Oxygen was occurring over a large area including the areas well outside the influence of the Projectˇ¦s activities.

2.8.10    These exceedances were considered not likely to be caused by this Contractˇ¦s activities after investigation.

2.8.11    Proper mitigation measures on water quality (e.g. maximum speed of the Cable Burial Tool shall be limited) have been provided to reduce adverse impacts on water quality during construction activities. The effective implementation of mitigation measures ensured the compliance with action and limit levels of water quality during the reporting period.

2.8.12    The event action plan is presented in Appendix G.

 

 

E2 Mid-Depth

 

 



Table 2.4     Summary of Water Quality Monitoring Results in the Reporting Period

Locations

Parameters

Salinity

(ppt)

Dissolved Oxygen 

(mg/L)

Turbidity

(NTU)

Suspended Solids (mg/L)

Result

Action Level

Limit Level

Result (Surface & Middle)

Action Level

Limit Level

Result (Bottom)

Action Level

Limit Level

Result

Action Level

Limit Level

Result

Action Level

Limit Level

L1

Avg.

31.2

N/A

N/A

6.98

6.26

4

4.76

6.10

2

1.04

2.60

3.34

2.86

7.10

10.10

Min.

24.4

6.02

4.15

0.68

1.62

Max.

37.3

7.96

5.43

1.55

4.32

E1

Avg.

30.9

7.20

4.76

1.07

3.39

Min.

21.8

6.65

4.11

0.62

1.70

Max.

37.3

7.71

5.46

1.62

5.05

E2

Avg.

30.8

7.06

4.69

1.25

3.39

Min.

21.5

6.32

4.17

0.90

1.47

Max.

37.3

7.95

5.13

1.55

6.45

E3

Avg.

30.6

7.08

4.85

1.25

4.03

Min.

21.8

6.02

4.16

0.88

2.70

Max.

37.3

8.16

5.46

1.67

7.33

E4

Avg.

30.2

7.05

4.84

1.35

3.02

Min.

17.2

6.35

4.07

0.77

1.37

Max.

37.3

8.14

5.73

1.73

5.05

E5

Avg.

30.2

7.25

4.80

1.44

3.21

Min.

18.5

6.39

4.07

1.18

1.20

Max.

37.4

8.45

5.60

1.57

5.20

E6

Avg.

29.5

7.33

4.92

1.23

3.72

Min.

14.7

6.58

4.01

0.72

1.77

Max.

37.3

8.50

5.72

1.55

5.70

E7

Avg.

30.3

7.12

4.81

1.21

3.87

Min.

21.5

6.50

3.96

1.02

2.78

Max.

37.2

7.56

6.04

1.57

5.15

B1

Avg.

30.3

7.29

5.15

1.09

3.28

Min.

24.4

6.35

4.35

0.47

1.73

Max.

36.6

8.29

5.71

1.57

5.08

G1

Avg.

29.6

7.20

4.84

1.27

3.49

Min.

17.4

6.22

4.00

0.68

2.73

Max.

37.3

8.24

5.65

1.55

5.93

G2

Avg.

30.5

7.32

4.71

1.36

3.30

Min.

18.9

6.16

4.05

0.93

1.78

Max.

37.4

8.85

5.25

1.65

4.63

G3

Avg.

31.5

7.19

4.70

1.06

3.83

Min.

24.4

6.78

4.09

0.60

2.35

Max.

37.4

7.75

5.33

1.52

6.48

G4

Avg.

30.4

6.99

4.75

1.27

3.33

Min.

21.9

6.26

3.97

0.98

1.83

Max.

37.2

7.72

5.35

1.58

4.37

G5

Avg.

29.8

7.24

4.90

1.30

3.28

Min.

18.0

6.65

4.05

0.98

1.58

Max.

37.2

8.20

5.66

1.58

4.72

C1

Avg.

30.3

7.28

N/A

N/A

4.70

N/A

N/A

1.42

N/A

N/A

3.12

N/A

N/A

Min.

17.4

6.40

4.02

1.15

1.22

Max.

37.4

8.67

5.12

1.62

5.37


3              Silt Curtain monitoring and audit

3.1          Monitoring Requirements

3.1.1       In accordance with the Updated EM&A Manual, the silt curtain monitoring was conducted each day during which cable burial will be carried out from Ch.500m to Ch.2.5km in the Project.

3.2          Monitoring Equipment

3.2.1       The brand and model of water quality monitoring equipment is given in Table 3.1.

Table 3.1          Silt Curtain Monitoring Equipment

Equipment

Brand and Model

Turbiditimeter

WTW Turb 430T

Echo Sounder

Eagle Cuda-168

Global Positioning System

JRC DGPS 224 Model JLR-4341 with J-NAV 500 Model NWZ4551

3.3          Monitoring Locations

3.3.1       In accordance with the Updated EM&A Manual, water quality monitoring ˇ§insideˇ¨ the silt curtain (S1) (i.e. between burial tool and the silt curtain) and ˇ§outsideˇ¨ of the silt curtain (S2) (i.e. between the silt curtain and Cape Dˇ¦Aguilar Marine Reserve) were conducted.

3.4          Monitoring Parameters, Frequency and Duration

3.4.1       The monitoring parameters, frequency and duration of water quality monitoring are summarized in Table 3.2.

Table 3.2          Water Quality Monitoring Parameters, Frequency and Duration

Parameter

Frequency and Duration

Turbidity

Hourly basis,
each day during which cable burial will be carried out

 

3.5          Monitoring Methodology

3.5.1       The water quality monitoring procedures are presented in the following:

Ÿ All monitoring equipment were checked and calibrated before use.  Responses of sensors and electrodes were also checked with certified standard solutions before each use.

Ÿ Duplicate in-situ measurements were carried out in each sampling event.

Ÿ Measurements were taken at 1m above sea bed.

Ÿ All monitoring equipment were certified by a laboratory accredited under HOKLAS. Calibration certificates of all monitoring equipment are provided in Appendix C.

 

3.6          Limit Level

3.6.1       Water quality is considered to be unaffected by cable burial works if the monitoring result at S1 is <20% above the SDAILYBASELINE value. If the monitoring result at S1 is ≥20% above the SDAILYBASELINE value, then the results will be evaluated against the Limit Level. The Limit Level for S2 was established by the equation, S2LIMIT = (S1 ˇV SDAILYBASELINE) * 15% + SDAILYBASELINE, and summarized in Table 3.3.

3.7          Results and Observations

3.7.1       The silt curtain monitoring was conducted on 11 and 12 July 2017. The silt curtain monitoring was not carried out from 13 July 2017 onwards as cable burial works from Ch.500m to Ch.2.5km were completed on 12 July 2017. The monitoring results are summarized in Table 3.3.

3.7.2       SDAILYBASELINE recorded for 11 and 12 July 2017 are 1.065 and 1.740 NTU respectively. The values of 20% above the SDAILYBASELINE values are 1.278 and 2.088 NTU respectively.

3.7.3       Four (4) recorded S1 average turbidity is ≥20% above the SDAILYBASELINE value in the reporting month. Monitoring results which are ≥20% above the SDAILYBASELINE value were recorded at 14:31 pm and 16:30 pm on 11 July 2017 and at 14:05 pm and 15:05 pm on 12 July 2017. Limit Levels of S2LIMIT were established to evaluate these monitoring results.

3.7.4       No exceedance of Limit Level (i.e. S2LIMIT = (S1 ˇV SDAILYBASELINE) * 15%) + SDAILYBASELINE) was recorded in the reporting month.

3.7.5       Proper mitigation measures on water quality (e.g. maximum speed of the Cable Burial Tool shall be limited) have been provided to reduce adverse impacts on water quality during construction activities. The effective implementation of mitigation measures ensured the compliance with limit levels of water quality during the reporting period.

3.7.6       The event action plan is presented in Appendix G.

 

Table 3.3          Summary of Silt Curtain Monitoring Results in the Reporting Period

Date

Location

Sampling Hour

Sampling Start Time

Turbidity (NTU)

Average Turbidity (NTU)

SDAILY

BASELINE

20% above SDAILY BASELINE

Limit Level

S2 Limit

Exceedance

11 July 2017

S1

1st

13:30

0.94

0.88

0.910

1.065

N

N/A

N

S2

0.77

0.80

0.785

S1

2nd

14:31

1.80

1.88

1.840

Y

1.181

N

S2

0.91

0.85

0.880

S1

3rd

15:30

1.22

1.23

1.225

N

N/A

N

S2

0.99

0.90

0.945

S1

4th

16:30

1.50

1.53

1.515

Y

1.133

N

S2

1.08

1.03

1.055

12 July 2017

S1

1st

10:05

1.75

1.56

1.655

1.740

N

N/A

N

S2

1.18

1.24

1.210

S1

2nd

11:05

2.08

2.00

2.040

N

N/A

N

S2

1.38

1.46

1.420

S1

3rd

12:05

1.76

1.86

1.810

N

N/A

N

S2

1.40

1.37

1.385

S1

4th

13:05

2.02

2.11

2.065

N

N/A

N

S2

1.54

1.58

1.560

S1

5th

14:05

2.22

2.31

2.265

Y

1.819

N

S2

1.21

1.26

1.235

S1

6th

15:05

2.23

2.09

2.160

Y

1.803

N

S2

1.23

1.36

1.295

S1

7th

16:05

1.88

1.88

1.880

N

N/A

N

S2

1.58

1.51

1.545

S1

8th

17:05

1.51

1.47

1.490

N

N/A

N

S2

1.17

1.20

1.185

S1

9th

18:05

2.03

2.05

2.040

N

N/A

N

S2

1.29

1.34

1.315

4              Marine mammal observation

4.1          Monitoring Requirements

4.1.1       In accordance with the Updated EM&A Manual, marine mammal observations were conducted each day during which cable burial will be carried out from Ch.500m to Ch.10km in the Project.

4.2          Monitoring Equipment

4.2.1       Table 4.1 summarizes the equipment used for the marine mammal observation.

Table 4.1          Marine Mammal Observation Equipment

Equipment

Brand and Model

Binocular

Olympus 8 x 42 EXWP I

Camera

Nikon D90 18-105mm zoom lens

Global Positioning System

JRC DGPS 224 Model JLR-4341 with J-NAV 500 Model NWZ4551

 

4.3          Monitoring Locations and Frequency

4.3.1       In accordance with the Updated EM&A Manual, marine mammal observations were conducted in which the qualified observer stand on the upper decks of the barge and scan the 250m exclusion zone for at least 30 minutes before the installation work starts.

4.4          Results and Observations

4.4.1       Marine mammal observations were conducted on 11, 12, 13 and 20 July 2017.

4.4.2       The weather were mainly sunny with good visibility. Sea conditions were mainly at a Beaufort Sea State of 2 to 4.

4.4.3       No cetacean was observed in the exclusion zone for 30 minutes before the installation works start on 11, 12, 13 and 20 July 2017.

 

5              Conclusions and Recommendations

5.1.1       One (1) Action Level exceedance of Suspended Solids at E3 at Mid-Flood tide on 12 July 2017 was recorded in the reporting month. This exceedance was considered not likely to be caused by this Contractˇ¦s activities after investigation.

5.1.2       Four (4) Action Level exceedances of Dissolved Oxygen at surface & middle level at L1 (Mid-Flood, 11 July 2017), E3 (Mid-Flood, 11 July 2017), G1 (Mid-Ebb, 12 July 2017) and G2 (Mid-Ebb, 20 July 2017) were recorded in the reporting month. These exceedances were considered not likely to be caused by this Contractˇ¦s activities after investigation.

5.1.3       One hundred and twenty (120) Action Level exceedances of Dissolved Oxygen at bottom level of all monitoring locations at both Mid-Ebb and Mid-Flood tide every monitoring day were recorded in the reporting month. These exceedances were considered not likely to be caused by this Contractˇ¦s activities after investigation.

5.1.4       No exceedance of Limit Level of silt curtain monitoring was recorded in the reporting month.

5.1.5       No cetacean was observed in the exclusion zone for 30 minutes before the installation works start on 11, 12, 13 and 20 July 2017.

5.1.6       No environmental complaint, notification of summons and prosecution was received in the reporting month.