MTR Corporation Limited

 

 

 

 

 

 

 

 

 

 

Tuen Mun South Extension

Monthly EM&A Report No. 4

[For March 2024]


Table of Contents

 

 

Executive summary. I

1......... Introduction. 1

1.1         Background. 1

1.2         Project Programme. 1

1.3         Purpose of the Report 1

2......... Environmental Monitoring and Audit. 2

2.1         EM&A Results. 2

3......... implementation status on the environmental protection requirements. 4

 

 

List of Tables

 

Table 1.1             Summary of Awarded Works Contract

Table 2.1             Summary of Major Construction Activities in the Reporting Period

Table 2.2             Summary of 1-Hour TSP Monitoring Results in the Reporting Period

Table 2.3             Summary of Construction Noise Monitoring Results in the Reporting Period

Table 3.1             Summary of EP Submissions Status

 

 

 

List of Appendices

Appendix A       Monthly EM&A Report for Contract 1500 TME Stations, Viaducts and River Crossing (March 2024)

Appendix B       Monthly Ardeid Monitoring Result (March 2024)

 

 

 

 


Executive summary

The Tuen Mun South Extension (TME) is one of the seven recommended railway schemes in the Railway Development Strategy 2014 (“RDS-2014”).  The project will extend the Tuen Ma Line (TML), from Tuen Mun (TUM) Station southwards by about 2.4 km, terminating at a new station near Tuen Mun Ferry Pier (i.e. Tuen Mun South (TMS) Station) with an intermediate station at Tuen Mun Area 16 (i.e. A16 Station). 

 

The Environmental Impact Assessment (EIA) Report and its Environmental Monitoring and Audit (EM&A) Manual (Register No. AEIAR – 236/2022) for TME was approved on 12 July 2022, with an Environmental Permit

(EP) granted on 18 August 2022 (EP No. EP-615/2022).

 

The construction was commenced in December 2023. This is the 4th EM&A report documents the findings of EM&A works conducted during the period from 1 to 31 March 2024.

 

EM&A Activities Summary

A summary of the EM&A activities in this reporting month is listed below:

EM&A Activities

Date

Details

Air Quality Monitoring

1, 7, 13, 19, 25 and 28 March 2024

Refers to Appendix A

Noise Monitoring

1, 7, 13,19 and 25 March 2024

Refers to Appendix A

Water Quality Monitoring

N/A (1)

Refers to Appendix A

Monthly Ardeid Monitoring

20 March 2024

Refers to Appendix B

Environmental Site Inspection

6, 13, 20 and 27 March 2024

Refers to Appendix A

Note: (1) No construction work was conducted on Tuen Mun River Channel

 

Breaches of Action and Limit Levels for Air Quality

No exceedances of the Action / Limit Level of 1-hour TSP due to the Project construction were recorded in the reporting month. Details is provided in Appendix A.

 

Breaches of Action and Limit Levels for Noise

No exceedance of the Action / Limit Level of construction noise due to the Project construction was recorded in the reporting month. Details is provided in Appendix A.

 

Breaches of Action and Limit Levels for Water Quality

No water quality monitoring was conducted in the reporting month. Details is provided in Appendix A.

 

Complaint, Notification of Summons and Successful Prosecution

No complaint, notification of summons and successful prosecution were received in the reporting month. Details is provided in Appendix A.

 

Reporting Changes

There was no reporting change in the reporting month.

 

Future Key Issues

Key issues to be considered in the next three months included the following. Details is provided in Appendix A.

Location

Site Activities

Tuen Mun River West Bank

Tree felling, tree transplantation and construction of temporary platform

Wu Shan Road Recreation Playground

Tree felling, site clearance and preparation works

Pet Garden & Eastern Garden

Site clearance and preparation works

A16 (i.e. Tuen Mun Swimming Pool)

Tree felling, tree transplantation, pre-drilling works and construction of temporary platform

Wu King Road

Tree felling, tree transplantation and utilities diversions

Loading and Unloading Area 1 & 2

Site establishment

Viaduct on Tuen Mun River Channel

Site establishment and construction of temporary platform

Potential environmental impacts arising from the above construction activities are mainly associated with construction dust, construction noise, water quality, waste management, landscape and ecology.


1                 Introduction

 

1.1             Background

1.1.1        The Tuen Mun South Extension (TME) (hereinafter referred to as “the Project”) is one of the seven recommended railway schemes in the Railway Development Strategy 2014 (“RDS-2014”).  The Project will extend the Tuen Ma Line (TML), from Tuen Mun (TUM) Station southwards by about 2.4 km, terminating at a new station near Tuen Mun Ferry Pier (i.e. Tuen Mun South (TMS) Station) with an intermediate station at Tuen Mun Area 16 (i.e. A16 Station). 

1.1.2        The Environmental Impact Assessment (EIA) Report (Register No.: AEIAR-236/2022) for the Project was approved on 12 July 2022 under the Environmental Impact Assessment Ordinance (EIAO).  Following the approval of the EIA Report, an Environmental Permit (EP) was granted on 18 August 2022 (EP No: EP-615/2022) for the construction and operation of the Project.

1.2             Project Programme

1.2.1        The civil construction works contract (Contract 1500) of the Project was awarded in December 2023. The construction of the Project commenced in December 2023 and expected to complete in 2030. Table 1.1 presents the information of the awarded Works Contract.

Table 1.1       Summary of Awarded Works Contract

Works Contract

Description

Construction Start Date

Contractor

Environmental Team

1500

TME Stations, Viaducts and River Crossing

December 2023

CRBC – Building King Joint Venture

WSP (Asia) Ltd.

 

1.3             Purpose of the Report

1.3.1        The Environmental Monitoring and Audit (EM&A) programme for the Project commenced in December 2023. This is the 4th EM&A Report for the Project which summarises the EM&A works undertaken during the period from 1 to 31 March 2024.


 

2                 Environmental Monitoring and Audit

 

2.1             EM&A Results

2.1.1        The EM&A Report for Works Contract 1500 prepared by the Contractor’s ET is provided in Appendix A. The EM&A Report provides details of the project information, EM&A requirements, impact monitoring for air quality, noise and water quality, and audit results for the Contract.  The details of the monthly ardeid monitoring is presented in Appendix B.

2.1.2        A summary of the major construction activities undertaken by the Contractor of Works Contract during the reporting period are presented in Table 2.1.

Table 2.1       Summary of Major Construction Activities in the Reporting Period

Location

Site Activities

Tuen Mun River West Bank

Tree felling and preparation works of temporary platform construction

Wu Shan Road Recreation Playground

Tree felling, site clearance and preparation works

Pet Garden & Eastern Garden

Site clearance and preparation works

A16 (i.e. Tuen Mun Swimming Pool)

Tree felling, tree transplantation, preparation works of temporary platform construction and pre-drilling works

Wu King Road

Tree felling and utilities diversions

Loading and Unloading Area 1 & 2

Site establishment

Viaduct on Tuen Mun River Channel

Site establishment

 

2.1.3        During the reporting month, impact monitoring for air quality and construction noise were conducted in accordance with the EM&A Manual. No exceedances of the Action / Limit Level of 1-hour TSP and Action / Limit level of construction noise due to the Project construction were recorded. Results of air quality and construction noise are summarised in Tables 2.2 and 2.3 respectively. Details of the monitoring requirements, locations, equipment and methodology are presented in the EM&A Report in Appendix A.

Table 2.2     Summary of 1-Hour TSP Monitoring Results in the Reporting Period

Monitoring Station ID

Location

TSP Concentration (μg/m3)

Action Level (μg/m3)

Limit Level (μg/m3)

Exceedance due to the Project Construction (Yes/No)

AM1

Islamic Primary School

15 – 98

277.6

500

N/A

AM2a(1)

Oi Tak House, Yau Oi Estate

19 – 111

277.4

500

N/A

AM3

Yan Chai Hospital Law Chan Chor Si Primary School

53 – 140

279.9

500

N/A

AM4

Wu Tsui House, Wu King Estate

48 – 142

279.9

500

N/A

AM5

Tuen Mun Swimming Pool

19 – 98

277.1

500

N/A

Note:     (1)  Alternative monitoring location to AM2 Oi Lai House, Yau Oi Estate in the approved EM&A Manual.

 

Table 2.3     Summary of Construction Noise Monitoring Results in the Reporting Period

Monitoring Station ID

Location

Noise Level (Leq, 30mins, dB(A)

Limit Level (Leq, 30mins, dB(A)

Exceedance due to the Project Construction (Yes/No)

CN1

Tower 1, Century Gateway Phase 1

63 – 67

75

N/A

CN2

Islamic Primary School

60 – 62

70

N/A

60

65 during exams

N/A

CN3

Block 13, Lung Mun Oasis

60 – 64

75

N/A

CN4

Yan Chai Hospital Ho Sik Nam Primary School

65 – 69

70

N/A

64

65 during exams

CN5

Taoist Ching Chung Primary School

62 – 70

70

N/A

63

65 during exams

CN6

Tower 1, Oceania Heights

69 – 71

75

N/A

CN7

Block 1, Pierhead Garden

62 – 65

75

N/A

CN8

Wu Fai House

56 – 59

75

N/A

CN9

Block 8, Glorious Garden

57 – 63

75

N/A

CN10

Oi Lai House, Yau Oi Estate

61 – 66

75

N/A

CN11

Wu Tsui House

60 – 64

75

N/A

 

2.1.4        During the reporting period, water quality monitoring was not conducted since no major construction works was carrying out at the corresponding areas (i.e. On Tuen Mun River Channel).

2.1.5        Monthly ardeid monitoring was conducted on 20 March 2024 and the detail of the monitoring is presented in Appendix B.

2.1.6        No environmental complaints, notification of summons and successful prosecutions were recorded in the reporting period.  

2.1.7        Regular site inspections were conducted by the ET, ER and the Contractor on a weekly basis and IEC audits on a monthly basis to check the implementation of environmental pollution control and mitigation measures for the Project.  Details are provided in Appendix A.

 

3                 implementation status on the environmental protection requirements

3.1.1        The Contractor has implemented all mitigation measures and requirements as stated in the EIA Report, EM&A Manual and EP (EP No: EP-615/2022). Details are provided in Appendix A.

3.1.2        The status of required submissions under the EP as of the reporting period are summarised in Table 3.1.

Table 3.1     Summary of EP Submissions Status

EP Condition

(EP-615/2022)

Submission

Submission date

Status

Condition 1.12

Notification of Commencement Date of Construction

4 August 2023

3 October 2023 (update)

Deposited

Condition 1.14

Notification of Commencement Date of Operation

No later than 2 months prior to the commencement of operation

To be submitted in due course

Condition 2.11

EP Submission Schedule

19 October 2023

Deposited

Condition 2.12

Management Organization

7 November 2023

18 December 2023 (update)

27 February 2024 (update) 

Deposited

Condition 2.14

Construction Noise Management Plan (CNMP)

7 September 2023

13 December 2023 (update)

2 February 2024 (update) 

Deposited

Condition 2.15

Rail Noise Mitigation Plan (RNMP)

23 August 2023

Pending approval

Condition 2.16

Pre-Construction Ardeid Survey Plan (PASP)

1 August 2023

Approved (18 August 2023)

Condition 2.17

Pre-Construction Ardeid Survey Report (PASR)

1 November 2023

Deposited

Condition 2.18

Monthly Ardeid Monitoring Plan (MAMP)

9 August 2023

 

Approved (14 November 2023)

29 January 2024 (update)

Approved (15 February 2024)

Condition 2.19

Compensatory Tree Planting Implementation Plan (CTPIP)

To be submitted no later than 6 weeks of the commencement of the construction of the corresponding parts of the Project

To be submitted in due course

Condition 2.20

Landscape and Visual Mitigation Plan (LVMP)

To be submitted no later than 2 months before the commencement of the construction of the corresponding parts of landscape and visual mitigation measures of the Project

To be submitted in due course

Condition 2.21

Waste Management Plan (WMP)

6 November 2023

Deposited

Condition 2.25

Fixed Plant Noise Audit Report

To be submitted at least 1 month before commencement of operation of the Project

To be submitted in due course

Condition 2.26

Noise Performance Test Report

To be submitted at least 1 month before commencement of operation of the Project

To be submitted in due course

Condition 3.3

Baseline Monitoring Report

11 November 2023 (Water Quality)

21 November 2023 (Dust)

Deposited

Condition 3.4

Monthly EM&A Report No.1 – 3

Submitted within 10 working days after the end of the reporting month

Deposited

Monthly EM&A Report No.4

This submission

-

Condition 4.2

Dedicated Internet Website

9 January 2024

Deposited