Table of Contents
2......... Environmental Monitoring and Audit
3......... implementation status on the environmental protection requirements
List of Tables
Table 1.1 Summary of Awarded Works Contract
Table 2.1 Summary of Major Construction Activities in the Reporting Period
Table 2.2 Summary of 1-Hour TSP Monitoring Results in the Reporting Period
Table 2.3 Summary of Construction Noise Monitoring Results in the Reporting Period
Table 3.1 Summary of EP Submissions Status
List of Appendices
Appendix B Monthly Ardeid Monitoring Result (March 2024)
The Tuen Mun South Extension (TME) is one of the seven recommended railway schemes in the Railway Development Strategy 2014 (“RDS-2014”). The project will extend the Tuen Ma Line (TML), from Tuen Mun (TUM) Station southwards by about 2.4 km, terminating at a new station near Tuen Mun Ferry Pier (i.e. Tuen Mun South (TMS) Station) with an intermediate station at Tuen Mun Area 16 (i.e. A16 Station).
The Environmental Impact Assessment (EIA) Report and its Environmental Monitoring and Audit (EM&A) Manual (Register No. AEIAR – 236/2022) for TME was approved on 12 July 2022, with an Environmental Permit
(EP) granted on 18 August 2022 (EP No. EP-615/2022).
The construction was commenced in December 2023. This is the 4th EM&A report documents the findings of EM&A works conducted during the period from 1 to 31 March 2024.
EM&A Activities Summary
A summary of the EM&A activities in this reporting month is listed below:
EM&A Activities |
Date |
Details |
Air Quality Monitoring |
1, 7, 13, 19, 25 and 28 March 2024 |
Refers to Appendix A |
Noise Monitoring |
1, 7, 13,19 and 25 March 2024 |
Refers to Appendix A |
Water Quality Monitoring |
N/A (1) |
Refers to Appendix A |
Monthly Ardeid Monitoring |
20 March 2024 |
Refers to Appendix B |
Environmental Site Inspection |
6, 13, 20 and 27 March 2024 |
Refers to Appendix A |
Note: (1) No construction work was conducted on Tuen Mun River Channel
Breaches of Action and Limit Levels for Air Quality
No exceedances of the Action / Limit Level of 1-hour TSP due to the Project construction were recorded in the reporting month. Details is provided in Appendix A.
Breaches of Action and Limit Levels for Noise
No exceedance of the Action / Limit Level of construction noise due to the Project construction was recorded in the reporting month. Details is provided in Appendix A.
Breaches of Action and Limit Levels for Water Quality
No water quality monitoring was conducted in the reporting month. Details is provided in Appendix A.
Complaint, Notification of Summons and Successful Prosecution
No complaint, notification of summons and successful prosecution were received in the reporting month. Details is provided in Appendix A.
Reporting Changes
There was no reporting change in the reporting month.
Future Key Issues
Key issues to be considered in the next three months included the following. Details is provided in Appendix A.
Location |
Site Activities |
Tuen Mun River West Bank |
Tree felling, tree transplantation and construction of temporary platform |
Wu Shan Road Recreation Playground |
Tree felling, site clearance and preparation works |
Pet Garden & Eastern Garden |
Site clearance and preparation works |
A16 (i.e. Tuen Mun Swimming Pool) |
Tree felling, tree transplantation, pre-drilling works and construction of temporary platform |
Wu King Road |
Tree felling, tree transplantation and utilities diversions |
Loading and Unloading Area 1 & 2 |
Site establishment |
Viaduct on Tuen Mun River Channel |
Site establishment and construction of temporary platform |
Potential environmental impacts arising from the above construction activities are mainly associated with construction dust, construction noise, water quality, waste management, landscape and ecology.
Table 1.1 Summary of Awarded Works Contract
Works Contract |
Description |
Construction Start Date |
Contractor |
Environmental Team |
1500 |
TME Stations, Viaducts and River Crossing |
December 2023 |
CRBC – Building King Joint Venture |
WSP (Asia) Ltd. |
Table 2.1 Summary of Major Construction Activities in the Reporting Period
Location |
Site Activities |
Tuen Mun River West Bank |
Tree felling and preparation works of temporary platform construction |
Wu Shan Road Recreation Playground |
Tree felling, site clearance and preparation works |
Pet Garden & Eastern Garden |
Site clearance and preparation works |
A16 (i.e. Tuen Mun Swimming Pool) |
Tree felling, tree transplantation, preparation works of temporary platform construction and pre-drilling works |
Wu King Road |
Tree felling and utilities diversions |
Loading and Unloading Area 1 & 2 |
Site establishment |
Viaduct on Tuen Mun River Channel |
Site establishment |
Table 2.2 Summary of 1-Hour TSP Monitoring Results in the Reporting Period
Monitoring Station ID |
Location |
TSP Concentration (μg/m3) |
Action Level (μg/m3) |
Limit Level (μg/m3) |
Exceedance due to the Project Construction (Yes/No) |
AM1 |
Islamic Primary School |
15 – 98 |
277.6 |
500 |
N/A |
AM2a(1) |
Oi Tak House, Yau Oi Estate |
19 – 111 |
277.4 |
500 |
N/A |
AM3 |
Yan Chai Hospital Law Chan Chor Si Primary School |
53 – 140 |
279.9 |
500 |
N/A |
AM4 |
Wu Tsui House, Wu King Estate |
48 – 142 |
279.9 |
500 |
N/A |
AM5 |
Tuen Mun Swimming Pool |
19 – 98 |
277.1 |
500 |
N/A |
Note: (1) Alternative monitoring location to AM2 Oi Lai House, Yau Oi Estate in the approved EM&A Manual.
Table 2.3 Summary of Construction Noise Monitoring Results in the Reporting Period
Monitoring Station ID |
Location |
Noise Level (Leq, 30mins, dB(A) |
Limit Level (Leq, 30mins, dB(A) |
Exceedance due to the Project Construction (Yes/No) |
CN1 |
Tower 1, Century Gateway Phase 1 |
63 – 67 |
75 |
N/A |
CN2 |
Islamic Primary School |
60 – 62 |
70 |
N/A |
60 |
65 during exams |
N/A |
||
CN3 |
Block 13, Lung Mun Oasis |
60 – 64 |
75 |
N/A |
CN4 |
Yan Chai Hospital Ho Sik Nam Primary School |
65 – 69 |
70 |
N/A |
64 |
65 during exams |
|||
CN5 |
Taoist Ching Chung Primary School |
62 – 70 |
70 |
N/A |
63 |
65 during exams |
|||
CN6 |
Tower 1, Oceania Heights |
69 – 71 |
75 |
N/A |
CN7 |
Block 1, Pierhead Garden |
62 – 65 |
75 |
N/A |
CN8 |
Wu Fai House |
56 – 59 |
75 |
N/A |
CN9 |
Block 8, Glorious Garden |
57 – 63 |
75 |
N/A |
CN10 |
Oi Lai House, Yau Oi Estate |
61 – 66 |
75 |
N/A |
CN11 |
Wu Tsui House |
60 – 64 |
75 |
N/A |
Table 3.1 Summary of EP Submissions Status
(EP-615/2022) |
Submission |
Submission date |
Status |
Condition 1.12 |
Notification of Commencement Date of Construction |
4 August 2023 3 October 2023 (update) |
Deposited |
Condition 1.14 |
Notification of Commencement Date of Operation |
No later than 2 months prior to the commencement of operation |
To be submitted in due course |
Condition 2.11 |
EP Submission Schedule |
19 October 2023 |
Deposited |
Condition 2.12 |
Management Organization |
7 November 2023 18 December 2023 (update) 27 February 2024 (update) |
Deposited |
Condition 2.14 |
Construction Noise Management Plan (CNMP) |
7 September 2023 13 December 2023 (update) 2 February 2024 (update) |
Deposited |
Condition 2.15 |
Rail Noise Mitigation Plan (RNMP) |
23 August 2023 |
Pending approval |
Condition 2.16 |
Pre-Construction Ardeid Survey Plan (PASP) |
1 August 2023 |
Approved (18 August 2023) |
Condition 2.17 |
Pre-Construction Ardeid Survey Report (PASR) |
1 November 2023 |
Deposited |
Condition 2.18 |
Monthly Ardeid Monitoring Plan (MAMP) |
9 August 2023
|
Approved (14 November 2023) |
29 January 2024 (update) |
Approved (15 February 2024) |
||
Condition 2.19 |
Compensatory Tree Planting Implementation Plan (CTPIP) |
To be submitted no later than 6 weeks of the commencement of the construction of the corresponding parts of the Project |
To be submitted in due course |
Condition 2.20 |
Landscape and Visual Mitigation Plan (LVMP) |
To be submitted no later than 2 months before the commencement of the construction of the corresponding parts of landscape and visual mitigation measures of the Project |
To be submitted in due course |
Condition 2.21 |
Waste Management Plan (WMP) |
6 November 2023 |
Deposited |
Condition 2.25 |
Fixed Plant Noise Audit Report |
To be submitted at least 1 month before commencement of operation of the Project |
To be submitted in due course |
Condition 2.26 |
Noise Performance Test Report |
To be submitted at least 1 month before commencement of operation of the Project |
To be submitted in due course |
Condition 3.3 |
Baseline Monitoring Report |
11 November 2023 (Water Quality) 21 November 2023 (Dust) |
Deposited |
Condition 3.4 |
Monthly EM&A Report No.1 – 3 |
Submitted within 10 working days after the end of the reporting month |
Deposited |
Monthly EM&A Report No.4 |
This submission |
- |
|
Condition 4.2 |
Dedicated Internet Website |
9 January 2024 |
Deposited |