Content |
Chapter Title Page
Figure 1.1:_ General Layout
Plan Figure 1.2:_ Location of
Secondary Boundary Fence and Noise Monitoring Station at Section 4 |
Tables
This is the 8th Monthly EM&A Report for
the works carried out during the reporting month from 1 to 31 January 2011, and
presents a summary of the environmental monitoring and audit works, list of
activities, and mitigation measures implemented during the abovementioned
reporting month.
Site Activities
The following major construction activities took place
during the reporting month:
Works Order No. 1 (ASD 010962):
¡
No
major works. (Substantial completion was certified on 12 October 2010.)
Works Order No. 2 (ASD 010969):
¡
Tree
pruning work;
¡
Installation
of transparent panel for the new boundary fence;
¡
Construction
of footing for the new boundary fence;
¡
Construction
of steel frame and mesh for the new boundary fence;
¡
Excavation
works for footing of steel fence;
¡
Reinstatement
of pavement and carriageway; and
¡
Construction
of footing for the new pedestrian gate.
Works Order No. 3 (ASD 010974):
¡
Erection
of hoarding for the new check point;
¡
Construction
of stud wall and retaining wall at the new check point site; and
¡
Construction
of footing and super-structural works at the new check point site.
Breach of Action and Level Limits
There was no breach of Action or Limit levels for
noise level (measured as Leq) in the reporting month.
Complaints
There was no record of complaints received in the reporting month.
Notification of Summons and Successful Prosecutions
There was no record of Notification of summons and
successful prosecution in the reporting month.
Reporting Changes
There are no reporting changes in the reporting month.
Future Key Issues
Future key issues to be considered in the forthcoming
month include:
Air
¡
Regular
maintenance of all plant and equipment;
¡
Handling
of any excavated dusty materials or stockpile of dusty materials;
¡
Spraying
of water prior to any loading, unloading or transfer of dusty materials; and
¡
Washing
of vehicles before leaving the construction sites.
Noise
¡
Location
of noisy equipment and noisy activities relative to the Noise Sensitive
Receivers (NSRs);
¡
Avoiding
the operation of unused equipment, and minimising the use of Powered Mechanical
Equipment (PME) and parallel use of noisy equipment / machinery;
¡
Adoption
of Level 1 site-specific direction mitigation measures (use of quiet plant and
movable noise barrier) for construction/demolition work undertaken at a
distance of 60m or less to the NSRs; and
¡
Regular
maintenance of all plant and equipment.
Water Quality
¡
No
discharge of silty water into the storm drain and drainage channel within and
the vicinity of the site;
¡
Removal
off-site of construction plant causing pollution to water system due to leakage
of oil or fuel; and
¡
Temporary
stockpiling of excavated soil in a specially designated area with provision of
tarpaulin cover.
Waste
¡
Control
measures at the stockpiling area to prevent the generation of dust and
pollution of stormwater channels, fish ponds or river channels;
¡
Segregation,
storage, transportation and disposal of different types of waste; and
¡
Keeping
of records of quantities of wastes generated, recycled and disposal (with
locations).
Ecology
¡
Good
site practices for controlling the dust and water quality; and
¡
Clear
definition of works limit to avoid impact on adjacent habitats.
Landscape and Visual
¡
Retain
tree with high amenity or ecology value and contributing most to landscape and
amenity of site;
¡
Precautionary
area around trees to be retained equal to half of the tree canopy diameter;
¡
Prohibition
of the storage of materials including fuel, the movement of construction
vehicles, and the refuelling and washing of equipment including concrete mixers
within the precautionary area;
¡
Pruning
of the branches of existing trees identified for transplantation and retention;
¡
Rectification
and repair of damaged vegetation following the construction phase to its
original condition;
¡
Careful
monitoring of all works affecting the trees identified for retention and
transplantation; and
¡
Enforcement
of construction site controls including storage of materials, location and
appearance of site accommodation and the careful design of site lighting to
prevent light spillage.
Environmental mitigation measures will be implemented
on site as recommended and weekly site audits will be carried out to ensure
that the environmental conditions are acceptable.
The Frontier Closed Area (FCA) is an
integral part of the package of measures aimed at maintaining the integrity of
the boundary of the Hong Kong Special Administrative Region (HKSAR) with
mainland
The PBF and SBF (hereafter referred
to as ‘The Project’) will be erected along the northern and southern curbs of
the realigned BPR respectively to facilitate the Hong Kong Police Force (HKPF)
in combating cross-boundary criminal activities. The reduced FCA will comprise a narrow strip
of land covering the realigned BPR and areas to its north, together with the
points of crossing the boundary (i.e. the Boundary Control Points and Sha Tau
Kok town). Areas south of the SBF will
generally be excised from the FCA.
An Environmental Impact Assessment
(EIA) for the proposed works was carried out under the Environmental Impact
Assessment Ordinance (EIAO, Cap 499). An EIA Report and an Environmental
Monitoring and Audit (EM&A) Manual were completed in January 2009 and
approved by the Environmental Protection Department (EPD) in April 2009
(Register No. AEIAR-136/2009). The entire length of the proposed works is about
21.7 km from west of Pak Hok Chau to east of Sha Tau Kok and is divided into four
sections. A general layout plan of the Project site is presented in Figure
1.1, while the location of the SBF at Section 4 in
Sha Tau Kok is presented in Figure
1.2.
An Environmental Permit (EP)
covering the overall proposed works was issued in June 2009 (Permit No.
EP-347/2009). An application for Variation of the Environmental Permit (VEP)
(Application No. VEP-314/2010) was subsequently submitted on 24 May 2010 and
the amended Environmental Permit (Permit No. EP-347/2009/A) was issued by EPD
on 9 June 2010.
With regard to Section 4, an
application for a Further Environmental Permit (FEP) covering the works under
Works Order No. ASD 010962 (also known as Works Order No. 1) was submitted to
EPD on 2 March 2010 (Application No. FEP-104/2010) and this was granted on 29
March 2010 (Permit No. FEP-03/347/2009). Furthermore, another application for
an FEP covering the works under Works Order Nos. ASD 010969 and ASD 010974
(also known as Works Order Nos. 2 and 3 respectively) – including a new section
of SBF consisting of transparent panel, a new checkpoint and kiosk – was
submitted to EPD on 13 August 2010 (Application No. FEP-112/2010) and was
granted on 7 September 2010 (Permit No. FEP-04/347/2009/A).
The Architectural Services
Department (ArchSD) has been entrusted with the management of the Project by
the Project Proponent – the Secretary for Security of the HKSAR Government.
Mott MacDonald Hong Kong Limited (MMHK) has in turn been commissioned by ArchSD
as the consulting engineer for the entire Project under Consultancy Agreement
No. 9SN005, and is the Engineer’s Representative (ER) for construction of the
Project.
For Section 4 of the Project, MMHK
and ENVIRON Hong Kong Limited (ENVIRON) have been commissioned as the
Environmental Team (ET) and Independent Environmental Checker (IEC)
respectively to undertake the Environmental Monitoring and Audit (EM&A)
programme as described in the approved EM&A Manual of the Project. Also,
the Contract to undertake and perform the construction works for Section 4 was
awarded to Chun Wo Construction & Engineering Company Limited (‘The
Contractor’) and is scheduled to last for approximately 18 months. It formally
commenced on 28 May 2010, and the construction works and EM&A programme
under the above-mentioned EP and FEP(s) also commenced on this date. The
construction works programme is presented in Appendix A.
This monthly EM&A report
summarises the environmental monitoring and audit works, list of activities and
mitigation measures implemented at Section 4 during the period of 1 to 31
January 2011 inclusive (‘reporting month’).
The scope of works for Section 4
consists of:
¡
Erection
of an SBF from the entrance of the Sha Tau Kok town (i.e. the location of ‘Gate
One’) to the Sha Tau Kok Control Point (approximately 0.5 km);
¡
Use
of transparent panel for a section of an SBF;
¡
Provision
of a two-storey high checkpoint at ‘Gate One’;
¡
Addition
of a kiosk/guard house on an existing footpath of
¡
Removal
of the existing checkpoint at Shek Chung Au.
The organisation chart and lines of
communication with respect to the on-site environmental management structure
together with the contact information of the key personnel are shown in Appendix
B.
1.3
Works
Undertaken in the Reporting Month
The following activities have taken
place during the reporting month:
Works Order No. 1 (ASD 010962):
¡
No
major works. (Substantial completion was certified on 12 October 2010.)
Works Order No. 2 (ASD 010969):
¡
Tree
pruning work;
¡
Installation
of transparent panel for the new boundary fence;
¡
Construction
of footing for the new boundary fence;
¡
Construction
of steel frame and mesh for the new boundary fence;
¡
Excavation
works for footing of steel fence;
¡
Reinstatement
of pavement and carriageway; and
¡
Construction
of footing for the new pedestrian gate.
Works Order No. 3 (ASD 010974):
¡
Erection
of hoarding for the new check point;
¡
Construction
of stud wall and retaining wall at the new check point site; and
¡
Construction
of footing and super-structural works at the new check point site.
Figure 1.1: General Layout Plan
Figure 1.2: Location of Secondary
Boundary Fence and Noise Monitoring Station at Section 4
1.1
Summary
of EM&A Requirements
The EM&A programme requires environmental
monitoring of construction noise as well as environmental site inspections for
air quality, noise, water quality, waste management, ecology, landscape and
visual, as specified in the approved EM&A Manual.
Originally,
the EM&A Manual designated two locations as noise monitoring stations
during the construction phase. However, currently noise levels at only one of
these monitoring stations (as shown in Figure 1.2) are monitored. The reasons for this arrangement
are detailed in Section 3.2.
A summary of impact EM&A
requirements is presented in Table
2.1. The Environmental Quality Performance Limits and
the Event and Action Plans (for construction noise only) are shown in Appendix
C and Appendix D respectively.
Table 2.1: Summary of EM&A Impact
Requirements
Parameters |
Description |
Location(s) |
Frequency |
Duration |
Air |
On-site
Inspection |
Active Works Sites |
Weekly |
During Construction |
Noise |
Leq,
30min |
STK-DBD |
Weekly |
During Construction |
Waste management |
On-site Waste Audit |
Active Works Sites |
Weekly |
During Construction |
On-site Waste Inspection |
||||
Wastewater |
On-site Wastewater Audit |
Active Works Sites |
Weekly |
During Construction |
Ecology |
On-site Audit of Recommended Ecological Mitigation Measures |
Active Works Sites |
Periodically (by Contractor) |
As specified in EM&A Manual (see Table E.5) |
Landscape and Visual |
On-site Audit of Recommended Landscape and Visual Mitigation Measures |
Active Works Areas |
Regular intervals (by Contractor/ Landscape Sub-Contractor) |
As specified in EM&A Manual (see Table E.6) |
General Site Conditions |
Environmental Site Inspection |
Works areas and areas affected by works |
Weekly |
During Construction |
1.2
Implementation
of Environmental Mitigation Measures
The Contractor is required to
implement mitigation measures listed in the latest valid EP and FEP(s) (where
applicable), EIA Report and EM&A Manual. During routine site inspections,
the Contractor's implementation of mitigation measures, if any, are to be inspected
and reviewed. A schedule of the implementation of mitigation measures
identified at the EIA stage is given in Appendix E.
2.1
Monitoring
Parameters, Frequency and Duration
Following the requirements in the
EM&A Manual for noise, noise monitoring has to be carried out during the
construction phase. Continuous noise monitoring for the A-weighted levels Leq,
L10 and L90 is undertaken once per every week during
daytime hours (between 07:00 and 19:00) on normal weekdays.
Table 3.1 summarizes the monitoring parameters, frequency
and duration of air quality monitoring. The noise monitoring schedule during
the reporting month is presented in Appendix F.
Table 3.1: Noise Monitoring Parameters,
Frequency and Duration
Monitoring Station |
Parameter |
Frequency |
Duration |
STK-DBD |
Leq, L90 & L10 |
Once every week |
30 min |
Originally, two construction noise
monitoring stations were proposed in the EM&A Manual, namely: STK03 (Block 1,
Sha Tau Kok Estate) and STK05 (Village House at Sha Tau Kok). STK03 was mainly
selected for the construction works related to the SBF and the new checkpoint
in Sha Tau Kok, while STK05 was mainly selected for the removal of the existing
checkpoint at Shek Chung Au.
However, access to STK03 to perform
noise monitoring was not granted, therefore an alternative nearby location –
STK-DBD (HKPF Operation Base, Sha Tau Kok Division, Border District) – was
proposed by ET and agreed to by IEC and EPD. Baseline noise monitoring was
subsequently conducted at STK-DBD from 16 to 29 March 2010.
Currently, there is no solid
timetable or programme for the demolition works of the existing checkpoint at
Shek Chung Au, although the end of 2011 has been proposed as a possible
commencement date. This is subject to future confirmation of the demolition
programme by the Security Bureau and HKPF. No noise monitoring at STK05 has
been carried out at this stage.
As a result, only one noise impact
monitoring station is included in the current EM&A programme for Section 4.
The location of the agreed noise quality monitoring station is listed in Table
3.2 and shown in Figure 1.2.
Table 3.2: Noise Impact Monitoring
Location
Monitoring Station |
Description of Location |
Type of measurement |
STK-DBD |
HKPF Operational Base, Sha Tau Kok Division, Border District |
Façade |
Integrating Sound Level Meter will
be used for noise monitoring. It is a Type 1 sound level meter capable of
giving a continuous readout of the noise level readings including equivalent
continuous sound pressure level (Leq) and percentile sound pressure
level (Lx). They comply with International Electrotechnical
Commission Publications 651:1979 (Type 1) and 804:1985 (Type 1). Table 3.3 summarizes the noise monitoring equipment
model(s) being used.
Table 3.3: Noise Monitoring Equipment
Equipment |
Model(s) |
Precision Integrating Sound Level Meter |
Rion NL-18 & NL-31 |
Acoustic Calibrator |
Castle GA607 |
The
calibration frequencies of the monitoring equipment are provided in Table
3.4.
Table 3.4: Noise Monitoring Equipment
Calibration Frequencies
Equipment, Model and Serial Number |
Calibration Frequency |
Calibration Due Date(s) |
Precision Integrating Sound Level Meter (NL7-SLM-02) Rion NL-18 (serial number 00570459) |
Every year |
12 Dec 2011 |
Precision Integrating Sound Level Meter Rion NL-31 (serial number 01262786) |
Every year |
10 May 2011 |
Acoustic Calibrator Castle GA607 (serial number 040162) |
Every year |
9 Dec 2011 |
The calibration certificates are
presented in Appendix
G.
¡
The
Sound Level Meter was set on a tripod at a height of at least 1.2 m above the
ground.
¡
Façade
measurements were made at the monitoring locations.
¡
The
battery condition was checked to ensure the correct functioning of the meter.
¡
Parameters
such as frequency weighting, the time weighting and the measurement time were
set as follows:
- frequency weighting: A
- time weighting: Fast
- time measurement: 5-minute intervals
(between 07:00 and 19:00); Leq (30 min) was determined by
calculating the logarithmic average of six Leq (5-min) data.
¡
Prior
to and after each noise measurement, the meter was calibrated using a
Calibrator for 94 dB at 1 kHz. If the
difference in the calibration level before and after measurement was more than
1 dB, the measurement would be considered invalid and have to be repeated after
re-calibration or repair of the equipment.
¡
During
the monitoring period, the Leq, L10 and L90
noise levels were recorded. In addition,
any site observations and noise sources were recorded on a standard record
sheet.
2.5.2
Maintenance
and Calibration
¡
The
microphone head of the sound level meter and calibrator is cleaned with soft
cloth at quarterly intervals.
¡
The
meter and calibrator are sent to the supplier or Hong Kong Laboratory
Accreditation Scheme (HOKLAS) laboratory to check and calibrate at yearly
intervals.
2.6
Results
of Impact Monitoring
The measured construction noise levels, in
terms of Leq (30-min), during the reporting month are summarised in Table
3.5. Detailed
results, including general weather conditions and graphical presentations are
presented in Appendix
H.
Table 3.5: Results of Noise Impact
Monitoring
Monitoring Station |
Measured Leq (30-min) Range, dB(A) |
Limit Level for Leq, dB(A) |
STK-DBD |
62 – 65 |
75 |
Note: All figures are rounded off to the
nearest whole number.
No exceedance of Action / Limit Levels for
construction noise was recorded.
No direct comparison between the measured noise
levels and the construction noise levels predicted in the EIA Report for this
Project was possible due to the minor nature of site works conducted during the
reporting month.
Wind data obtained from the nearest Hong Kong
Observatory monitoring station, at Ta Kwu Ling, covering all noise monitoring
days during the reporting month is included in Appendix
K.
Environmental site inspections were
carried out on a weekly basis to monitor the proper implementation of
environmental pollution control and mitigation measures for Section 4. In the
reporting month, one monthly site inspections were carried out jointly by the
ER, Contractor, ET and IEC on 31 January 2011, and additional weekly site
inspections were carried out by the ER, Contractor and ET on 8, 14, 19 and 25
January 2011. The EM&A schedule is presented in Appendix
F.
Major findings provided jointly by
the ET and IEC during the joint monthly site inspections, and provided by ET
during the additional weekly site inspections, are summarised in Table 4.1. In general, the works site areas were found to
be in compliance with the environmental mitigation requirements listed in the
EM&A Manual and no adverse impacts were found.
Table 4.1: Summary of Environmental
Site Inspections
Date of Inspection |
Major Observations |
Status |
8 Jan 2011 |
The Contractor is again reminded to provide and maintain all necessary tree protection works in the areas covered by Works Order No. 2. This includes placement of construction materials away from trees and proper fencing of precautionary areas. |
Tree protection measures, including fencing of precautionary areas and backfilling of excavated soil as early as possible as possible after completion of footing for the new boundary fence, were provided in the works areas covered by Works Order No. 2, as observed on 31 Jan 2011. (closed) |
|
Extra hoarding was provided at the site entrance. However, some construction dust was still observed in the public area and should be cleared as soon as possible. |
Construction dust was cleared from the public area, as observed on 14 Jan 2011. (closed) |
|
The EP and FEP were not observed at the new checkpoint site. The Contractor is asked to reinstate these as soon as possible. |
The EP and FEP were displayed at the new checkpoint site entrance, as observed on 25 Jan 2011. (closed) |
14 Jan 2011 |
Some material from site concrete works had spilt to the adjacent car park. The Contractor is reminded to prevent dusty construction materials from leaving the site area. Wheel wash facilities should be implemented if required. |
As observed during the follow-up site inspection on 19 Jan 2011, water hose was used to clean a cement truck during concrete works before its departure from the new checkpoint site. No silty run-off or dusty construction materials were discharged from the site. (closed) |
19 Jan 2011 |
Nil. |
N/A |
25 Jan 2011 |
Some discarded plastic bottles were observed within a site boundary. The Contractor is reminded to dispose of these properly. |
Discarded plastic bottles were removed from site and disposed of, as observed on 31 Jan 2011. (closed) |
31 Jan 2011 |
Nil. |
N/A |
During the reporting month, one
environmental meeting was held on 31 January 2011.
3.3
Status
of Environmental Submissions, Permits and Licences
A summary of
status of all environmental submissions, valid permits/licences, and/or
notifications to EPD for this Project during the reporting month is presented
in Table
4.2. A summary of submissions made under the valid EP
and FEP(s) for Section 4 during the same period is presented in Table 4.3.
Table 4.2: Status of Environmental
Submissions, Permits and Licences
Statutory Reference |
Description |
Permit / Reference No. |
Valid Period |
Status |
EIAO |
Environmental Permit |
EP-347/2009/A |
9 Jun 2010 – present |
Valid |
EIAO |
Further Environmental Permit |
FEP-03/347/2009 |
29 Mar 2010 – present |
Valid |
EIAO |
Application for Further Environmental Permit (Remaining Section) |
FEP-112/2010 |
- |
Submitted to EPD on 13 Aug 2010. Approved by EPD on 7 Sep 2010. |
EIAO |
Further Environmental Permit (Remaining Section) |
FEP-04/347/2009/A |
7 Sep 2010 – present |
Valid |
APCO |
Notification pursuant to Section 3(1) of the Air Pollution Control (Construction Dust) Regulation (Form NA) |
312959 EPD notified on 4 Jan 2010 |
- |
Valid |
Legend: EIAO
– Environmental
Impact Assessment Ordinance (Cap 499)
APCO – Air Pollution Control Ordinance (Cap 311)
WPCO – Water Pollution Control Ordinance (Cap 358)
WDO – Waste Disposal Ordinance (Cap 354)
NCO – Noise Control Ordinance (Cap 400)
Table 4.3: Environmental Submissions
Made under the Valid EP & FEP(s) during the Reporting Month
EP/FEP Ref. |
Description |
Submission Date |
EP Condition 4.5 & FEP(s) Condition 4.5 |
Monthly EM&A Report (Dec 2010) |
14 Jan 2011 |
3.4
Advice
on the Solid and Liquid Waste Management Status
The construction and demolition
(C&D) material and general refuse generated by Section 4 of the Project in
the reporting month are shown in Appendix I. Wastes were handled and disposed from site in
accordance with the EM&A Manual and all relevant legislation and
regulations.
3.5
Review
of Environmental Monitoring Procedures
The monitoring works conducted by
the Environmental Team have been reviewed regularly. No changes in the
environmental monitoring procedures are considered necessary at this stage.
3.6
Implementation
Status of Environmental Mitigation Measures
An Implementation Schedule of
Mitigation Measures from the EIA Report / EM&A Manual is provided in Appendix
E, in the following order (see Table 4.4):
Table 4.4: Implementation Schedule of
Mitigation Measures
Parameter |
Table |
Air Quality |
|
Noise |
|
Water Quality |
|
Waste Management |
|
Ecology |
|
Landscape and Visual |
4.1
Non-compliance
of Action and Limit Levels
There was no breach of Action or
Limit Levels for construction noise impact monitoring in the reporting month.
No environmental complaints were
received or made against Section 4 of the Project during the reporting month.
The complaint log is presented in Appendix J.
4.3
Notifications
of Summons and Successful Prosecutions
No notifications of summons or
successful prosecution were received or made against Section 4 of the Project
during the reporting month.
5.1
Construction
Programme for the Next Reporting Month
The major construction works
forecast for Section 4 in February 2011 will be:
Works Order No. 1 (ASD 010962):
¡
No
major works forecast.
Works Order No. 2 (ASD 010969):
¡
Tree
felling and pruning work;
¡
Delivery
of materials to site;
¡
Installation
of transparent panel for the new boundary fence.
¡
Construction
of footing for the new boundary fence;
¡
Erection
of steel frame and mesh along the boundary fence; and
¡
Excavation
works for the new boundary fence;
¡
Fabrication
works for the new boundary fence;
¡
Construction
of footing for the new pedestrian gate.
¡
Construction
of footing for the new vehicular gates.
Works Order No. 3 (ASD 010974):
¡
Erection
of hoarding for the new check point;
¡
Construction
of retaining wall at the new check point site; and
¡
Construction
of footing and super-structural works at the new check point site.
5.2
Key
Issues for the Next Reporting Month
Based on the forecast major
construction works listed in Section 6.1, the key environmental issues to be considered
include:
¡
All
plant and equipment to be maintained to prevent any undue air emissions.
¡
Any
excavated dusty materials or stockpile of dusty materials should be covered entirely
by impervious sheeting or sprayed with water so as to maintain the entire
surface wet, and recovered or backfilled or reinstated within 24 hours of the
excavation or unloading;
¡
All
dusty materials should be sprayed with water prior to any loading, unloading or
transfer; and
¡
Every
vehicle should be washed to remove any dusty materials from its body and wheels
before leaving the construction sites.
¡
Noisy
equipment and noisy activities should be located as far away from the Noise
Sensitive Receivers (NSRs) as is practical;
¡
Unused
equipment should be turned off. Powered Mechanical Equipment (PME) should be
kept to a minimum and the parallel use of noisy equipment / machinery should be
avoided;
¡
Adoption
of Level 1 site-specific direction mitigation measures (use of quiet plant and
movable noise barrier) for construction/demolition work undertaken at a
distance of 60m or less to the NSRs; and
¡
Regular
maintenance of all plant and equipment.
¡
No
discharge of silty water into the storm drain and drainage channel within and
the vicinity of the site;
¡
Any
construction plant which causes pollution to the water system due to leakage of
oil or fuel shall be removed off-site immediately; and
¡
Excavated
soil which needs to be temporarily stockpiled should be stored in a specially
designated area and provided with a tarpaulin cover to avoid runoff into the
drainage channels.
¡
Control
measures should be taken at the stockpiling area to prevent the generation of
dust and pollution of stormwater channels, fish ponds or river channels;
¡
Different
types of waste should be segregated, stored, transported and disposed of in
accordance with the relevant legislative requirements and guidelines; and
¡
Records
of quantities of wastes generated, recycled and disposal (with locations) shall
be kept.
¡
Good
site practices for controlling the dust and water quality (avoid stockpiles
adjacent to wetlands, covering the stockpiles with impervious sheeting, control
of vehicle speed, no discharge of silty water to the rivers, streams and
drainage channels); and
¡
Clear
definition of works limit to avoid impact on adjacent habitats.
¡
Retain
trees that have high amenity or ecology value and contribute most to the
landscape and amenity of the site and its immediate environs;
¡
Creation
of precautionary area around trees to be retained equal to half of the tree
canopy diameter. Precautionary area to be fenced;
¡
Prohibition
of the storage of materials including fuel, the movement of construction
vehicles, and the refuelling and washing of equipment including concrete mixers
within the precautionary area;
¡
Pruning
of the branches of existing trees identified for transplantation and retention
to be based on the principle of crown thinning maintaining their form and
amenity value;
¡
The
rectification and repair of damaged vegetation following the construction phase
to its original condition prior to the commencement of the works or replacement
using specimens of the same species, size and form where appropriate to the
design intention of the area affected;
¡
All
works affecting the trees identified for retention and transplantation will be
carefully monitored. This includes the key stages in the preparation of trees, the
implementation of protection measures and health monitoring throughout the
construction period; and
¡
Construction
site controls should be enforced including the storage of materials, the
location and appearance of site accommodation and the careful design of site
lighting to prevent light spillage.
5.3
Monitoring
Schedule for the Next Reporting Month
The tentative schedule for
environmental monitoring in February 2011 is provided in Appendix
F. Actual monitoring dates may change due to
unforeseen events such as inclement weather.
The construction phase and EM&A
programme for Section 4 commenced on 28 May 2010. EM&A was performed from 1
to 31 January 2011 during which some minor site works have commenced. All
monitoring and audit results in the reporting month were checked and reviewed.
Construction noise monitoring was
carried out in the reporting month. As no noise-related complaint was received
or follow-up by ET during the reporting month, no Action Level exceedance was
recorded. All noise monitoring results obtained complied with the Limit Level.
Environmental site inspections were
carried out five times during the reporting month. During the site audits,
recommendations on remedial actions were given to the Contractor for any
deficiencies identified.
Wastes were handled and disposed
from site in accordance with the EM&A Manual and all relevant legislation
and regulations.
No environmental complaints,
notification of summons of successful prosecutions were received or made
against Section 4 of the Project during the reporting month.
Overall, the EM&A programme for
Section 4 during the reporting month was in compliance with the relevant EIA
Report, EM&A Manual, EP and FEP(s) and all relevant legislation and
regulations.
No further recommendations were made
at this stage pending more site progress achieved.
Appendix A.
Construction Works Programme |
Appendix B.
Project Organisation Chart for Section 4 |
Table C.1: Action
and Limit Levels for Construction Noise
Time Period |
Action Level |
Limit Level |
Daytime (07:00-19:00) except general holidays and Sundays Measurements in Leq (30min) |
When one documented complaint is received |
75 dB(A) |
Table D.1: Event
and Action Plan for Construction Noise
EVENT |
ACTION |
|
|
|
|
ET Leader |
IEC |
ER |
Contractor |
Action Level |
1. Notify IEC and the Contractor. 2. Carry out investigation. 3. Report the results of investigation to IEC and the Contractor. 4. Discuss with the Contractor and formulate remedial measures. 5. Increase monitoring frequency to check mitigation measures. |
1. Review with analyzed results submitted by ET. 2. Review the proposed remedial measures by the Contractor and advise ER accordingly. 3. Supervise the implement of remedial measures. |
1. Confirm receipt of notification of exceedance in writing. 2. Notify the Contractor. 3. Require the Contractor to propose remedial measures for the analyzed noise problem. 4. Ensure remedial measures are properly implemented. |
1. Submit noise mitigation proposals to IEC. 2. Implement noise mitigation proposals. |
Limit Level |
1. Identify the source. 2. Notify IEC, ER, EPD and the Contractor. 3. Repeat measurement to confirm findings. 4. Increase monitoring frequency. 5. Carry out analysis of Contractor’s working procedures to determine possible mitigation to be implemented. 6. Inform IEC, ER, and EPD the causes & actions taken for the exceedances. 7. Assess effectiveness of the Contractor’s remedial actions and keep IEC, EPD and ER informed of the results. 8. If exceedance stops, cease additional monitoring. |
1. Discuss amongst ER, ET Leader and the Contractor on the potential remedial actions. 2. Review the Contractor’s remedial actions whenever necessary to assure their effectiveness and advise ER accordingly. 3. Supervise the implementation of remedial measures. |
1. Confirm receipt of notification of exceedance in writing. 2. Notify the Contractor. 3. Require the Contractor to propose remedial measures for the analyzed noise problem. 4. Ensure remedial measures are properly implemented. 5. If exceedance continues, consider what activity of the work is responsible and instruct the Contractor to stop that activity of work until the exceedance is abated. |
1. Take immediate action to avoid further exceedance. 2. Submit proposals for remedial actions to IEC within 3 working days of notification. 3. Implement the agreed proposals. 4. Resubmit proposals if problem still not under control. 5. Stop the relevant activity of works as determined by the ER until the exceedance is abated. |
Table E.1: Recommended Mitigation
Measures – Air Quality
EIA Ref. |
EM&A Manual Ref. |
Recommended Mitigation Measures |
Who to implement? |
When to implement? (1) |
Implementation Status (2) |
2.5.2 |
3.2.2 |
The
following good site practice should be implemented: ¡ any excavated dusty materials or stockpile
of dusty materials should be covered entirely by impervious sheeting or
sprayed with water so as to maintain the entire surface wet, and recovered or
backfilled or reinstated within 24 hours of the excavation or unloading; ¡ the working area of excavation should be
sprayed with water immediately before, during and immediately after the
operations so as to maintain the entire surface wet; ¡ dusty materials carried by vehicle leaving
a construction site should be covered entirely by clean impervious sheeting; ¡ the area where vehicle washing takes place
and the section of the road between the washing facilities and the exit point
should paved with concrete, bituminous materials or hardcores; ¡ the portion of road leading only to a
construction site that is within 30m of designated vehicle entrance or exit
should be kept clear of dusty materials; ¡ all dusty materials should be sprayed with
water prior to any loading, unloading or transfer; ¡ vehicle speed should be limited to 10kph
except on completed access roads; ¡ every vehicle should be washed to remove
any dusty materials from its body and wheels before leaving the construction
sites. |
Contractor |
DC |
4, REC |
Legend: (1) DC - During Construction
(2) 4 - Implemented
P - Partially Implemented
5 - Not Implemented
REC - Rectified by Contractor
(REC) - Partially Rectified by Contractor
! - Pending Contractor’s Rectification
Action
N/A - Not Applicable
Table E.2: Recommended Mitigation
Measures – Noise
EIA Ref. |
EM&A Manual Ref. |
Recommended Mitigation Measures |
Who to implement? |
When to implement? (1) |
Implementation Status (2) |
3.8.14 |
4.8.1 |
The following good site practical should be
implemented: ¡ The Contractor shall adopt the Code of
Practice on Good Management Practice to Prevent Violation of the Noise
Control Ordinance (Chapter 400) (for Construction Industry) published by EPD; ¡ The Contractor shall observe and comply
with the statutory and non-statutory requirements and guidelines; ¡ Before commencing any work, the Contractor
shall submit to the Engineer Representative for approval the method of
working, equipment and noise mitigation measures intended to be used at the
site; ¡ The Contractor shall devise and execute
working methods to minimise the noise impact on the surrounding sensitive
uses, and provide experienced personnel with suitable training to ensure that
those methods are implemented; ¡ Noisy equipment and noisy activities
should be located as far away from the Noise Sensitive Receivers (NSRs) as is
practical; ¡ Unused equipment should be turned
off. Powered Mechanical Equipment
(PME) should be kept to a minimum and the parallel use of noisy equipment /
machinery should be avoided; ¡ Regular maintenance of all plant and
equipment; ¡ Material stockpiles and other structures
should be effectively utilised as noise barriers, where practicable. |
Contractor |
DC |
4 |
3.8.1 -3.8.3 |
4.8.2 -4.8.3 |
Other than good site practice, the
Contractor is required to adopt Levels 1 and 2 site-specific direct
mitigation measures as specified below during the construction phase. With construction / demolition work undertaken
at a distance of 60m or less to the NSRs, below mitigation measures should be
included: Level 1 – Use of Quiet Plant and Movable Noise Barrier ¡ The Contractor shall obtain particular
models of plant that are quieter than standards given in the Technical
Memorandum on Noise from Construction Work other than Percussive Piling
(GW-TM). ¡ Purpose-built movable noise barriers should be used to mitigate construction noise directly at sources that are not usually mobile provide that the direct line of sight to the source is blocked. |
Contractor |
DC |
P |
3.8.9 |
4.8.4 |
In addition to the use of quiet plant and
movable noise barrier, alternative demolition method of existing boundary
fence at Section 2-3 shall be used where demolition works would be undertaken
at a distance of 12m or less to the NSRs. These particular mitigation
measures should be included: Level 2 – Alternative Demolition Method of Existing Boundary Fence ¡ The use of welder is recommended to
replace the use of hand-held driller; ¡ The use of hand-held breaker with movable
noise barrier is recommended to replace the use of mini-robot mounted
breaker; and the duration for the use of hand-held breaker is minimal as only
the surface level of the footing to be broken; and ¡ The removal of the footing of the existing boundary fence should be carried by concrete crusher mini-robot mounted after the surface level broken by hand-held breaker. |
Contractor |
DC |
P |
Legend: (1) DC - During
Construction
(2) 4 - Implemented
P - Partially Implemented
5 - Not Implemented
REC - Rectified by Contractor
(REC) - Partially Rectified by Contractor
! - Pending Contractor’s Rectification
Action
N/A - Not Applicable
Table E.3: Recommended Mitigation
Measures – Water Quality
EIA Ref. |
EM&A Manual Ref. |
Recommended Mitigation Measures |
Who to implement? |
When to implement? (1) |
Implementation Status (2) |
4.7.1 |
5.3.1 |
Good site practices in
addition to the implementation of mitigation measures would minimize the
impact to the surrounding environment. General Prevention and Precaution Measures: ¡ The site should be confined to avoid silt
runoff to the site. ¡ No discharge of silty water into the storm
drain and drainage channel within and the vicinity of the site. ¡ Any soil contaminated with chemicals/oils
shall be removed from site and the void created shall be filled with suitable
materials. ¡ Stockpiles to be covered by tarpaulin to
avoid spreading of materials during rainstorms; ¡ Suitable containers shall be used to hold
the chemical wastes to avoid leakage or spillage during storage, handling and
transport; ¡ Chemical waste containers shall be
labelled with appropriate warning signs in English and Chinese to avoid
accidents. there shall also be clear
instructions showing what action to take in the event of an accidental; ¡ Storage areas shall be selected at safe
locations on site and adequate space shall be allocated to the storage area; ¡ Any construction plant which causes
pollution to the water system due to leakage of oil or fuel shall be removed
off-site immediately; ¡ Spillage or leakage of chemical waste to
be controlled by using suitable absorbent materials; ¡ Chemicals will always be stored on drip
trays or in bunded areas where the volume is 110% of the stored volume; ¡ Regular clearance of domestic waste
generated in the temporary sanitary facilities to avoid waste water
spillage. ¡ Temporary sanitary facilities to be provided for on-site workers during construction. |
Contractor |
DC |
4, REC |
4.7.2 - 4.7.3 |
5.3.2 - 5.3.3 |
Concreting Work A temporary drainage channel and associated facilities should be provided to collect the runoff generated and prevent concrete-contaminated water from entering watercourses. Adjustment of pH can be achieved by adding a suitable neutralising reagent to wastewater prior to discharge. The concreting works should be temporarily isolated with proper methods, such as by placing of sandbags or silt curtains with lead edge at bottom and properly supported props. |
Contractor |
DC |
N/A |
4.7.4 |
5.3.4 |
Soil Excavation and
Stockpiling Excavated soil which needs to be temporarily stockpiled should be stored in a specially designated area and provided with a tarpaulin cover to avoid runoff into the drainage channels. |
Contractor |
DC |
4 |
4.7.5 - 4.7.6 |
5.3.5 -5.3.6 |
Site Depot All compounds in works areas should be located on areas of hard standing with provision of drainage channels and settlement ponds where necessary to allow interception and controlled release of settled/treated water. Hard standing compounds should drain via an oil interceptor. The oil interceptor should be regularly inspected and cleaned to avoid wash-out of oil during storm conditions. A bypass should be provided to avoid overload of the interceptor's capacity. Any contractor generating waste oil or other chemicals as a result of his activities should register as a chemical waste producer. Disposal of the waste oil should be done by a licensed collector. Good housekeeping practices should be implemented to minimise careless spillage and to keep the storage and the work space in a tidy and clean condition. Appropriate training including safety codes and relevant manuals should be given to the personnel who regularly handle the chemicals on site. |
Contractor |
DC |
P |
4.7.7 |
5.3.7 |
Construction of
Checkpoint Sewage system should be constructed to divert domestic sewage, which will be generated from the sanitary facilities provided in the new checkpoint at Sha Tau Kok, to public sewer connected to government sewage treatment facilities. |
Contractor |
DC |
N/A |
Legend: (1) DC - During Construction
(2) 4 - Implemented
P - Partially Implemented
5 - Not Implemented
REC - Rectified by Contractor
(REC) - Partially Rectified by Contractor
! - Pending Contractor’s Rectification
Action
N/A - Not Applicable
Table E.4: Recommended Mitigation
Measures – Waste Management
EIA Ref. |
EM&A Manual Ref. |
Recommended Mitigation Measures |
Who to implement? |
When to implement? (1) |
Implementation Status (2) |
5.6.7 |
6.3.6 |
Site Clearance The topsoil and vegetation removed and excavated material may have to be temporarily stockpiled on-site. Control measures should be taken at the stockpiling area to prevent the generation of dust and pollution of stormwater channels, fish ponds or river channels. However, to eliminate the risk of blocking drains in the wet season, it is recommended that stockpiling of excavated materials during the wet season should be avoided as far as practicable. |
Contractor |
DC |
4 |
5.6.10 - 5.6.12 |
6.3.8 |
Construction and
Demolition Materials Careful design, planning and good site management can minimize over-ordering and generation of waste materials such as concrete mortars and cement grouts. The design of formwork should maximize the use of standard wooden panels so to achieve high reuse levels. Alternatives such as steel formwork or plastic facing should be considered to increase the potential for reuse. The Contractor should recycle as much of the C&D materials as possible on-site. Proper segregation of waste on-site will increase the feasibility of certain components of the waste stream by the recycling contractors. Different areas of the worksite shall be designated for such segregation and storage wherever site conditions permit. Trip-ticket system should be employed to monitor the disposal of C&D material and solid at public filling facilities and landfills, and to control fly-tipping. Government has established a differentiated charging scheme for the disposal of waste to landfill, construction waste sorting facilities and public fill facilities. This will provide additional incentives to reduce the volume of waste generated and to ensure proper segregation of wastes. |
Contractor |
DC |
4 |
5.6.13 - 5.6.14 |
6.3.9 - 6.3.13 |
Chemical Waste For those processes which generate chemical
waste, it may be possible to find alternatives which generate reduced quantities
or even no chemical waste, or less dangerous types of chemical waste. Chemical waste that is produced, as defined
by Schedule 1 of the Waste Disposal (Chemical Waste) (General) Regulation,
should be handed in accordance with the Code of Practice on the Packaging,
Handling and Storage of Chemical Waste as follows: Containers used for the storage of chemical
wastes should: ¡ be suitable for the substance they are
holding, resistant to corrosion, maintained in a good condition, and securely
closed: ¡ have a capacity of less than 450 litres
unless the specification have been approved by the EPD; and ¡ display a label in English and Chinese in
accordance with instructions prescribed in Schedule 2 of the Regulations, The storage area for chemical wastes should: ¡ be clearly labelled and used solely for
the storage of chemical waste; ¡ be enclosed on at least 3 sides; ¡ have an impermeable floor and bunding, of
capacity to accommodate 110% of the volume of the largest container or 20% by
volume of the chemical waste stored in that area whichever is the greatest; ¡ have adequate ventilation; ¡ be covered to prevent rainfall entering
(water collected within the bund must be tested and disposed as chemical
waste if necessary); and ¡ be arranged so that incompatible materials
are adequately separated. Disposal of chemical waste should: ¡ be via a licensed waste collector; and ¡ be to a facility licensed to receive
chemical waste, such as the Chemical Waste Treatment Facility which also
offers a chemical waste collection service and can supply the necessary
storage containers, or ¡ to be re-user of the waste, under approval from the EPD. |
Contractor |
DCP |
N/A |
5.6.16 |
6.3.15 |
General Refuse Should be stored in enclosed bins or compaction units separate from C&D and chemical wastes. The Contractor should employ a reputable waste collector to remove general refuse from the site, separate from C&D and chemical wastes, on a regular basis to minimise odour, pest and litter impacts. Burning of refuse on construction sites is prohibited by law. |
Contractor |
DC |
4, REC |
5.6.18 |
6.3.16 |
Construction Waste
Management Plan A construction waste management plan (CWMP) should be prepared and developed by the contractor to ensure proper collection, treatment and disposal of waste on site. This CWMP will also take into account the requirement to handle chemical wastes on site which will need to be managed by a licensed waste collection contractor. |
Contractor |
DC |
4 |
Legend: (1) DC - During Construction
DCP -
During Construction Planning
(2) 4 - Implemented
P - Partially Implemented
5 - Not Implemented
REC - Rectified by Contractor
(REC) - Partially Rectified by Contractor
! - Pending Contractor’s Rectification
Action
N/A - Not Applicable
Table E.5: Recommended Mitigation
Measures – Ecology
EIA Ref. |
EM&A Manual Ref. |
Recommended Mitigation Measures |
Who to implement? |
When to implement? (1) |
Implementation Status (2) |
Table 6.38 |
7.2 |
Ecological Impacts on Floral Species of
Conservation Concern ¡ Erection of protective fencing to protect
the plant during construction period |
Contractor |
DC |
4 |
Table 6.40 |
7.2 |
Potential Ecological Impacts on Offsite
Habitats ¡ Good site practices for controlling the
dust and water quality (avoid stockpiles adjacent to wetlands, covering the
stockpiles with impervious sheeting, control of vehicle speed, no discharge
of silty water to the rivers, streams and drainage channels); ¡ Clear definition of works limit to avoid
impact on adjacent habitats. |
Contractor |
DC |
4 |
Table 6.39 - Table 6.45 |
7.2 |
Disturbance to Wetland-Dependent Birds,
Raptors, Terrestrial Birds and Egretry ¡ Good working practices include switching
off unused equipment, keep minimum number of powered mechanical equipment in
operation at the same period, the use of stockpiles and other structures to
form noise barriers where practicable, avoidance of feeding the wildlife to
cause disturbance, site confinement and proper cover of stockpiles with
impervious sheeting to minimize construction noise, uncontrolled surface
runoff and discharge of silts; ¡ Avoidance of construction works using
Power Mechanical Equipments within the Wetland Conservation Area during bird
migratory season (15th November – 15th March); and ¡ Restriction of excavation works within a
150m buffer zone from the egretry to ardeid non-breeding season (from August
to February). |
Contractor |
DC |
4 |
Legend: (1) DC -
During Construction
(2) 4 - Implemented
P - Partially Implemented
5 - Not Implemented
REC - Rectified by Contractor
(REC) - Partially Rectified by Contractor
! - Pending Contractor’s Rectification
Action
N/A - Not Applicable
Table E.6: Recommended Mitigation
Measures – Landscape and Visual
EIA Ref. |
EM&A Manual Ref. |
Recommended Mitigation Measures |
Who to implement? |
When to implement? (1) |
Implementation Status (2) |
|
|
Preservation of Existing
Vegetation |
|
|
|
Table 7-13 CP1 |
Table 9-1 |
¡
To retain trees that have high amenity or ecology
value and contribute most to the landscape and visual amenity of the site and
its immediate environs. |
Project Landscape Architect / Contractor |
TCP |
4 |
Table 7-13 CP1 |
Table 9-1 |
¡
Creation of precautionary area around trees to be
retained equal to half of the trees canopy diameter. Precautionary area to be
fenced. |
Project Landscape Architect / Contractor |
BCP |
4 |
Table 7-13 CP1 |
Table 9-1 |
¡
Prohibition of the storage of materials including
fuel, the movement of construction vehicles, and the refuelling and washing
of equipment including concrete mixers within the precautionary area. |
Project Landscape Architect / Contractor |
TCP |
4, REC |
Table 7-13 CP1 |
Table 9-1 |
¡
Phased segmental root pruning for trees to be
retained and transplanted over a suitable period (determined by species and
size) prior to lifting or site formation works which affect the existing
rootball of trees identified for retention. The extent of the pruning will be
based on the size and the species of the tree in each case. |
Project Landscape Architect / Contractor |
TCP |
4 |
Table 7-13 CP1 |
Table 9-1 |
¡
Pruning of the branches of existing trees identified
for transplantation and retention to be based on the principle of crown
thinning maintaining their form and amenity value. |
Project Landscape Architect / Contractor |
TCP |
4 |
Table 7-13 CP1 |
Table 9-1 |
¡
The watering of existing vegetation particularly
during periods of excavation when the water table beneath the existing
vegetation is lowered. |
Project Landscape Architect / Contractor |
TCP |
N/A |
Table 7-13 CP1 |
Table 9-1 |
¡
The rectification and repair of damaged vegetation following
the construction phase to its original condition prior to the commencement of
the works or replacement using specimens of the same species, size and form
where appropriate to the design intention of the area affected. |
Project Landscape Architect / Contractor |
TCP |
N/A |
Table 7-13 CP1 |
Table 9-1 |
¡
All works affecting the trees identified for
retention and transplantation will be carefully monitored. This includes the key stages in the
preparation of the trees, the implementation of protection measures and
health monitoring through out the construction period. |
Project Landscape Architect / Contractor |
TCP |
4, REC |
Table 7-13 CP1 |
Table 9-1 |
¡
Detailed landscape and tree preservation proposals will
be submitted to the relevant government departments for approval under the
lease conditions and in accordance with ETWB TCW No. 2/2004 and WBTC No.
3/2006. |
Project Landscape Architect / Contractor |
TCP |
P |
Table 7-13 CP1 |
Table 9-1 |
¡
The tree preservation works should be implemented by
approved Landscape Contractors and inspected and approved on site by a
qualified Landscape Architect. A tree protection specification would be
included within the contract documents. |
Contractor |
TCP |
4 |
|
|
Preservation of Existing
Topsoil |
|
|
|
Table 7-13 CP2 |
Table 9-1 |
¡ Topsoil disturbed during the construction
phase should be tested using a standard soil testing methodology and where it
is found to be worthy of retention stored for re-use. |
Contractor |
TCP |
4 |
Table 7-13 CP2 |
Table 9-1 |
¡ The soil will be stockpiled to a maximum
height of 2m and will be either temporarily vegetated with hydroseeded grass
during construction or covered with a waterproof covering to prevent erosion. |
Contractor |
TCP |
4 |
Table 7-13 CP2 |
Table 9-1 |
¡ The stockpile should be turned over on a
regular basis to avoid acidification and the degradation of the organic
material, and reused after completion. Alternatively, if this is not
practicable, it should be considered for use elsewhere, including other
projects. |
Contractor |
TCP |
4 |
|
|
Permanent and Temporary
Works Areas |
|
|
|
Table 7-13 CP3 |
Table 9-1 |
¡ Where appropriate to the final design the
landscape of these works areas should be restored following the completion of
the construction phase. |
Contractor |
TCP |
N/A |
Table 7-13 CP3 |
Table 9-1 |
¡ Construction site controls should be
enforced including the storage of materials, the location and appearance of
site accommodation and the careful design of site lighting to prevent light
spillage. |
Contractor |
TCP |
4 |
|
|
Mitigation Planting |
|
|
|
Table 7-13 CP4 |
Table 9-1 |
¡
Replanting
of disturbed vegetation should be undertaken at the earliest possible stage
of the construction phase. |
Contractor |
TCP |
N/A |
Table 7-13 CP4 |
Table 9-1 |
¡ Use of native plant species predominantly
in the planting design for the buffer areas. |
Contractor |
TCP |
N/A |
Table 7-13 CP4 |
Table 9-1 |
¡ The tree planting works should be
implemented by approved Landscape Contractors and inspected and approved on
site by a qualified Landscape Architect. A tree planting specification would
be included within the contract documents. |
Contractor |
TCP |
N/A |
|
|
Transplantation of Existing Trees |
|
|
|
Table 7-13 CP5 |
Table 9-1 |
¡ The tree transplanting works should be
implemented by approved Landscape Contractors and inspected and approved on
site by a qualified Landscape Architect. A tree protection / transplanting
specification would be included within the contract documents. |
Contractor |
PTCPW |
N/A |
|
|
Design of the Fence and associated Structures |
|
|
|
Table 7-14 OP1 |
Table 9-2 |
Design of Boundary Fence, 1.
Integrated
design approach – the boundary fence should integrated, as far as technically
feasible, with existing built structures such as existing road, footpath and
track and embankment of fishponds,
river and drainage channel as part of design mitigation measures to reduce
the potential cumulative impact of the proposed works. The location and
orientation of the police check points should be away from landscape and
visually sensitive areas such wetland, fishpond and agricultural field. 2.
Building
massing - the proposed use of simple responsive design for the built
structures with a low building height profile to reduce the potential visual
mass of the structure within a rural context. 3.
Treatment
of built structures - the architectural design should seek to reduce the
apparent visual mass of the facilities further through the use of natural materials
such as wooden frame, vertical greening or other sustainable materials such
as recycled plastic. 4.
Responsive
building and fence finishes - In terms of the proposed finishes natural tones
should be considered for the colour palette with non-reflective finishes are
recommended to reduce glare effect. The use of colour blocking on the
proposed fence could be used to break up the visual mass of the structure. 5.
Responsive
lighting design – Aesthetic design of architectural and track lighting with
following glare design measures: -
Directional
and full cut off lighting is recommended particularly for areas adjacent to
existing village to minimise light spillage. -
Minimise
geographical spread of lighting, only applied for safety and security
reasons; -
Limited
lighting intensity to meet the minimum safety and operation requirement; and - High-pressure sodium road lighting is recommended for more stringent light control reducing spillage and thus visual impacts. |
ArchSD |
TDP |
P |
|
|
Compensatory Planting Proposals |
|
|
|
Table 7-14 OP2 |
Table 9-2 |
¡ Utilise native to |
Contractor |
TDP |
P |
Table 7-14 OP2/3 |
Table 9-2 |
¡ A qualified or registered landscape
architect will be involved in the design, construction supervision and
monitoring, and maintenance period to oversee the implementation of the
recommended landscape and visual mitigation measures including the tree
preservation and landscape works on site. |
Contractor |
TDP |
4 |
Table 7-14 OP2 |
Table 9-2 |
Tree
and Shrub Planting – Given the rural nature of the proposed alignment it is
recommended that the where possible tree and shrub species which are native
to |
Contractor |
TDP |
P |
Table 7-14 OP2 |
Table 9-2 |
Compensatory
Planting Proposals – Given the works extent is largely limited along existing
roadside embankment to minimise impact to existing village settlements and valuable
landscape resources such as wetland, fishpond, stream course and existing
trees, and considered the importance of tree retention within the works area,
new tree planting will concentrate in selected new amenity areas along the
alignment, infilling between retained and transplanted trees. The preliminary
planting proposals for the proposed works include the planting of some 357
new trees utilising a combination of mature to light standard sized stock
(i.e. approximately 15% of mature trees, 75% of standard trees, and 10% light
standard trees). These trees will be planted in woodland clumps and small
tree groups at strategic locations to de-emphasise the horizontality of the
fence alignment. Based on preliminary findings the proposed planting will result
in a compensatory planting ratio of 1:1 (new planting: trees recommended for
felling). This compares favourably with the report's assertion that some 357
trees would be felled due to the proposed works. With the proposed
preservation of existing trees, transplantation of trees in conflict with the
proposals and the planting of new trees the project area will contain
approximately 2000 trees. Trees forming part of the new planting will provide
screening to neighbourhood villagers and will utilise species native to |
Contractor |
TDP |
P |
Legend: (1) TCP -
Throughout Construction Phase
BCP - Before Construction Phase Commences
PTCPW - Prior to the Commencement of the Proposed
Works
TDP - Throughout Design Phase
(2) 4 - Implemented
P - Partially Implemented
5 - Not Implemented
REC - Rectified by Contractor
(REC) - Partially Rectified by Contractor
! - Pending Contractor’s
Rectification Action
N/A - Not Applicable
Appendix F.
EM&A Schedule |
Appendix G.
Calibration Certificates |
Table I.1: Monthly
Summary Waste Flow Table for 2010
|
Actual Quantities of Inert C&D
Materials Generated Monthly (in ‘000 m3) |
Actual Quantities of C&D Wastes
Generated Monthly |
||||||||||||||||||
Month |
Total Quantity Generated |
Broken Concrete |
Reused in the Contract |
Reused in other Projects |
Disposed of at Public Fill |
Metals (‘000 kg) |
Paper/ Cardboard (‘000 kg) |
Plastics (‘000 kg) |
Chemical waste (‘000 kg) |
Others
(e.g. refuse) (‘000 m3) |
||||||||||
|
Est. |
Act. |
Est. |
Act. |
Est. |
Act. |
Est. |
Act. |
Est. |
Act. |
Est. |
Act. |
Est. |
Act. |
Est. |
Act. |
Est. |
Act. |
Est. |
Act. |
Jan |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
Feb |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
Mar |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
Apr |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
May |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0.0195 |
Jun |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
Sub-total |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0.0195 |
Jul |
- |
0.0195 |
- |
0 |
- |
0 |
- |
0 |
- |
0.0195 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0.013 |
Aug |
- |
0.1625 |
- |
0 |
- |
0 |
- |
0 |
- |
0.1625 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0.013 |
Sep |
- |
0.2405 |
- |
0 |
- |
0 |
- |
0 |
- |
0.2405 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
Oct |
- |
0.0780 |
- |
0 |
- |
0 |
- |
0 |
- |
0.0780 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0.0007 |
Nov |
- |
0.1755 |
- |
0 |
- |
0 |
- |
0 |
- |
0.1755 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
Dec |
- |
0.2925 |
- |
0 |
- |
0 |
- |
0 |
- |
0.2925 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0.0065 |
Total |
- |
0.9685 |
- |
0 |
- |
0 |
- |
0 |
- |
0.9685 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0.0527 |
Table I.2: Monthly
Summary Waste Flow Table for 2011
|
Actual Quantities of Inert C&D
Materials Generated Monthly (in ‘000 m3) |
Actual Quantities of C&D Wastes
Generated Monthly |
||||||||||||||||||
Month |
Total Quantity Generated |
Broken Concrete |
Reused in the Contract |
Reused in other Projects |
Disposed of at Public Fill |
Metals (‘000 kg) |
Paper/ Cardboard (‘000 kg) |
Plastics (‘000 kg) |
Chemical waste (‘000 kg) |
Others
(e.g. refuse) (‘000 m3) |
||||||||||
|
Est. |
Act. |
Est. |
Act. |
Est. |
Act. |
Est. |
Act. |
Est. |
Act. |
Est. |
Act. |
Est. |
Act. |
Est. |
Act. |
Est. |
Act. |
Est. |
Act. |
Jan |
- |
0.1365 |
- |
0 |
- |
0 |
- |
0 |
- |
0.1365 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
Feb |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Mar |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Apr |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
May |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Jun |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Sub-total |
- |
0.1365 |
- |
0 |
- |
0 |
- |
0 |
- |
0.1365 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
Jul |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Aug |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Sep |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Oct |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Nov |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Dec |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Total |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Table J.1: Complaint Log for the Reporting Month (January 2011)
Log Ref. |
Location |
Complainant / Date of Contact |
Details of Complaint |
Investigation / Mitigation Action |
File Closed |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
Note: No environmental complaint was received
in January 2011.
Appendix K.
Weather Information from Hong Kong
Observatory |
This
Appendix presents wind data obtained from the nearest Hong Kong Observatory
monitoring station, at Ta Kwu Ling, during noise impact monitoring days.