Contract No: HK/2015/01 Wanchai
Development Phase II and Central Wanchai Bypass Sampling,
Field Measurement and Testing Work (Stage 3) Environmental Permit no. EP-364/2009/G, Further Evironmental permit
nos. fep-01/364/2009, FEP-05/364/2009/A, FEp-06/364/2009/a,
FEp-07/364/2009/G, FEP-09/364/2009/B, fep-10/364/2009/B and fep-11/364/2009/E,
FEP-12/364/2009/D Quarterly Environmental Monitoring
and Audit Report
- September to November
2019 –
|
CLIENTS: |
|
Civil
Engineering and Development Department and Highways
Department |
Lam Geotechnics
Limited 11/F Centre
Point Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
CHECKED by: |
|
Raymond Dai Environmental Team Leader |
|
DATE: |
|
February 2020 |
2.2 Scope of the Project and Site
Description
2.3 Division of the Project Responsibility
2.4 Project Organization and Contact
Personnel
2.5 Principal Work and Activities
4.2. Real Time Noise Monitoring Results
4.3. Air quality
monitoring Results
5.3. Real Time Noise Monitoring
5.5. Review of the Reasons for and the
Implications of Non-compliance.
5.6. Summary of action taken in the event of
and follow-up on non-compliance.
6. Complaints, Notification
of Summons and Prosecution
7. Cumulative Construction
Impact due to the Concurrent Projects
lIST
OF TABLES
Table I Principal Work
Activities for Contract no. HY/2009/18
Table II Principal
Work Activities for Contract no. HK/2009/01
Table III Principal Work Activities for
Contract no. HK/2009/02
Table IV Principal Work Activities for
Contract no. HY/2009/15
Table V Principal
Work Activities for Contract no. HY/2009/19
Table VI Principal Work Activities for Contract
no. HK/2012/08
Table VII Principal Work Activities for Contract
no. HY/2010/08
Table VIII Principal Work Activities for Contract no.
HY/2011/08
Table 2.1 Schedule
2 Designated Projects under this Project
Table 2.2 Details
of Individual Contracts under the Project
Table 2.3 Contact
Details of Key Personnel
Table 2.4 Principal Work Activities for
Contract no. HY/2009/18
Table 2.5 Principal Work Activities for
Contract no. HK/2009/01
Table 2.6 Principal
Work Activities for Contract no. HK/2009/02
Table 2.7 Principal
Work Activities for Contract no. HY/2009/15
Table 2.8 Principal
Work Activities for Contract no. HY/2009/19
Table 2.9 Principal
Work Activities for Contract no. HK/2012/08
Table 2.10 Principal Work
Activities for Contract no. HY/2010/08
Table 2.11 Principal Work
Activities for Contract no. HY/2011/08
Table 3.1 Noise
Monitoring Stations
Table 3.2 Real
Time Noise Monitoring Stations
Table 3.3 Air
quality monitoring Stations
Table 4.1 Noise Monitoring Station
for Contract no. HY/2009/18
Table 4.2 Noise Monitoring
Stations for Contract nos. HK/2009/01 and HK/2009/02
Table 4.3 Noise Monitoring Station
for Contract nos. HY/2009/15
Table 4.4 Noise
Monitoring Stations for Contract no. HY/2009/19
Table 4.5 Noise Monitoring Stations for Contract
no. HY/2010/08
Table 4.6 Noise Monitoring Stations for Contract no.
HY/2011/08
Table 4.7 Real
Time Noise Monitoring Stations for Contract no. HY/2009/19
Table 4.8 Real Time
Noise Monitoring Stations for Contract
no. HY/2011/08
Table 4.9 Air
quality monitoring Stations for Contract no. HY/2009/18
Table 4.10 Air
quality monitoring Stations for Contract no. HK/2009/01
Table 4.11 Air
quality monitoring Station for Contract no. HK/2009/02
Table 4.12 Air
quality monitoring Station for Contract no. HY/2009/15
Table 4.13 Air
quality monitoring Stations for Contract no. HY/2009/19
Table 4.14 Air
quality monitoring Stations for Contract no. HK/2012/08
Table 4.15 Air
quality monitoring Stations for Contract no. HY/2010/08
Table 4.16 Air quality monitoring Stations for
Contract no. HY/2011/08
Table 4.17 Details
of Waste Disposal for Contract no. HK/2009/01
Table 4.18 Details
of Waste Disposal for Contract no. HK/2009/02
Table 4.19 Details
of Waste Disposal for Contract no. HY/2009/18
Table 4.20 Details
of Waste Disposal for Contract no. HY/2009/15
Table 4.21 Details
of Waste Disposal for Contract no. HY/2009/19
Table 4.22 Details
of Waste Disposal for Contract no. HK/2012/08
Table 4.23 Details of Waste Disposal for Contract no.
HY/2010/08
Table 4.24 Details of
Waste Disposal for Contract no. HY/2011/08
Table 6.1 Cumulative
Statistics on Complaints
Table 6.2 Cumulative
Statistics on Successful Prosecutions
lIST OF FIGUREs
Figure
2.1 Project Layout
Figure
2.2 Project Organization Chart
Figure
3.1 Locations of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix 2.1 Environmental Mitigation
Implementation Schedule
Appendix 3.1 Action and Limit Level
Appendix 4.1 Noise Monitoring Results and
Graphical Presentations
Appendix
4.2 Real-time Noise Monitoring Results and
Graphical Presentations
Appendix 4.3 Air Quality Monitoring Results
and Graphical Presentations
Appendix 5.1 Event Action Plans
Appendix 6.1 Complaint Log
Appendix 6.2 Notification of Exceedance
Appendix 7.1 Construction Programme of
Individual Contracts
EXECUTIVE
SUMMARY
Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
Major construction activities
for Contract no. HK/2009/02 have been commenced on 26
Table III Principal Work
Activities for Contract no. HK/2009/02
September 2019 |
October 2019 |
November 2019 |
Construction of EVA Erect chain link fence Backfilling work Hung Hing Road
and Wan Shing Street road modification works |
Construction of EVA Clean drainage Erect chain link fence Backfilling work Hung Hing Road and Wan Shing Street
road modification works |
Clean drainage Erect chain link fence Backfilling work Hung Hing Road and Wan Shing Street
road modification works |
Contract no. HY/2009/19 - Central -
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under
FEP-07/364/2009/G
Major construction activities
for Contract no. HY/2009/19 have been commenced on March 2011. During this
reporting period, the principal work activities are summarized as below:
Table V Principal Work Activities for Contract no.
HY/2009/19
September 2019 |
October 2019 |
November 2019 |
Bridge noise enclosure installation
works. Hing Fat Street road and drainage
works. Soft Landscaping
works. Open area hard paving works. D9 to D12 and P22 to P25 drainage
works. Open area Fire Main laying work. D12 masking wall |
Bridge noise enclosure installation
works. Hing Fat Street road works. Soft Landscaping works. Open area hard paving works. D9 to D12 and P22 to P25 drainage
works. P17-P18 drainage downpipe installation
works. D12 masking wall |
Bridge noise enclosure installation
works. Hing Fat Street road works. Soft Landscaping works. Open area hard paving works. D9 to D12 and P22 to P25 drainage
works. P17-P18 drainage downpipe installation
works. D12 masking wall |
Contract
no. HK/2012/08 – Wan Chai Development Phase II – Central- Wan Chai Bypass at
Wan Chai West under FEP-09/364/2009/B and FEP-12/364/2009/D
Table VI Principal Work
Activities for Contract no. HK/2012/08
September 2019 |
October 2019 |
November 2019 |
Remediation works Landscaping |
Remediation works Landscaping |
Nil |
Contract
no. HY/2010/08 – Central and WanChai Bypass – Slip road 8 section under
FEP-10/364/2009B
Table VII Principal Work
Activities for Contract no. HY/2010/08
September 2019 |
October 2019 |
November 2019 |
Drainage improvement works Utility diversion works Junction modification |
Drainage improvement works Utility diversion works Junction modification |
Drainage improvement works Utility diversion works Junction modification |
Contract
no. HY/2011/08 –Central - Wan Chai Bypass (CWB) –Tunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning under
FEP-11/364/2009/E
Table VIII Principal Work
Activities for Contract no. HY/2011/08
September 2019 |
October 2019 |
November 2019 |
ABWF works at Ventilation Buildings,
inclusive of Administration Building, Central Ventilation Building, East
Ventilation Shaft/Building, West Ventilation Building Scaffold erection at MVB Installation of external louvre at MVB Installation of glass canopy at ADB Installation of treated-waste wood at
ADB Drainage Works at Pump Sump C at Wan
Chai Floor painting works at MVB Traffic sign installation and
modification of directional sign at various locations Road resurfacing and road marking
works Painting works at Man Kwong Street |
ABWF works at Ventilation Buildings,
inclusive of Administration Building, Central Ventilation Building, East
Ventilation Shaft/Building, West Ventilation Building Scaffold erection at MVB Installation of external louvre at MVB Installation of glass canopy at ADB Installation of treated-waste wood at
ADB Floor painting works at MVB Traffic sign installation and
modification of directional sign at various locations Painting works
at Man Kwong Street Planting works
at Man Po Street and Kong Chung Lane |
ABWF works at Ventilation Buildings,
inclusive of Administration Building, Central Ventilation Building, East
Ventilation Shaft/Building, West Ventilation Building Scaffold erection at MVB Installation of external louvre at MVB Installation of glass canopy at ADB Installation of treated-waste wood at
ADB Floor painting works at MVB Traffic sign installation and
modification of directional sign at various locations Painting works at Man Kwong Street Planting works at Man Po Street and
Kong Chung Lane |
Noise Monitoring
Real time Noise Monitoring
viii.
24-hour real time
noise monitoring was conducted at RTN1 - FEHD Hong Kong Transport Section
Whitefield Depot for the pilling works in FEHD Whitfield Depot and RTN2 – Tunnel
(North Point Section) and Island Eastern Corridor Link during the period from
28 September 2012 til 10am on 5 October 2012 in the reporting period.
ix.
Real time noise monitoring station at Oil Street Community Liaison
Centre (RTN2- Oil Street Community Centre) was relocated from Oil Street
Community Liaison Centre to Hong Kong Electric (RTN2a- Electric Centre) on 5
Oct which is a representative of the noise sensitive receiver City Garden. The
baseline noise level of RTN2a will adopt the results derived from the baseline
noise monitoring conducted in Electric Centre from 4 December 2009 to 17
December 2009.
x.
As confirmed by CWB RSS, the IECL parapet removal operations will
commence in March 2013. Liaison was
conducted with HK Baptist Church Henrietta Secondary School and Po Leung Kuk Yu
Lee Mo Fan Memorial School regarding the set up of RTN3 real time noise
monitoring station. Po Leung Kuk Yu Lee
Mo Fan Memorial School grant permission for set up on 4 Sep 2012 and station
set up was performed on 14 Sep 2012.
xi.
Real Time Noise Monitoring at RTN3- Po Leung Kuk Yu Lee Mo Fan Memorial
School was commenced since 06 Oct 2012.
xii.
Causeway Bay Community Centre has granted permission for set up of real
time noise monitoring station on 21 Dec 2012 and station set up was performed
on 27 Dec 2012. The Baseline noise level
of RTN4- Causeway Bay Community Centre will adopt the results from the baseline
noise monitoring report for EP/364/2009 in 22
xiii.
According to clause 3.1 stated in EP-364/2009B, “the real-time
monitoring system shall be in place no later than two weeks before the
commencement date of demolition works of the existing Island Eastern Corridor”.
IEC demolition associated construction works was commenced on 3 Feb 2013 and
Real time noise monitoring at RTN4-Causeway Bay Community Centre was commenced
on 13 Jan 2013.
xiv.
Real-time noise monitoring station RTN1-FEHD Whitfield Depot was finely
adjusted from 2/F to roof-top at FEHD Whitfield Depot on 24 June 2013 with
respect to the commencement of advance works for IEC parapet demolition.
xv.
With respect to the non-CWB Project building construction at Oil Street,
the real-time noise monitoring station RTN2a- Hong Kong Electric Centre was
finely adjusted from Northeast Side to Northwestern side at Roof Top location.
xvi.
24-hour real time noise monitoring was conducted at RTN1- FEHD Hong Kong
Transport Section Whitfield Depot.
-
No limit level exceedance was recorded in the September 2019 reporting
period.
-
No limit level exceedance was recorded in the October 2019 reporting
period.
-
No limit level exceedance was recorded in the November 2019 reporting
period.
-
No limit level exceedance was recorded in the September 2019 reporting
period.
-
Limit level exceedance was recorded on 5 October 2019 in the October 2019
reporting period. After the investigation, the exceedance was concluded as
non-project related.
-
No limit level exceedance was recorded in the November 2019 reporting
period.
-
Limit level exceedance was recorded on 6 and 23 September 2019 in the September
2019 reporting period. After the investigation, the exceedances were concluded
as non-project related.
-
Limit level exceedance was recorded on 8, 14 and 23 October 2019 in the October
2019 reporting period. After the investigation, the exceedances were concluded
as non-project related.
-
No limit level exceedance was recorded in the November 2019 reporting
period.
-
No limit level exceedance was recorded in the September 2019 reporting
period.
-
No limit level exceedance was recorded in the October 2019 reporting
period.
-
No limit level exceedance was recorded in the November 2019 reporting
period.
Air Quality
Monitoring
Complaints,
Notifications of Summons and Successful Prosecutions
EPD referred a complaint to ET on 25
September 2019 (CASE Ref: H05/RS/00026537-19). It was alleged in the complaint
that construction works under Contract No. HK/2009/02 was carried out at around
21:00 hours on 11 September 2019 at Wan Shing Street, Wan Chai with 1 generator
and 1 concrete saw in operation. The works was suspected to contravene the
Noise Control Ordinance, Cap. 400.
ET confirmed with the Resident Site
Staff that 1) CEDD and RSS conducted the weekly ad-hoc site inspection on 11 September
2019 night time period; 2) CEDD and RSS observed that one portable generator
and one electrical hand held grinder were operated at about 20:45 hours; 3) Construction
Noise Permit GW-RS0734-19 could not cover the above mentioned PME operation
from 1900 to 2300 on 11 September 2019 at Wan Shing Street area; 4) RSS has
immediately discussed with the Contractor’s representative of Contract No.
HK/2009/02 about the incident and the works was stopped; 5) CEDD advised RSS to
investigate the cause of accident and provide action to prevent recurrence by
18 September 2019.
In view of the information gathered, the
possible causes are as follow: 1) Contractor did not deploy enough supervision
staff on-site to check the CNP compliance of construction works during
restricted hours; 2) The workers did not follow the instruction of Contractor’s
engineer.
The complaint was considered as Project
related and Contractor of HK/2009/02 was required and urged to implement
remedial measures and preventative measures to ensure the strict compliance
with construction noise permit. The Corrective Action including the Contractor’s
engineer immediately stopped the worker to use PME implemented immediately and
Preventative Action recommended are as follow: 1) The Contractor of HK/2009/02
was recommended to fully review the “Supervision and Control Plan for Works in
Restricted Hours”; 2) The Contractor of HK/2009/02 was recommended to provide comprehensive
training to frontline supervisors and workers on the requirement and condition
of CNP for the works, including no unplanned PME operation should be allowed in
restricted hours; 3) The Contractor of HK/2009/02 was recommended that all PME
(Hand tools) not allowed to be used in the CNP should be removed from site during
restricted hours; 4) The Contractor of HK/2009/02 was recommended that the
ignition device for the PME on site should be kept by the assigned responsible
person and any workers intended to use of PME should obtain the permission from
the assigned responsible person beforehand; 5) The Contractor of HK/2009/02 was
also recommended to assign a delegated personnel to conduct checking on the
deployment of PME onsite during restricted hours to ensure only PME allowed
under relevant Construction Noise Permit are operated.
An ICC complaint was referred to the ET
on 31 October 2019 (CASE Ref: CASE#2-5906833748). The complainant reported
that:
Road improvement works on the westbound
carriageway of the Island Eastern Corridor are being carried out around 2 a.m.
without any noise mitigation measures, causing serious disturbance to residents
of Provident Centre.
ET confirmed with the Resident Site
Staff that:
The ICC complaint was recorded on 26
October 2019 at around 02:15. Emergency Construction Work (HyD Emergency Serial
Number: EO1194) was notified to EPD on 25 October 2019 18:15. The Emergency
Construction Work including replacement of movement joint and installation of
defective noise panel at noise enclosure was conducted at Island Eastern
Corridor West Bound at Pier 46 from 26 October 2019 01:00 to 05:30.
During the concerned period, the PME
operated and noise mitigation measure implemented were as follow:
For replacement of movement joint:
- Total 2 no. of electric hand-held
breakers, 2 no. of hand-held drills and 1 no. of welding set were operated;
- Noise mitigation measure including
acoustic enclosure comprised of acoustics mat and plywood was provided to
electric hand-held breakers.
For Installation of defective noise
panel at noise enclosure:
- Total 1 no. of truck mounted aerial
platform and 1 no. of hand-held drill were operated.
In view of the information gathered, the
complaint was considered as related to noise nuisance from emergency
construction work.
The Contractor of HY/2009/19 is
recommended to adopt additional noise mitigation measure for future emergency
construction work as below:
1.
The Contractor of HY/2009/19 is recommended
to make sure the noise enclosure deployed for breaking works or any other noisy
activities shall be fenced between the direct line of sight between the noise
emanating source and the NSR in order to minimize the noise impact. Standby
noise mitigation measures such as noise barrier or noise enclosure is
recommended to stored on-site for emergency deployment;
2.
The Contractor of HY/2009/19 is recommended
to make use QPME(s), wherever possible, for emergency works to reduce the noise
emission from site;
3.
The Contractor of HY/2009/19 is recommended
to avoid multiple PMEs operated concurrently or reduce the amount of PMEs
operated concurrently, wherever possible, to avoid cumulative noise impact;
4.
The Contractor of HY/2009/19 is recommended
to complete the noisy work as soon as possible to minimize disturbance to
nearby residents;
5.
The Contractor of HY/2009/19 is recommended
to notify nearby noise sensitive receivers in advance, wherever possible for
future emergency construction works
1.1.1. Lam Geotechnics Limited (LGL) has been appointed to work as
the Environmental Team (ET) under Environmental Permit no. EP-364/2009/G and
Further Environmental permit nos. FEP-01/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A, FEP-07/364/2009/G, FEP-09/364/2009/B,
FEP-10/364/2009/B, FEP-11/364/2009/E and FEP-12/364/2009/D to implement the
Environmental Monitoring and Audit (EM&A) programme as stipulated in the
EM&A Manual of the approved Environmental Impact Assessment (EIA) Report
for Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.:
AEIAR-125/2008) and in the EM&A Manual of the approved EIA Report for
Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No. AEIAR-041/2001).
1.1.2. This report presents the environmental monitoring and
auditing work carried out in accordance to the Section 10.3 of EM&A Manual and “Environmental
Monitoring and Audit Requirements” under Particular Specification Section 27.
1.1.3.
This report documents
the finding of EM&A works during the period from 27 August 2019 to 26 November 2019.
Section 1 Introduction – details the scope and structure of the
report.
Section 2 Project Background – summarizes background and scope of the
project, site description, project organization and contact details of key
personnel during the reporting period.
Section 3 Monitoring Requirements – summarizes all monitoring parameters,
monitoring locations, monitoring frequency, duration and action plan.
Section 4 Monitoring Results – summarizes the monitoring results
obtained in the reporting period.
Section 5 Compliance Audit – summarizes the auditing of monitoring results, all
exceedances environmental parameters.
Section 6 Complaints,
Notification of summons and Prosecution – summarizes the cumulative
statistics on complaints, notification of summons and prosecution
Section 7 Cumulative
Construction Impact due to the Concurrent Projects – summarizes the
relevant cumulative construction impact due to the concurrent activities of the
concurrent Projects.
Section 8 Conclusion
2.1.1. “Wan Chai Development phase II and Central-Wan Chai Bypass”
and “Central-Wan Chai Bypass and Island Eastern Corridor Link” (hereafter
called “the Project”) are Designed Project (DP) under the Environmental Impact
Assessment Ordinance (Cap. 499) (EIAO).
The Environmental Impact Assessment (EIA) Reports for Central-Wan Chai
Bypass and
2.1.2. The key purpose of Wan Chai Development Phase II (WDII) is
to provide land at Wan Chai North and North Point for construction of the
Central-Wan Chai Bypass and Island Eastern Corridor Link (CWB). Land formed
under the project will be developed as a world-class waterfront promenade
joining that at the new Central waterfront for public enjoyment.
2.1.3. There is a compelling and present need for the CWB to
provide relief to the very congested
2.2.1. Design and Construction of
Central – Wan Chai Bypass and Island Eastern Corridor Link under the Project
involves the construction and operation of a trunk road and its road tunnel
more than 800m in length between portals that is shown at Figure 2.1.
2.2.2.
The study area
encompasses existing developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB) and Island Eastern Corridor Link (IECL)
includes:
·
A dual three-lane trunk road, approximately 4.5 km
in length, and tunnel approximately 3.7 km in length defined from the
connection with the existing Rumsey Street Flyover in Central, through to a
connection with the existing Island Eastern Corridor to the east of the
Causeway Bay Typhoon Shelter (CBTS);
·
The Central Interchange near the Rumsey Street
Flyover to provide road connections to the Central area;
·
Tunnel control buildings and ventilation buildings;
·
Slip roads to connect the CWB to the local road
system in the Wan Chai North and
·
Associated road lighting, road signing, traffic
control and surveillance system; and
·
Other associated works.
2.2.3. The project also contains various Schedule 2 DPs that,
under the EIAO, require Environmental Permits (EPs) to be granted by the DEP
before they may be either constructed or operated. Table 2.1 summarises the
five individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.
Table 2.1 Schedule 2 Designated Projects under this Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1. Due to the multi-contract nature of the Project, there are
a number of contracts sub-dividing the whole works area into different work
areas to be commenced. Contractors of
individual contracts will be required by the EP holder to apply Further
Environmental Permits such that the impact
monitoring stations are sub-divided accordingly to facilitate the
implementation of EM&A programme and to streamline the EM&A reporting
for individual FEP holders correspondingly.
2.3.2.
In the reporting
period, the following construction Contracts were on-going and Contract HY/2009/01,
HY/2009/17, 04/HY/2006, HY/2009/15, HY/2009/18 and HK/2010/06 had been
completed. The details of individual contracts are
summarized in Table2.2.
Table 2.2 Details
of Individual Contracts under the Project
Contract No. |
Contract Title |
Associated DP(s) |
Construction Commencement Date |
HY/2009/17 |
Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced
piling works. |
DP1 |
5 October 2010 (Completed) |
HY/2009/18 |
Central – Wan Chai Bypass (CWB) – Central Interchange |
DP1 |
21 (Completed) |
04/HY/2006 |
Reconstruction of Bus Terminus near |
DP1 |
September 2010 (Completed) |
HK/2009/01 |
Wan Chai Development Phase II – Central – Wan Chai Bypass at |
DP1, DP2 |
25 August 2011 (Completed) |
HK/2009/02 |
Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai
East (CWB Tunnel) |
DP1 |
26 |
HY/2009/15 |
Central-Wanchai Bypass – Tunnel ( |
DP1 |
13 July 2011 (Completed) |
HY/2009/19 |
Central – Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link |
DP1 |
24 March 2011 |
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen
Wan Line |
DP3 |
22 March 2011 (Completed) |
HK/2012/08 |
Wan Chai Development Phase II- Central-Wan Chai
Bypass at Wan Chai West |
DP1,DP2, DP3 |
10 March 2014 |
HY/2010/08 |
Central- Wanchai Bypass Tunnel – Tunnel (Slip
Road 8) |
DP1, DP2, DP3 |
21 March 2013 |
HY/2011/08 |
Central - Wan Chai Bypass (CWB) –Tunnel
Buildings, Systems and Fittings, and Works Associated with Tunnel
Commissioning |
DP1 |
8 October 2014 |
2.3.3.
The construction works of Contract no. 04/HY/2006 – Reconstruction of
Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A
was completed, and the FEP was surrendered by the Contractor on 11 February
2011.
2.3.4.
Construction
of bored pile E3B under HY/2009/17 was confirmed completed and the respective
work area under FEP-03/364/2009 was handover and inspected under HY/2009/19
from 19 Dec 2012 onwards. Subsequently, the FEP-03/364/2009 was surrendered by
the Contractor on 28 March 2013.
2.3.5.
Construction
works under HK/2010/06 was confirmed completed and the respective work area
under FEP-08/364/2009/A was handover and inspected under HK/2012/08 from 22 Sep
2014 onwards. Subsequently, the FEP-08/364/2009/A was surrendered by the
Contractor on 3 October 2014.
2.3.6.
The
Construction works under HY/2009/15 was confirm completed by the RSS from 27 October
2017 onwards. The weekly site audit inspection and the associated monitoring station
for HY/2009/15 were temporary suspended from 27 October 2017 onwards.
2.3.7.
The
Construction works under HY/2009/18 was confirm completed by the RSS from 25
April 2018 onwards. The weekly site audit inspection and the associated
monitoring station for HY/2009/18 were temporary suspended from 27 April 2018
onwards.
2.3.8.
As
confirmed with WDII RSS and with respect to the joint inspection conducted with
IEC on 25 May 2018, RSS, ET and IEC share the view that there is no adverse
environmental impact of remaining works under Contract HK/2009/01 and the
respective environmental site inspection and associated monitoring station were
temporary suspended from 26 May 2018 onwards. FEP-02/364/2009 was surrendered
by the Contractor on 3 September 2018.
2.4.1. Civil Engineering and
Development Department and Highways Department are the overall project
controllers for the Wan Chai Development Phase II and Central-Wan Chai Bypass
respectively. For the construction phase of the Project, Project
Engineer, Contractor(s), Environmental Team and Independent Environmental
Checker are appointed to manage and control environmental issues.
2.4.2. The proposed project organization and lines of
communication with respect to environmental protection works are shown in Figure 2.2. Key personnel and
contact particulars are summarized in Table 2.3.
Table 2.3 Contact
Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer’s Representative for WDII |
Chief Resident Engineer |
Ms. Gloria Tang |
2587 1778 |
2587 1877 |
Engineer’s Representative for CWB |
Chief Resident Engineer |
Mr. Dennis Norton |
3912 3188 |
3912
3010 |
|
Chief Resident Engineer |
Mr. S. K. Lo |
3912 3288 |
3912
3010 |
||
Chief Resident Engineer |
Mr. David Kwan |
3650 1888 |
3912
3010 |
||
Chun Wo – CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Site Agent |
Mr. Paul Yu |
3658-3002 |
2827 9996 |
Environmental Officer |
Mr. C.P. Ho |
9191 8856 |
|||
Chun Wo - CRGL - MBEC Joint Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. David Lau |
3758 8879 |
2570 8013 |
Site Agent |
Mr. William Luk |
9456 9819 |
|||
Deputy Site Agent |
Mr. Andrew Cheng |
3758 8879 |
|||
Environmental Manager / Environmental Officer |
Mr. M.H. Isa |
3757 8218 |
|||
Assistant Environmental Officer |
Mr. James Chan |
3757 8217 |
|||
Construction Manager (Marine) |
Mr. Wingo Wong |
9300 2625 |
|||
Construction Manager (Noise Barrier) |
Mr. Jerry Siu |
9493 3664 |
|||
Construction Manager (Land) |
Mr. Yung Kwok Wah |
9834 1010 |
|||
Leighton Contractors (Asia) Limited |
Contractor under Contract no. HY/2009/18 |
Site Agent |
Mr. Jimmy Chu |
3973
0803 |
2140 6799 |
Environmental
Officer |
Mr. Y.K Wu |
3973 1977 |
|||
China State Construction Engineering (HK) Ltd. |
Contractor under Contract no. HY/2009/15 |
Project
Director |
Mr. Chris Leung |
3577
6393 |
2566 2192 |
Site
Agent |
Mr. Patrick Ho |
3557
6405 |
|||
Environmental Officer |
Mr. Gabriel
Wong |
3557 6347 |
|||
China State- Leader JV |
Contractor under Contract no. HK/2012/08 |
Project
Director |
Mr. C.N.
Lai |
9137
1811 |
2877
1522 |
Site
Agent |
Mr. George
Cheung |
9268
1918 |
|||
Environmental
Officer |
Mr. James
MA |
9130
9549 |
|||
Environmental
Supervisor |
Mr. Y. L. Ho |
9856
5669 |
|||
China State |
Contractor under Contract no. HY/2010/08 |
Project
Director |
Mr.
Chris Leung |
9210
7116 |
3465 2899 |
Project
Manager |
Mr.
Chan Ying Lun |
3418
3001 |
|||
Site
Agent |
Mr. Thomas
Lui |
3557
6407 |
|||
Environmental
Officer |
Mr. Gabriel
Wong |
3557
6466 |
|||
Leighton Joint Venture |
Contractor under Contract no. HY/2011/08 |
Site Agent |
Mr. Colman Wong |
2823 1410 |
2140 6799 |
Environmental
Officer |
Mr. Y.K. Wu |
3973 1977 |
|||
Lam Geotechnics Limited |
Environmental
Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
RAMBOLL Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3465
2888 |
3465 2899 |
2.5.1.
Major construction activities for Contract no. HK/2009/02 have been
commenced on 26
Table 2.6 Principal Work Activities for Contract no. HK/2009/02
September
2019 |
October
2019 |
November
2019 |
Construction of EVA
Erect chain link fence
Backfilling work
Hung Hing Road and Wan Shing Street road
modification works |
Construction of EVA
Clean drainage
Erect chain link fence
Backfilling work
Hung Hing Road and Wan Shing Street road modification works |
Clean drainage
Erect chain link fence
Backfilling work
Hung Hing Road and Wan Shing Street road modification works |
2.5.2.
Major construction activities for Contract no. HY/2009/19 have been
commenced on March 2011. During this reporting period, the principal work
activities are summarized in Table 2.8:
Table 2.8 Principal Work Activities for Contract no. HY/2009/19
September
2019 |
October
2019 |
November
2019 |
Bridge noise enclosure installation works.
Hing Fat Street road and drainage works.
Soft Landscaping works.
Open area hard paving works.
D9 to D12 and P22 to P25 drainage works.
Open area Fire Main laying work.
D12 masking wall |
Bridge noise enclosure installation works.
Hing Fat Street road works.
Soft Landscaping works.
Open area hard paving works.
D9 to D12 and P22 to P25 drainage works.
P17-P18 drainage downpipe installation works.
D12 masking wall |
Bridge noise enclosure installation works.
Hing Fat Street road works.
Soft Landscaping works.
Open area hard paving works.
D9 to D12 and P22 to P25 drainage works.
P17-P18 drainage downpipe installation works.
D12 masking wall |
2.5.3.
Major construction activities for Contract no. HK/2012/08 have been
commenced on March 2013. During the reporting period, the principal work
activities are summarized in Table 2.9
Table 2.9 Principal Work Activities for Contract no. HK/2012/08
September
2019 |
October
2019 |
November
2019 |
Remediation works
Landscaping |
Remediation works
Landscaping |
Nil |
2.5.4.
Major
construction activities for Contract no. HY/2010/08 have been commenced on
March 2013. During the reporting period, the principal work activities are
summarized in Table 2.10
Table 2.10 Principal Work Activities for Contract no. HY/2010/08
September
2019 |
October
2019 |
November
2019 |
Drainage improvement works
Utility diversion works
Junction modification |
Drainage improvement works
Utility diversion works
Junction modification |
Drainage improvement works
Utility diversion works
Junction modification |
2.5.5.
Contract
no. HY/2011/08 –Central - Wan Chai Bypass (CWB) –Tunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009/E.
During the reporting period, the principal work activities are summarized in Table
2.11
Table 2.11 Principal
Work Activities for Contract no. HY/2011/08
September 2019 |
October 2019 |
November 2019 |
ABWF works at Ventilation Buildings,
inclusive of Administration Building, Central Ventilation Building, East
Ventilation Shaft/Building, West Ventilation Building Scaffold erection at MVB Installation of external louvre at MVB Installation of glass canopy at ADB Installation of treated-waste wood at
ADB Drainage Works at Pump Sump C at Wan
Chai Floor painting works at MVB Traffic sign installation and
modification of directional sign at various locations Road resurfacing and road marking
works Painting works at Man Kwong Street |
ABWF works at Ventilation Buildings,
inclusive of Administration Building, Central Ventilation Building, East
Ventilation Shaft/Building, West Ventilation Building Scaffold erection at MVB Installation of external louvre at MVB Installation of glass canopy at ADB Installation of treated-waste wood at
ADB Floor painting works at MVB Traffic sign installation and
modification of directional sign at various locations Painting works
at Man Kwong Street Planting works
at Man Po Street and Kong Chung Lane |
ABWF works at Ventilation Buildings,
inclusive of Administration Building, Central Ventilation Building, East
Ventilation Shaft/Building, West Ventilation Building Scaffold erection at MVB Installation of external louvre at MVB Installation of glass canopy at ADB Installation of treated-waste wood at
ADB Floor painting works at MVB Traffic sign installation and
modification of directional sign at various locations Painting works at Man Kwong Street Planting works at Man Po Street and
Kong Chung Lane |
2.5.6.
Implementation
status of the recommended mitigation measures during this reporting period is
presented in Appendix 2.1.
3.1.1. The noise monitoring stations for the Project are listed
and shown in Table 3.1 and Figure 3.1. Appendix 3.1 shows the established Action/Limit Levels for the
monitoring works.
Table
3.1 Noise Monitoring Station
Station |
Description |
M1a* |
Footbridge at Ex-Harbour Road Sports Centre |
M2b |
Noon Gun
Area |
M3a |
Tung Lo Wan
Fire Station |
M4b |
Victoria Centre |
M5b |
|
M6 |
HK |
M7e* |
International Finance Centre (Eastern End of Podium) |
M7w |
International Finance Centre (Western End of Podium) |
M8** |
City Hall |
Remark*: Location ID
has been updated from M7 to M8 for City Hall
Remark**: M7e has
become a reference station starting from 7 Aug 2012
Remarks***: The
location ID of monitoring station M1a was updated as “Footbridge for Ex-Harbour
Road Sports Centre” in May 2017.
Real time Noise Monitoring Stations
3.1.2.
The noise monitoring
stations for the Project are listed and shown in Table 3.2 and Figure 3.1.. Appendix 3.1 shows the established Action/Limit Levels for the
monitoring works.
Table 3.2 Real Time Noise
Monitoring Station
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD Hong Kong Transport Section Whitefield Depot |
North Point |
RTN2a* |
Electric Centre |
North Point |
RTN3 |
Po Leung Kuk Yu Lee Mo Fan
Memorial School |
Tin Hau |
RTN4 |
|
Remarks*: RTN2 was
relocated from Oil Street Community Liaison Centre to Electric Centre on 05 Oct
2012 and re-designated as RTN2a.
Noise Monitoring
Parameters, Frequency and Duration
3.1.3.
The
construction noise level shall be measured in terms of the A-weighted
equivalent continuous sound
pressure level (Leq). Leq (30 minutes) shall be used as
the monitoring parameter for the time period between 0700 and
1900 hours on normal weekdays. For all other time periods, Leq (5 minutes)
shall be employed for comparison with the Noise Control Ordinance (NCO)
criteria. Supplementary information for data auditing,
statistical results such as L10 and L90 shall also be
obtained for reference.
3.1.4.
Noise monitoring
shall be carried out at all the designated monitoring stations. The monitoring
frequency shall depend on the scale of the construction activities. The
following is an initial guide on the regular monitoring frequency for each
station on a weekly basis when noise generating activities are underway:
·
One
set of measurements between 0700 and 1900 hours on normal weekdays.
3.1.5.
Real time noise
shall be carried out at the designated monitoring stations. The following is an
initial guide on the regular monitoring frequency for each station on a 24
hours daily basis when noise generating activities are underway:
·
One
set of measurements between 0700 and 1900 hours on normal weekdays.
·
One
set of measurements between 1900 and 2300 hours on normal weekdays and 0700 and
2300 hours on public holidays.
·
One
set of measurements between 2300 and 0700 hours on next day on everyday.
3.1.6.
If construction
works are extended to include works during the hours of 1900 – 0700 as well as
public holidays and Sundays, additional weekly impact monitoring shall be
carried out during respective restricted hours periods. Applicable permits
under NCO shall be obtained by the Contractor.
Monitoring Equipment
3.1.7.
As referred to in
the Technical Memorandum ™ issued under the NCO, sound level meters in
compliance with the International Electrotechnical Commission Publications 651:
1979 (Type 1) and 804: 1985 (Type 1) specifications shall be used for carrying
out the noise monitoring. Immediately prior to and following each noise
measurement the accuracy of the sound level meter shall be checked using an
acoustic calibrator generating a known sound pressure level at a known
frequency. Measurements may be accepted as valid only if the calibration level
from before and after the noise measurement agree to within 1.0 dB.
3.1.8.
Noise measurements
shall not be made in fog, rain, wind with a steady speed exceeding 5 m/s or
wind with gusts exceeding 10 m/s. The wind speed shall be checked with a
portable wind speed meter capable of measuring the wind speed in m/s.
3.1.9.
The sound level
meter shall be checked using an acoustic calibrator generating a known sound
pressure level at a known frequency before deployment to the site and during
each site visit. Measurements may be accepted as valid only if the calibration
level from before and after the noise measurement agree to within 1.0 dB.
Air Quality Monitoring Stations
3.2.1. The air quality monitoring stations for the Project
are listed and shown in Table 3.3 and Figure 3.1. Appendix 3.1 shows the established
Action/Limit Levels for the monitoring works.
Table
3.3 Air quality monitoring Stations
Station ID |
Monitoring
Location |
Description |
CMA1b |
Harbour Grand Hotel
Boundary Wall |
North Point |
CMA2a |
|
|
CMA3a |
CWB PRE Site Office |
|
CMA4a |
Society for the
Prevention of Cruelty to Animals |
Wan Chai |
CMA5b |
Pedestrian Plaza** |
Wan Chai |
MA1e |
International Finance Centre (Eastern End of Podium) |
Central |
MA1w |
International Finance Centre (Western End of Podium) |
Central |
Remarks*: The location ID of monitoring
station CMA1b was updated as “Oil Street Site Office” in
Remarks**: With respect to the area handover, the air
quality monitoring station CMA5a at Children Playgrounds opposite to the
Pedestrian Plaza was relocated to the Pedestrian Plaza on 3 December 2014. The
station reference and location ID of the air quality monitoring station CMA5a
was updated as CMA5b and Pedestrian Plaza respectively.
Air quality monitoring Parameters, Frequency and Duration
3.2.2. One-hour and 24-hour TSP levels should be measured
to indicate the impacts of construction dust on air quality. The 24-hour TSP
levels shall be measured by following the standard high volume sampling method
as set out in the Title 40 of the Code of Federal Regulations, Chapter 1 (Part
50), Appendix B.
3.2.3. All relevant data including temperature, pressure,
weather conditions, elapsed-time meter reading for the start and stop of the sampler,
identification and weight of the filter paper, and any other local atmospheric
factors affecting or affected by site conditions, etc., shall be recorded down
in detail.
3.2.4. For regular impact monitoring, the sampling
frequency of at least once in every six-days, shall be strictly observed at all
the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring,
the sampling frequency of at least three times in every six-days should be
undertaken when the highest dust impact occurs.
Sampling Procedure and Monitoring Equipment
3.2.5. High volume samplers (HVSs) in compliance with the
following specifications shall be used for carrying out the 1-hour and 24-hour
TSP monitoring:
·
0.6
– 1.7 m3 per minute adjustable flow range;
·
Equipped
with a timing / control device with +/- 5 minutes accuracy for 24 hours
operation;
·
Installed
with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;
·
Capable
of providing a minimum exposed area of 406 cm2;
·
Flow
control accuracy: +/- 2.5% deviation over 24-hour sampling period;
·
Equipped
with a shelter to protect the filter and sampler;
·
Incorporated
with an electronic mass flow rate controller or other equivalent devices;
·
Equipped
with a flow recorder for continuous monitoring;
·
Provided
with a peaked roof inlet;
·
Incorporated
with a manometer;
·
Able
to hold and seal the filter paper to the sampler housing at horizontal
position;
·
Easily
changeable filter; and
·
Capable
of operating continuously for a 24-hour period.
3.2.6. Initial calibration of dust monitoring equipment
shall be conducted upon installation and thereafter at bi-monthly intervals.
The transfer standard shall be traceable to the internationally recognized
primary standard and be calibrated annually. The concern parties such as IEC
shall properly document the calibration data for future reference. All the data
should be converted into standard temperature and pressure condition.
3.2.7. Laboratory Measurement / Analysis
3.2.8. A clean laboratory with constant temperature and
humidity control, and equipped with necessary measuring and conditioning
instruments to handle the dust samples collected, shall be available for sample
analysis, and equipment calibration and maintenance. The laboratory should be
HOKLAS accredited.
3.2.9. Filter paper of size 8” x 10” shall be labelled
before sampling. It shall be a clean filter paper with no pinholes, and shall
be conditioned in a humidity-controlled chamber for over 24-hours and be
pre-weighed before use for the sampling.
3.2.10. After sampling, the filter paper loaded with dust
shall be kept in a clean and tightly sealed plastic bag. The filter paper shall
then be returned to the laboratory for reconditioning in the humidity
controlled chamber followed by accurate weighing by an electronic balance with
readout down to 0.1 mg. The balance shall be regularly calibrated against a
traceable standard.
3.2.11. All the collected samples shall be kept in a good
condition for 6 months before disposal.
4.0.1. Per EPD’s letter dated 3 Aug
2012 (received by ET on 6 Aug 2012 through HyD), noise monitoring at M8 – City
Hall commenced on 7 Aug 2012, and the monitoring station M7e – International
Finance Centre (Eastern Podium) has become a reference station starting from 7
Aug 2012.
4.0.2. Due to safety concerns, the
monitoring location for M4b – Victoria Centre has been finely adjusted from 7
June 2012.
4.0.3. Monitoring for report of review baseline noise
level was performed from 11
4.0.4. The environmental monitoring will be implemented
based on the division of works areas of each designed project managed under
different contracts with separate FEP applied by individual contractors. Overall layout showing work areas of various
contracts, latest status of work commencement and monitoring stations is shown
in Figure 2.1 and Figure 3.1. The
monitoring results are presented in according to the Individual Contract(s).
4.0.5. The Construction works under HY/2009/18
was confirm completed by the RSS from 25 April 2018 onwards. The associated
monitoring station for HY/2009/18 were temporary suspended from 27 April 2018
onwards.
4.0.6. The Construction works under HY/2009/15
was confirm completed by the RSS from 27 October 2017 onwards. The associated
monitoring station for HY/2009/15 were temporally suspended from 27 October
2017 onwards.
4.0.7. As confirmed with WDII RSS and with
respect to the joint inspection conducted with IEC on 25 May 2018, RSS, ET and
IEC share the view that there is no adverse environmental impact of remaining
works under Contract HK/2009/01 and the associated monitoring station were
temporary suspended from 26 May 2018 onwards.
4.0.8. In the reporting period, the concurrent contracts are
as follows:
Contract
no. HY/2009/19 – Central
– Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009
Contract
no. HK/2009/02 Wanchai Development Phase II – Central- Wanchai Bypass at Wanchai
East under FEP-01/364/2009
Contract
no. HK/2012/08 – Wan Chai Development Phase II – Central- Wan Chai Bypass at
Wan Chai West under FEP-09/364/200/B
Contract
no. HY/2010/08 – Central and WanChai Bypass – Slip road 8 Section under
FEP-10/364/2009/B
Contract no. HY/2011/08 –Central - Wan
Chai Bypass (CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated
with Tunnel Commissioning under FEP-11/364/2009/E
Contract no. HK/2009/02 - Wanchai Development Phase
II - Central - Wanchai Bypass at Wanchai East (CWB Tunnel) under
FEP-01/364/2009
4.1.1.
The commencement of
construction works for Contract no. HK/2009/02 under FEP-01/364/2009 is on 26
Table
4.2
Noise
Monitoring Stations
for Contract no.
HK/2009/02
Station |
Description |
M1a |
Footbridge at Ex-Harbour Road Sports Centre |
Reporting period of September 2019
4.1.2.
No action or limit level exceedance was recorded in the reporting
period.
Reporting period of October 2019
4.1.3.
No action or limit level exceedance was recorded in the reporting
period.
Reporting period of November 2019
4.1.4.
No action or limit level exceedance was recorded in the reporting
period.
4.1.5.
Noise monitoring
results measured in this reporting period are reviewed and summarized. Details of noise monitoring results and graphical
presentation can be referred in Appendix 4.1.
Contract no. HY/2009/19 - Central -
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/G
4.1.6. Noise monitoring for the tunnel works under
contract no. HY/2009/19 was commenced on 24
Table 4.4 Noise
Monitoring Stations for Contract no. HY/2009/19
Station |
Description |
M4b |
Victoria Centre |
M5b |
|
M6 |
HK |
Reporting period of September 2019
4.1.7.
No action or limit level exceedance was recorded in the reporting
period.
Reporting period of October 2019
4.1.8.
No action or limit level exceedance was recorded in the reporting
period.
Reporting period of November 2019
4.1.9.
No action or limit level exceedance was recorded in the reporting
period.
4.1.10.
Noise monitoring results measured in this reporting
period are reviewed and summarized.
Details of noise monitoring results and graphical presentation can be
referred in Appendix 4.1 and the
Notification of Exceedance can be referred in Appendix 6.2.
Contract no. HY/2010/08 –
Central-Wanchai Bypass –Wanchai Bypass Tunnel (Slip Raod 8 Section) under FEP-10/364/2009/B
4.1.11. The commencement of construction works
for Contract no. HY/2010/08 under FEP-10/364/2009/B was on 02 September 2013.
Noise monitoring was commenced on 02 September 2013. The proposed divisions of
noise monitoring stations are summarized in Table 4.5 below.
Table 4.5 Noise Monitoring Stations for Contract no. HY/2010/08
Station |
Description |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
4.1.12.
As
confirmed with CWB RSS, junction modification works in Central area would be
conducted by Contract HY/2010/08 starting from July 2018 and tentatively
completed in September 2018. The noise monitoring station M7e - International
Finance Centre (Eastern End of Podium), M7w - International Finance Centre
(Western End of Podium) and M8 City Hall would tentatively associated with
Contract HY/2010/08.
4.1.13.
As
confirmed with Resident Site Staff, the junction modification under Contract
HY/2010/08 at Central Area was generally completed while the remaining works
was considered to be no adverse impact and not related to DP works. As such,
The noise monitoring station M7e - International Finance Centre (Eastern End of
Podium), M7w - International Finance Centre (Western End of Podium) and M8 –
City Hall would no longer associated with Contract HY/2010/08 in August 2019
reporting month.
Reporting period of September 2019
4.1.14.
No action or limit level exceedance was recorded in the reporting
period.
Reporting period of October 2019
4.1.15.
No action or limit level exceedance was recorded in the reporting
period.
Reporting period of November 2019
4.1.16.
No action or limit level exceedance was recorded in the reporting
period.
4.1.17.
Noise
monitoring results measured in this reporting period are reviewed and
summarized. Details of noise monitoring
results and graphical presentation can be referred in Appendix
4.1.
Contract no. HY/2011/08 – Central - Wan Chai Bypass
(CWB) – Tunnel Buildings, Systems and Fittings, and Works Associated with
Tunnel Commissioning
4.1.18. Noise monitoring for the Central
Interchange works under contract no. HY/2011/08 was commenced on 22 April
2011.The proposed division of noise monitoring stations for Contract no.
HY/2011/08 are summarized in Table 4.6 below:
Table 4.6 Noise Monitoring
Stations for Contract no. HY/2011/08
Station |
Description |
M4b |
Victoria Centre |
*M7e |
International Finance Centre (Eastern End of
Podium) |
M7w |
International Finance Centre (Western End of
Podium) |
M8 |
City Hall |
*
Remark: M7e has become a reference station starting from 7 Aug 2012
Reporting period of September 2019
4.1.19.
No action or limit level exceedance was recorded in the reporting
period.
Reporting period of October 2019
4.1.20.
No action or limit level exceedance was recorded in the reporting
period.
Reporting period of November 2019
4.1.21.
No action or limit level exceedance was recorded in the reporting
period.
4.1.22.
Noise
monitoring results measured in this reporting period are reviewed and
summarized. Details of noise monitoring
results and graphical presentation can be referred in Appendix 4.1
Contract no.
HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link under FEP-07/364/2009/G
4.2.1.
Real time noise monitoring
results measured in this reporting period are reviewed and summarized. Details of real time noise monitoring results and
graphical presentation can be referred to Appendix 4.2
4.2.2.
The proposed
division of noise monitoring stations are summarized in Table 4.7
below. Real time noise monitoring for major construction works under contract
no. HY/2009/19 was commenced on 24
Table 4.7 Real Time Noise
Monitoring Stations
for Contract no. HY/2009/19
Location ID |
District |
Description |
RTN1 |
Tin Hau |
FEHD Hong Kong Transport Section Whitefield Depot |
RTN2a |
North Point |
Electric Centre
(Replacement of RTN2) |
RTN3 |
North Point |
Pok Leung Kuk Yu |
RTN4 |
Tin Hau |
|
* Real time noise monitoring results and graphical presentation during
night time period are for information only.
*Real-time noise monitoring results and graphical presentation for RTN3
during restricted hours are for information only as no night classes were
conducted at the educational institute.
Reporting
period of September 2019
4.2.3.
No action
or limit level exceedance was recorded at RTN1 - FEHD Hong Kong Transport
Section Whitfield Depot in the reporting period.
4.2.4.
No action
or limit level exceedance was recorded at RTN2a - Hong Kong Electric Centre in the
reporting period.
4.2.5.
Limit
level exceedance was recorded at RTN3 - Yu Lee Mo Fan Memorial School on 6 and
23 September 2019 in the reporting period.
4.2.6.
After
checking with the Contractor, no construction activities was conducted under
Contractor HY/2009/19 around the monitoring station on 6 and 23 September 2019
during the monitoring period. Meanwhile, renovation works was conducted at
non-CWB construction site around the monitoring station and observed as major
noise contribution during monitoring. As such, the exceedance was considered as
non-Project related.
4.2.7.
No action
or limit level exceedance was recorded at RTN4 - Causeway Bay Community Centre in
the reporting period.
Reporting period of October 2019
4.2.8.
No action
or limit level exceedance was recorded at RTN1 - FEHD Hong Kong Transport
Section Whitfield Depot in the reporting period.
4.2.1.
Limit level exceedance was recorded at RTN2a - Hong Kong Electric Centre
on 5 October 2019 in the reporting period.
4.2.2.
After checking with the Contractor, no construction activities was
conducted under Contractor HY/2009/19 around the monitoring station on 5
October 2019 during the monitoring period. Meanwhile, renovation works was
conducted at non-CWB construction site around the monitoring station and
observed as major noise contribution during monitoring. As such, the exceedance
was considered as non-Project related.
4.2.3.
Limit level exceedance was recorded at RTN3 - Yu Lee Mo Fan Memorial
School on 8, 14 and 23 October 2019 in the reporting period.
4.2.9.
After checking with the
Contractor, no construction activities was conducted under Contractor HY/2009/19
around the monitoring station on 8, 14 and 23 October 2019 during the
monitoring period. Meanwhile, renovation works was conducted at non-CWB
construction site around the monitoring station and observed as major noise
contribution during monitoring. As such, the exceedance was considered as
non-Project related.
4.2.10.
No action
or limit level exceedance was recorded at RTN4 - Causeway Bay Community Centre
in the reporting period.
Reporting period of November 2019
4.2.11.
No action
or limit level exceedance was recorded at RTN1 - FEHD Hong Kong Transport
Section Whitfield Depot in the reporting period.
4.2.12.
No action
or limit level exceedance was recorded at RTN2a - Hong Kong Electric Centre in the
reporting period.
4.2.1.
No action or limit level exceedance was recorded at RTN3 - Yu Lee Mo Fan
Memorial School in the reporting period.
4.2.2.
No action or limit level exceedance was recorded at RTN4 - Causeway Bay
Community Centre in the reporting period.
4.2.4.
Real
time noise monitoring results measured in this reporting period are reviewed and
summarized. Details of real time noise monitoring results and graphical
presentation can be referred to Appendix 4.2
Contract no.
HY/2011/08 – Central - Wan Chai Bypass (CWB) – Tunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning
4.2.5.
The
proposed division of noise monitoring stations are summarized in Table
4.8 below. Real time noise monitoring for major construction works
under contract no. HY/2011/08 was commenced on 19 March 2015.
Table 4.8 Real Time Noise Monitoring Stations for Contract no. HY/2011/08
Location ID |
District |
Description |
RTN1 |
Tin Hau |
FEHD
Hong Kong Transport Section Whitfield Depot |
RTN2a1 |
North Point |
Hong
Kong Electric Centre |
RTN4 |
Tin
Hau |
Causeway Bay Community Centre |
* Real time noise monitoring results and graphical presentation during
restrict hours and night time period are for information only and noise during
CNP period shall be controlled under NCO.
Remarks 1: With
respect to the possession of site area Portion Xa and Portion Xb since 7 March
2016 as confirmed by CWB RSS, real time noise monitoring station RTN2a was
associated with Contract no. HY/2011/08 from 07 March 2016 onwards
Reporting period of September 2019
4.2.6.
No action
or limit level exceedance was recorded at RTN1 - FEHD Hong Kong Transport
Section Whitfield Depot in the reporting period.
4.2.7.
No action or limit level exceedance was recorded at RTN2a - Hong Kong
Electric Centre in the reporting period.
4.2.8.
No action
or limit level exceedance was recorded at RTN4 - Causeway Bay Community Centre
in the reporting period.
Reporting period of October 2019
4.2.9.
No action
or limit level exceedance was recorded at RTN1 - FEHD Hong Kong Transport
Section Whitfield Depot in the reporting period.
4.2.10.
Limit level exceedance was recorded at RTN2a - Hong Kong Electric Centre
on 5 October 2019 in the reporting period.
After checking with the Contractor, no construction
activities was conducted under Contractor HY/2011/08 around the monitoring
station on 5 October 2019 during the monitoring period. Meanwhile, renovation
works was conducted at non-CWB construction site around the monitoring station
and observed as major noise contribution during monitoring. As such, the
exceedance was considered as non-Project related.
4.2.11.
No action
or limit level exceedance was recorded at RTN4 - Causeway Bay Community Centre
in the reporting period.
Reporting period of November 2019
4.2.1.
No action
or limit level exceedance was recorded at RTN1 - FEHD Hong Kong Transport Section
Whitfield Depot in the reporting period.
4.2.2.
No action or limit level exceedance was recorded at RTN2a - Hong Kong
Electric Centre in the reporting period.
4.2.3.
No action
or limit level exceedance was recorded at RTN4 - Causeway Bay Community Centre
in the reporting period.
4.2.4.
Real time noise monitoring
results measured in this reporting period are reviewed and summarized. Details
of real time noise monitoring results and graphical presentation can be
referred to Appendix 4.2
4.3.1
Due to
extension of site boundary by contractor of HY/2009/19, location of air quality
monitoring station CMA1b – Oil Street Community Liaison Centre has been finely
adjusted on 21
Contract no. HK/2009/02 - Wan Chai Development
Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under
FEP-01/364/2009
4.3.2 The commencement of construction works for
HK/2009/02 under FEP-01/364/2009 is on 26
Table 4.11
Air quality monitoring
Station for Contract no. HK/2009/02
Station |
Description |
CMA3a |
CWB site office at Wanchai
Waterfront Promenade |
CMA4a |
Society for the Prevention of Cruelty to Animals |
Reporting period of September 2019
4.3.3
No action or limit level exceedance was recorded in the reporting
period.
Reporting period of October 2019
4.3.4
No action or limit level exceedance was recorded in the reporting period.
Reporting period of November 2019
4.3.5
One action level exceedance of 1hr TSP was recorded at CMA3a in the
reporting period.
4.3.6
After the investigation, it was noted that pavement reinstatement works
were undertaken on the monitoring date at around monitoring station CMA3a under
Contractor of HK/2009/02 and no particular observation regarding air quality impact
was observed during sampling. In view of the above, the action level exceedance
was considered to be non-project related and contributed by local ambient
condition. No exceedance was recorded in the subsequent monitoring on 14
November 2019.
4.3.7
One action level exceedance of 1hr TSP was recorded at CMA4a in the
reporting period.
4.3.8
After the investigation, it was noted that pavement reinstatement works
were undertaken on the monitoring date at around monitoring station CMA4a under
Contractor of HK/2009/02 and no particular observation regarding air quality impact
was observed during sampling. Meanwhile, non WDII-CWB Project construction
activities was observed opposite to the monitoring station on the monitoring
date. In view of the above, the exceedance was considered to be not related to
the Project works under Contract HK/2009/02 and potentially contributed by
nearby non WDII-CWB Project construction activities. No exceedance was recorded
in the subsequent monitoring on 14 November 2019.
4.3.9
Air quality monitoring
results measured in this reporting period are reviewed and summarized. Details of air quality monitoring results and
graphical presentation can be referred in Appendix 4.3.
Contract no.
HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link under FEP-07/364/2009/G
4.3.10 Air quality monitoring for the tunnel works was
commenced on 26
Table
4.13
Air quality monitoring
Stations
for Contract no. HY/2009/19
Station |
Description |
CMA1b |
Harbour
Grand Hotel Boundary Wall |
CMA2a |
|
Reporting period of September 2019
4.3.11
No action or limit level exceedance was recorded in the reporting
period.
Reporting period of October 2019
4.3.12
No action or limit level exceedance was recorded in the reporting period.
Reporting period of November 2019
4.3.13
One action level exceedance of 1hr TSP was recorded at CMA1b in the
reporting period.
4.3.14
After the investigation, it was noted that no construction works was
undertaken on the monitoring date at around monitoring station CMA1b under
Contractor of HY/2009/19 and no particular observation regarding air quality
impact was observed during sampling. In view of the above, the action level
exceedance was considered to be non-project related and contributed by local
ambient condition. No exceedance was recorded in the subsequent monitoring on
14 November 2019.
4.3.15 Air quality monitoring results measured
in this reporting period are reviewed and summarized. Details of air quality monitoring results and graphical presentation can
be referred in Appendix 4.3.
Contract
no. HK/2012/08- Wan Chai Development Phase II – Central-Wan Chai Bypass at Wan
Chai West under FEP-09/364/2009/B and
FEP-12/364/2009/D
4.3.16 The
commencement of construction works for Contract no. HK/2012/08 under
FEP-09/364/2009/B was on May 2014. Air quality monitoring was commenced on 14
July 2011. The
proposed division of air quality monitoring stations are summarized in Table
4.14 below.
Table 4.14 Air quality monitoring Station
for Contract no. HK/2012/08
Station |
Description |
CMA5b |
Pedestrian
Plaza |
Reporting
period of September 2019
4.3.17
No action or limit level exceedance was recorded in the reporting
period.
Reporting
period of October 2019
4.3.18
No action or limit level exceedance was recorded in the reporting period.
Reporting
period of November 2019
4.3.19
No action or limit level exceedance was recorded in the reporting
period.
4.3.20
As WDII RSS confirmation of construction works completion on 21 October
2019 and agreed with IEC on 1 November 2019, the associated monitoring station
for HK/2012/08 were temporary suspended from 1 November 2019 onwards.
4.3.21
Air quality monitoring results measured in this reporting period are
reviewed and summarized. Details of air quality monitoring results and
graphical presentation can be referred in Appendix 4.3.
Contract no. HY/2010/08 – Central-Wanchai Bypass –Wanchai Bypass Tunnel
(Slip Road 8 Section) under FEP-10/364/2009/B
4.3.22 The
commencement of construction works for Contract no. HY/2010/08 under FEP-10/364/2009/B
was on July 2014. Air quality monitoring was commenced on 14 July 2011. The proposed division of air quality
monitoring stations are summarized in Table 4.15 below.
Table 4.15 Air quality monitoring Station
for Contract no. HY/2010/08
Station |
Description |
CMA3a |
CWB
PRE Site Office |
4.3.23
As confirmed with CWB RSS, junction modification works in Central area
would be conducted by Contract HY/2010/08 starting from July 2018 and
tentatively completed in September 2018. The noise monitoring station MA1e -
International Finance Centre (Eastern End of Podium) and MA1w - International
Finance Centre (Western End of Podium) would tentatively associated with
Contract HY/2010/08.
4.3.24
As confirmed with Resident Site Staff, the junction
modification under Contract HY/2010/08 at Central Area was generally completed
while the remaining works was considered to be no adverse impact and not
related to DP works. As such, the air quality monitoring station MA1e -
International Finance Centre (Eastern End of Podium) and MA1w - International
Finance Centre (Western End of Podium) would no longer associated with Contract
HY/2010/08 in August 2019 reporting month.
Reporting
period of September 2019
4.3.25
No action or limit level exceedance was recorded in the reporting
period.
Reporting
period of October 2019
4.3.26
No action or limit level exceedance was recorded in the reporting period.
Reporting
period of November 2019
4.3.27
One action level exceedance of 1hr TSP was
recorded at CMA3a in the reporting period.
4.3.28 After the
investigation, it was noted that no construction work was undertaken on the monitoring
date at around monitoring station CMA3a under Contract HY/2010/08 and no particular
observation regarding air quality impact was observed during sampling. In view
of the above, the action level exceedance was considered to be non-project
related and contributed by local ambient condition. No exceedance was recorded
in the subsequent monitoring on 14 November 2019.
4.3.29
Air
quality monitoring results measured in this reporting period are reviewed and
summarized. Details of air quality monitoring results and
graphical presentation can be referred in Appendix 4.3.
Contract no.
HY/2011/08 – Central - Wan Chai Bypass (CWB) – Tunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning
4.3.30
Air quality monitoring for the Central Interchange works under contract
no. HY/2011/08 was commenced on 21 April 2011. The proposed division of air
quality monitoring stations are summarized in Table 4.16 below.
Table 4.16
Air
quality monitoring Stations
for Contract no. HY/2011/08
Station |
Description |
MA1e |
International
Finance Centre (Eastern End of Podium) |
MA1w |
International
Finance Centre (Western End of Podium) |
CMA1b |
Oil
Street Site Office |
CMA2a |
Causeway
Bay Community Centre |
CMA5b |
Pedestrian
Plaza |
Reporting
period of September 2019
4.3.31
No action or limit level exceedance was recorded in the reporting period.
Reporting
period of October 2019
4.3.32
No action or limit level exceedance was recorded in the reporting period.
Reporting
period of November 2019
4.3.33
One action level exceedance of 1hr TSP was recorded at CMA1b in the
reporting period.
4.3.34
After the investigation, it was noted that no construction works was
undertaken on the monitoring date at around monitoring station CMA1b under
Contractor of HY/2011/08 and no particular observation regarding air quality
impact was observed during sampling. In view of the above, the action level
exceedance was considered to be non-project related and contributed by local
ambient condition. No exceedance was recorded in the subsequent monitoring on
14 November 2019.
4.3.35
Air
quality monitoring results measured in this reporting period are reviewed and
summarized. Details of air quality monitoring results and
graphical presentation can be referred in Appendix 4.3.
4.4.1.
Inert
and non-inert C&D waste were disposed of in this reporting period. Details
of the waste flow table are summarized in Table 4.18.
Table 4.18 Details of Waste Disposal for Contract no. HK/2009/02
Inert C&D materials
disposed |
5342.5 |
551632.88 |
TKO137, TM 38 |
Inert C&D materials
recycled |
Nil |
46520 |
WCR2 |
Non-inert C&D
materials disposed |
82.4 |
6447.50 |
SENT Landfill |
Non-inert C&D
materials recycled |
Nil |
N/A |
N/A |
Chemical waste disposed |
Nil |
17718 |
N/A |
Marine Sediment (Type 1
– Open Sea Disposal) , m3 |
Nil |
65663 |
South Cheung Chau |
Contract no. HY/2009/18 - Central - Wan Chai Bypass
(CWB) – Central Interchange under FEP-05/364/2009/A
4.4.2.
No Inert
and non-inert C&D waste was disposed of in this reporting period. Details
of the waste flow table are summarized in Table 4.19.
Table 4.19 Details of Waste Disposal for
Contract no. HY/2009/18
Inert C&D materials
disposed |
Nil |
1415580.18 |
T.K.O. 137 |
Inert C&D materials
recycled |
Nil |
58787.05 |
N/A |
Non-inert C&D
materials disposed |
Nil |
4527.26 |
SENT Landfill |
Non-inert C&D materials recycled (tonnes) |
Nil |
878.37 |
N/A |
Chemical waste disposed |
Nil |
6772 |
N/A |
Remarks:
The cumulative amount of inert C&D material disposed has been updated in
the reporting period.
Contract no. HY/2009/15 –
Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) under
FEP-06/364/2009/A
4.4.3.
No Inert
& Non-inert C&D wastes were disposed of in this reporting period.
Details of the waste flow table are summarized in Table 4.20.
Table 4.20 Details of
Waste Disposal for Contract no. HY/2009/15
Waste Type* |
Quantity this quarter, m3 |
Cumulative-to-Date. m3 |
Disposal / Dumping Grounds |
Inert C&D materials
disposed, m3 |
Nil Nil |
625200.92 245453.3 |
Tuen Mun Area 38 TKO137 FB |
Inert C&D materials
recycled, m3 |
Nil |
358660.77 |
HY/2009/11 ex-PCWA TS4 /TS2 WDII Lun Ku Tan WENT HY/2010/08 |
Non-inert C&D
materials disposed, m3 |
Nil Nil |
4675.67 1.58 |
SENT Landfill WENT Landfill |
Non-inert C&D materials recycled , m3 |
Nil |
5496446.2 |
Xun Xiang Metalware Skylight Recycle (paper) |
Chemical waste disposed,
kg |
Nil |
22755 |
Dunwell Group |
Marine Sediment (Type1-Open
Sea Disposal (Dedicate Sites) &Type 2-Confined Marine Disposal), m3 |
Nil |
5684 |
South of the Brothers |
Contract no. HY/2009/19 – Central –
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/G
4.4.4.
Inert C&D materials was recycled
non-inert C&D waste was disposed of in this reporting period. Details of
the waste flow table are summarized in Table 4.21.
Table 4.21 Details of Waste Disposal for
Contract no. HY/2009/19
Inert C&D materials
disposed |
1952.7 |
820314.55 |
TKO137 TM38 |
Nil |
82349.7 |
N/A |
|
Non-inert C&D
materials disposed |
98.72 |
8680.14 |
SENT Landfill |
Non-inert C&D
materials recycled |
Nil |
565.63 |
N/A |
Chemical waste disposed |
0.33 |
16.04 |
N/A |
Marine Sediment (Tunnel) (Type 1- Open Sea
Disposal), m3 |
Nil |
20737.96 |
South of Cheung Chau |
Marine Sediment (Tunnel) (Type 1- Open Sea
Disposal (Dedicated Sites) & Type 2 – Confined Marine Disposal), m3 |
Nil |
30751 |
East
of Sha Chau |
Marine Sediment (Approach Ramp) (Type 2 –
Confined Marine Disposal), m3 |
Nil |
6491 |
East
of Sha Chau |
Contract no.
HK/2012/08 Wan Chai Development Phase II - Central-Wan Chai Bypass at Wan Chai
West under FEP-09/364/2009/B and FEP-12/364/2009/D
4.4.5.
Inert and
Non-inert C&D wastes were disposed of in this reporting period. Details of
the waste flow table are summarized in Table 4.22.
Table 4.22 Details of Waste Disposal for Contract no. HK/2012/08
Waste
Type* |
Quantity
this quarter, m3 |
Cumulative-to-Date,
m3 |
Disposal
/ Dumping Grounds |
Inert C&D materials disposed |
14 0 |
185157 119314 |
TKO137 TM38 |
Inert C&D materials recycled |
Nil |
Nil |
N/A |
Non-inert C&D materials disposed |
95 |
10287 |
SENT |
Non-inert C&D materials recycled |
NIL |
Nil |
N/A |
Chemical waste disposed |
NIL |
Nil |
N/A |
Marine Sediment (Type 1) Disposal, m3 |
Nil |
3145 |
South of Cheung Chau/ South of Brothers |
Contract no. HY/2010/08
Central – Wan Chai Bypass (CWB) –
Tunnel (Slip Road 8) under FEP-10/364/2009/B
4.4.6.
Inert and
Non-inert C&D wastes were disposed of in this reporting period. Details of
the waste flow table are summarized in Table 4.23.
Table 4.23 Details
of Waste Disposal for Contract no. HY/2010/08
Waste
Type* |
Quantity
this quarter, m3 |
Cumulative-to-Date,
m3 |
Disposal
/ Dumping Grounds |
Inert C&D
materials disposed |
7.12 Nil Nil 0 |
597625.22 262656.6 82911.8 72711.86 |
TM 38
/ CW / TKO137SF WENT SENT TKO
area 137 |
Inert C&D
materials recycled |
Nil |
Nil |
Nil |
Non-inert C&D
materials disposed |
9.66 |
6543.62 |
SENT |
Non-inert C&D
materials recycled |
Nil |
Nil |
Nil |
Chemical waste
disposed |
Nil |
1431 |
Nil |
Type 1 – Open Sea
Disposal |
Nil |
16368.4 |
East Sha Chau/ South Brothers Island |
Type 2 – Confined
Marine disposal |
Nil |
549.2 |
East Sha Chau |
Contract no. HY/2011/08
Central –Central - Wan Chai Bypass
(CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel
Commissioning under FEP-11/364/2009/E
4.4.7.
No inert and Non-inert C&D wastes were disposed of in this reporting
period. Details of the waste flow table are summarized in Table 4.24.
Table 4.24 Details of
Waste Disposal for Contract no. HY/2011/08
Waste Type* |
Quantity this quarter, m3 |
Cumulative-to-Date, m3 |
Disposal / Dumping Grounds |
Inert C&D materials disposed |
3.8 |
8585.824 |
CWPF & TKO137 |
Inert C&D materials recycled |
Nil |
Nil |
Nil |
Non-inert C&D materials disposed |
41.4 |
9193.42 |
SENT |
Non-inert C&D materials recycled |
Nil |
347.12 |
Nil |
Chemical waste disposed (kg) |
Nil |
3800 |
Nil |
5.0.1. The Event Action Plan for construction noise and air
quality are presented in Appendix
5.1.
Contract no. HK/2009/02 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel)
5.1.1.
No action
or limit level exceedance was recorded in the September 2019 reporting period.
5.1.2.
No action
or limit level exceedance was recorded in the October 2019 reporting period.
5.1.3.
No action
or limit level exceedance was recorded in the November 2019 reporting period.
Contract
no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link under FEP-07/364/2009/G
5.1.4.
No action
or limit level exceedance was recorded in the September 2019 reporting period.
5.1.5.
No action
or limit level exceedance was recorded in the October 2019 reporting period.
5.1.6.
No action
or limit level exceedance was recorded in the November 2019 reporting period.
Contract
no. HY/2010/08 – Central-Wanchai Bypass – Tunnel (Slip Road 8 Section) under
FEP-10/364/2009/B
5.1.7.
No action
or limit level exceedance was recorded in the September 2019 reporting period.
5.1.8.
No action
or limit level exceedance was recorded in the October 2019 reporting period.
5.1.9.
No action
or limit level exceedance was recorded in the November 2019 reporting period.
Contract
no. HY/2011/08 Central –Central - Wan Chai Bypass (CWB) –Tunnel Buildings,
Systems and Fittings, and Works Associated with Tunnel Commissioning under
FEP-11/364/2009/E
5.1.10. No action or limit level exceedance was
recorded in the September 2019 reporting period.
5.1.11. No action or limit level exceedance was
recorded in the October 2019 reporting period.
5.1.12. No action or limit level exceedance was
recorded in the November 2019 reporting period.
Contract nos. HK/2009/02 - Wan Chai Development
Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel)
5.2.1
No action or limit level exceedance was recorded in the September 2019
reporting period.
5.2.2
No action or limit level exceedance was recorded in the October 2019
reporting period.
5.2.1 One action level exceedance of 1hr TSP was recorded
at CMA3a – CWB site office at Wanchai Waterfront Promenade on 8 November 2019
in the November 2019 reporting period. After the investigation, the exceedance
was concluded as non-Project related.
5.2.2 One action level exceedance of 1hr TSP was recorded
at CMA4a – Society for the Prevention of Cruelty to Animals on 8 November 2019
in the November 2019 reporting period. After the investigation, the exceedance
was concluded as non-Project related.
Contract no. HY/2009/19 - Central -
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/G
5.2.3
No action or limit level exceedance was recorded in the September 2019
reporting period.
5.2.4
No action or limit level exceedance was recorded in the October 2019
reporting period.
5.2.5
One
action level exceedance of 1hr TSP was recorded at CMA1b – Harbour Grand Hotel
Boundary Wall on 8 November 2019 in the November 2019 reporting period. After the
investigation, the exceedance was concluded as non-Project related.
Contract no. HK/2012/08 Wan Chai Development Phase II - Central-Wan Chai
Bypass at Wan Chai West under FEP-09/364/2009/B and FEP-12/364/2009/D
5.2.6
No action or limit level exceedance was recorded in the September 2019
reporting period.
5.2.7
No action or limit level exceedance was recorded in the October 2019
reporting period.
5.2.8
No action or
limit level exceedance was recorded in the November 2019 reporting period.
5.2.9
As WDII RSS
confirmation of construction works completion on 21 October 2019 and agreed
with IEC on 1 November 2019, the associated monitoring station for HK/2012/08
were temporary suspended from 1 November 2019 onwards.
Contract no. HY/2010/08 – Central-Wanchai Bypass –
Tunnel (Slip Raod 8 Section) under FEP-10/364/2009/B
5.2.10
No action or limit level exceedance was recorded in the September 2019
reporting period.
5.2.11
No action or limit level exceedance was recorded in the October 2019
reporting period.
5.2.12
One
action level exceedance of 1hr TSP was recorded at CMA3a – CWB PRE Site Office
on 8 November 2019 in the November 2019 reporting period. After the
investigation, the exceedance was concluded as non-Project related.
Contract no. HY/2011/08 Central –Central - Wan Chai Bypass
(CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel
Commissioning under FEP-11/364/2009/E
5.2.13
No action or limit level exceedance was recorded in the September 2019
reporting period.
5.2.14
No action or limit level exceedance was recorded in the October 2019
reporting period.
5.2.15
One
action level exceedance of 1hr TSP was recorded at CMA1b – Harbour Grand Hotel
Boundary Wall on 8 November 2019 in the November 2019 reporting period. After the
investigation, the exceedance was concluded as non-Project related.
Contract
no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link under FEP-07/364/2009/G
5.3.1
24-hour real time noise monitoring was conducted at RTN1 - FEHD Hong
Kong Transport Section Whitfield Depot. No action or limit level exceedance was
recorded in the September 2019 reporting period.
24-hour real time noise monitoring was conducted at RTN2a – Hong Kong
Electric Centre. No action or limit level exceedance was recorded in the September
2019 reporting period.
24-hour real time noise monitoring was conducted at RTN3 – Yu Lee Mo Fan
Memorial School. Limit level exceedances were recorded on 6 and 23 September
2019 in the September 2019 reporting period. After the investigation, the
exceedances were concluded as non-project related.
24-hour real time noise monitoring was conducted at RTN4 – Causeway Bay
Community Centre. No action or limit level exceedance was recorded in the September
2019 reporting period.
5.3.2
24-hour real time noise monitoring was conducted at RTN1 - FEHD Hong
Kong Transport Section Whitfield Depot. No action or limit level exceedance was
recorded in the October 2019 reporting period.
24-hour real time noise monitoring was conducted at RTN2a – Hong Kong
Electric Centre. Limit level exceedance was recorded on 5 October 2019 in the October
2019 reporting period. After the investigation, the exceedances were concluded
as non-project related.
24-hour real time noise monitoring was conducted at RTN3 – Yu Lee Mo Fan
Memorial School. Limit level exceedances were recorded on 8, 14 and 23 October
2019 in the October 2019 reporting period. After the investigation, the
exceedances were concluded as non-project related.
24-hour real time noise monitoring was conducted at RTN4 – Causeway Bay
Community Centre. No action or limit level exceedance was recorded in the October
2019 reporting period.
5.3.3
24-hour real time noise monitoring was conducted at RTN1 - FEHD Hong
Kong Transport Section Whitfield Depot. No action or limit level exceedance was
recorded in the November 2019 reporting period.
24-hour real time noise monitoring was conducted at RTN2a – Hong Kong
Electric Centre. No action or limit level exceedance was recorded in the November
2019 reporting period.
24-hour real time noise monitoring was conducted at RTN3 – Yu Lee Mo Fan
Memorial School. No action or limit level exceedance was recorded in the November
2019 reporting period.
24-hour real time noise monitoring was conducted at RTN4 – Causeway Bay
Community Centre. No action or limit level exceedance was recorded in the November
2019 reporting period.
Contract
no. HY/2011/08 Central –Central - Wan Chai Bypass (CWB) –Tunnel Buildings,
Systems and Fittings, and Works Associated with Tunnel Commissioning under
FEP-11/364/2009/E
5.3.4
24-hour real time noise monitoring was conducted at RTN1 - FEHD Hong
Kong Transport Section
Whitfield Depot. No action or limit level exceedance was recorded in the September 2019 reporting
period.
24-hour real time noise monitoring was
conducted at RTN2a – Hong Kong Electric Centre. No action or limit
level exceedance was recorded in the September 2019 reporting period.
24-hour real time noise monitoring was
conducted at RTN4 – Causeway Bay Community Centre. No action or limit
level exceedance was recorded in the September 2019 reporting period.
5.3.5
24-hour real time noise monitoring was conducted at RTN1 - FEHD Hong
Kong Transport Section Whitfield Depot. No action or limit level exceedance was
recorded in the October 2019 reporting period.
24-hour real time
noise monitoring was conducted at RTN2a – Hong Kong Electric Centre. Limit
level exceedance was recorded on 5 October 2019 in the October 2019 reporting
period. After the investigation, the exceedance was concluded as non-project related.
24-hour real time
noise monitoring was conducted at RTN4 – Causeway Bay Community Centre. No action
or limit level exceedance was recorded in the October 2019 reporting period.
5.3.6
24-hour real time noise monitoring was conducted at RTN1 - FEHD Hong
Kong Transport Section Whitfield Depot. No action or limit level exceedance was
recorded in the November 2019 reporting period.
24-hour real time
noise monitoring was conducted at RTN2a – Hong Kong Electric Centre. No action
or limit level exceedance was recorded in the November 2019 reporting period.
24-hour real time
noise monitoring was conducted at RTN4 – Causeway Bay Community Centre. No action
or limit level exceedance was recorded in the November 2019 reporting period.
5.4.1
There was no non-compliance from the site audits in the reporting
period. During environmental site inspections conducted during the reporting period,
minor deficiencies were noted. However,
the Contractor rectified all deficiencies after receipt of notification.
5.5.1
EPD referred a complaint to ET on 25 September 2019 (CASE Ref:
H05/RS/00026537-19). It was alleged in the complaint that construction works
under Contract No. HK/2009/02 was carried out at around 21:00 hours on 11
September 2019 at Wan Shing Street, Wan Chai with 1 generator and 1 concrete
saw in operation. The works was suspected to contravene the Noise Control
Ordinance, Cap. 400.
5.5.2
ET confirmed with the Resident Site Staff that 1) CEDD and RSS conducted
the weekly ad-hoc site inspection on 11 September 2019 night time period; 2)
CEDD and RSS observed that one portable generator and one electrical hand held
grinder were operated at about 20:45 hours; 3) Construction Noise Permit
GW-RS0734-19 could not cover the above mentioned PME operation from 1900 to
2300 on 11 September 2019 at Wan Shing Street area; 4) RSS has immediately
discussed with the Contractor’s representative of Contract No. HK/2009/02 about
the incident and the works was stopped; 5) CEDD advised RSS to investigate the
cause of accident and provide action to prevent recurrence by 18 September
2019.
5.5.3
In view of the information gathered, the possible causes are as follow:
1) Contractor did not deploy enough supervision staff on-site to check the CNP
compliance of construction works during restricted hours; 2) The workers did
not follow the instruction of Contractor’s engineer.
5.5.4
The complaint was considered as Project related and Contractor of HK/2009/02
was required and urged to implement remedial measures and preventative measures
to ensure the strict compliance with construction noise permit.
5.6.1 The Corrective
Action including the Contractor’s engineer immediately stopped the worker to
use PME implemented immediately and Preventative Action recommended are as
follow: 1) The Contractor of HK/2009/02 was recommended to fully review the
“Supervision and Control Plan for Works in Restricted Hours”; 2) The Contractor
of HK/2009/02 was recommended to provide comprehensive training to frontline
supervisors and workers on the requirement and condition of CNP for the works,
including no unplanned PME operation should be allowed in restricted hours; 3)
The Contractor of HK/2009/02 was recommended that all PME (Hand tools) not
allowed to be used in the CNP should be removed from site during restricted
hours; 4) The Contractor of HK/2009/02 was recommended that the ignition device
for the PME on site should be kept by the assigned responsible person and any
workers intended to use of PME should obtain the permission from the assigned
responsible person beforehand; 5) The Contractor of HK/2009/02 was also
recommended to assign a delegated personnel to conduct checking on the
deployment of PME onsite during restricted hours to ensure only PME allowed
under relevant Construction Noise Permit are operated.
5.6.2
“Supervision and Control Plan for Works in Restricted Hours” (also known
as Noise Abatement and Management Plan) was reviewed and updated by Contractor
of HK/2009/02 on 2 October 2019. Other corrective and preventative measures
were generally implemented and under on-going review on effectiveness by CEDD,
RSS, ET and IEC. The interim report was submitted to the EPD on 3 October 2019.
6.0.1 One environmental complaint was received in the September 2019
reporting period.
EPD referred a complaint to ET on 25 September 2019 (CASE Ref:
H05/RS/00026537-19). It was alleged in the complaint that construction works
under Contract No. HK/2009/02 was carried out at around 21:00 hours on 11
September 2019 at Wan Shing Street, Wan Chai with 1 generator and 1 concrete
saw in operation. The works was suspected to contravene the Noise Control
Ordinance, Cap. 400.
ET confirmed with the Resident Site Staff that 1) CEDD and RSS
conducted the weekly ad-hoc site inspection on 11 September 2019 night time
period; 2) CEDD and RSS observed that one portable generator and one electrical
hand held grinder were operated at about 20:45 hours; 3) Construction Noise
Permit GW-RS0734-19 could not cover the above mentioned PME operation from 1900
to 2300 on 11 September 2019 at Wan Shing Street area; 4) RSS has immediately
discussed with the Contractor’s representative of Contract No. HK/2009/02 about
the incident and the works was stopped; 5) CEDD advised RSS to investigate the
cause of accident and provide action to prevent recurrence by 18 September
2019.
In view of the information gathered, the possible causes are as
follow: 1) Contractor did not deploy enough supervision staff on-site to check
the CNP compliance of construction works during restricted hours; 2) The
workers did not follow the instruction of Contractor’s engineer.
The complaint was considered as Project related and Contractor of
HK/2009/02 was required and urged to implement remedial measures and
preventative measures to ensure the strict compliance with construction noise
permit. The Corrective Action including the Contractor’s engineer immediately
stopped the worker to use PME implemented immediately and Preventative Action
recommended are as follow: 1) The Contractor of HK/2009/02 was recommended to
fully review the “Supervision and Control Plan for Works in Restricted Hours”;
2) The Contractor of HK/2009/02 was recommended to provide comprehensive
training to frontline supervisors and workers on the requirement and condition
of CNP for the works, including no unplanned PME operation should be allowed in
restricted hours; 3) The Contractor of HK/2009/02 was recommended that all PME
(Hand tools) not allowed to be used in the CNP should be removed from site
during restricted hours; 4) The Contractor of HK/2009/02 was recommended that
the ignition device for the PME on site should be kept by the assigned
responsible person and any workers intended to use of PME should obtain the
permission from the assigned responsible person beforehand; 5) The Contractor
of HK/2009/02 was also recommended to assign a delegated personnel to conduct
checking on the deployment of PME onsite during restricted hours to ensure only
PME allowed under relevant Construction Noise Permit are operated.
“Supervision and Control Plan for Works in Restricted Hours” (also
known as Noise Abatement and Management Plan) was reviewed and updated by
Contractor of HK/2009/02 on 2 October 2019. Other corrective and preventative
measures were generally implemented and under on-going review on effectiveness
by CEDD, RSS, ET and IEC. The interim report was submitted to the EPD on 3
October 2019.
6.0.2 No environmental complaint was received in the October 2019
reporting period.
6.0.3 One environmental complaint was received in the November 2019
reporting period.
An ICC complaint was referred to the ET on 31 October 2019 (CASE
Ref: CASE#2-5906833748). The complainant reported that:
Road improvement works on the westbound carriageway of the Island
Eastern Corridor are being carried out around 2 a.m. without any noise
mitigation measures, causing serious disturbance to residents of Provident
Centre.
ET confirmed with the Resident Site Staff that:
The ICC complaint was recorded on 26 October 2019 at around 02:15.
Emergency Construction Work (HyD Emergency Serial Number: EO1194) was notified
to EPD on 25 October 2019 18:15. The Emergency Construction Work including
replacement of movement joint and installation of defective noise panel at
noise enclosure was conducted at Island Eastern Corridor West Bound at Pier 46
from 26 October 2019 01:00 to 05:30.
During the concerned period, the PME operated and noise mitigation
measure implemented were as follow:
For replacement of movement joint:
- Total 2 no. of electric hand-held breakers, 2 no. of hand-held
drills and 1 no. of welding set were operated;
- Noise mitigation measure including acoustic enclosure comprised
of acoustics mat and plywood was provided to electric hand-held breakers.
For Installation of defective noise panel at noise enclosure:
- Total 1 no. of truck mounted aerial platform and 1 no. of
hand-held drill were operated.
In view of the information gathered, the complaint was considered
as related to noise nuisance from emergency construction work.
The Contractor of HY/2009/19 is recommended to adopt additional
noise mitigation measure for future emergency construction work as below:
The Contractor of HY/2009/19 is recommended to make sure the noise
enclosure deployed for breaking works or any other noisy activities shall be
fenced between the direct line of sight between the noise emanating source and
the NSR in order to minimize the noise impact. Standby noise mitigation
measures such as noise barrier or noise enclosure is recommended to stored
on-site for emergency deployment;
The Contractor of HY/2009/19 is recommended to make use QPME(s),
wherever possible, for emergency works to reduce the noise emission from site;
The Contractor of HY/2009/19 is recommended to avoid multiple PMEs
operated concurrently or reduce the amount of PMEs operated concurrently,
wherever possible, to avoid cumulative noise impact;
The Contractor of HY/2009/19 is recommended to complete the noisy
work as soon as possible to minimize disturbance to nearby residents;
The Contractor of HY/2009/19 is recommended to notify nearby noise
sensitive receivers in advance, wherever possible for future emergency
construction works
6.0.4
The details of cumulative complaint log
and summary of complaints are presented in Appendix
6.1.
6.0.5
Cumulative statistic on complaints and successful prosecutions are
summarized in Table 6.1 and Table 6.2 respectively.
Table 6.1 Cumulative Statistics on Complaints
Reporting Period |
No. of Complaints |
Commencement of Works up to last reporting period |
97 |
September to November 2019 |
2 |
Project-to-Date |
99 |
Table 6.2 Cumulative Statistics on Successful
Prosecutions
Environmental Parameters |
Cumulative No. Brought Forward |
No. of Successful Prosecutions this period
(Offence Date) |
Cumulative No. Project-to-Date |
Air |
1 |
0 |
1 |
Noise |
9 |
0 |
9 |
Water |
2 |
0 |
2 |
Waste |
0 |
0 |
0 |
Total |
12 |
0 |
12 |
7.0.2.
According to the Final EM&A Report of Central Reclamation Phase III
(CRIII) for Contract HK 12/02, the major construction activities were completed
by end of January 2014 and no construction activities were undertaken
thereafter and the water quality monitoring was completed in October 2011. As such, it is considered that there were no
cumulative construction impact due to the concurrent activities of the current
projects with the Central Reclamation Phase III (CRIII) undertaken by
contractor HK12/02 in the reporting period.
7.0.3.
According to the construction programme of Central-Wanchai Bypass at
Wanchai West at the Central Reclamation Phase III area, no works was conducted
in November 2019 reporting period. In view of the above, the cumulative
construction impact due to the Central Reclamation Phase III (CRIII) was not
anticipated in the reporting period of November 2019.
7.0.4.
According to the construction programme of Wan Chai Development Phase
II, Central-Wan Chai Bypass and Island Eastern Corridor Link projects, the
major construction activities under Wan Chai Development Phase II were road and
drains construction and trimming work at WCR1 and WCR3 at Wan Chai. The major
construction activities under Central-Wan Chai Bypass and Island Eastern
Corridor Link Projects were ventilation building ABWF works at Central; seabed
reinstatement at Causeway Bay; road works, drainage improvement work, utility
diversion works and landscape works at Victoria Park; bridge noise enclosure installation
works, road works, drainage works, soft landscape works and ventilation
building ABWF work at North Point area in the reporting period. In addition,
other non-Wan Chai Development Phase II, Central-Wan Chai Bypass and Island
Eastern Corridor Link projects were observed undertaken at Wan Chai North and
North Point area.
7.0.5.
No significant air impact from construction activities was anticipated
in the reporting period. Besides, no project related exceedance was recorded
during the air and noise environmental monitoring events in the reporting
period. Thus, it is evaluated that the cumulative construction impact from the
concurrent projects including Central Reclamation Phase III (CRIII), Wan Chai
Development Phase II (WDII), Central-WanChai Bypass (CWB), Island Eastern
Corridor Link projects (IECL) was insignificant.
8.0.1. The EM&A programme was carried out
in accordance with the EM&A Manual requirements, minor alterations to the
programme proposed were made in response to changing circumstances.
8.0.2. There was no non-compliance from the
site audits in the September,
October and November 2019
reporting period.
8.0.3. A total of Two environmental complaints were received in the September, October and November 2019 reporting period.
8.0.4. The construction
programmes of individual contracts are provided in Appendix 7.1.