`

 

 


 

 

 

Page   

TABLE OF CONTENTS

 

Executive SUMMARY       

 

1.0

INTRODUCTION

1

2.0

PROJECT INFORMATION

 

 

2.1 Project Background

1

 

2.2 Work Programme

1

 

2.3 Project Organization

2

 

2.4 Contact Details of Key Personnel

2

3.0

Work progress in this reporting month

2

4.0

Noise Monitoring

 

 

4.1 Monitoring Requirements

2

 

4.2 Monitoring Equipment

2

 

4.3 Monitoring Parameters, Duration and Frequency

2

 

4.4 Monitoring Locations

3

 

4.5 Monitoring Methodology

3

 

4.6 Action and Limit levels

4

 

4.7 Event-Action Plans

4

 

4.8 Results

4

5.0

Site Environmental Audit

4

 

5.1 Summary of the ET weekly site inspection findings

4 – 5

 

5.2 Recommendations on site inspection findings in Site Inspections of this month

5

6.0

Status of Environmental Permits

6

7.0

Waste Management

 

 

7.1 Monthly Waste Summary

6  

 

7.2 Advice on the Solid and Liquid Waste Management Status

6 – 7

8.0

Environmenatl non-conformance

 

 

8.1 Summary of Non-Conformance

7

 

8.2 Summary of Environmental Complaints

7

 

8.3 Summary of Notification of Summons and Prosecution

7

9.0

Implementation Status

 

 

9.1 Implementation Status of Environmental Mitigation Measures

7

 

9.2 Implementation Status of Event and Action Plan

7

 

9.3 Implementation Status of Environmental Complaint, Notifications of Summons and Successful Prosecutions Handling

7

10.0

Comments, Conclusion and Recommentations

7 – 8

11.0

Future key issue

 

 

11.1 Work Programme for the Coming Month

8

 

11.2 Key Issues for the Coming Month

8 – 9

 

 

APPENDIX

A

Organization Chart

B1

Calibration Certificates for Impact Noise Monitoring Equipment

B2

Impact Noise Monitoring Results

B3

Graphical Plots of Impact Noise Monitoring Data

C

Event-Action Plans

D

Work Programme

E

ET Weekly Site Inspection Records

F

Implementation Schedule of Mitigation Measures

G

Site General Layout Plan

H

Monthly Summary Waste Flow Table

I

Monitoring Schedule for this Reporting Month and the Coming Month

 


 

 

 

Figure

 

Figure 1

Locations of Noise Monitoring Stations

 

 

 

Tables

 

2.1

Contact Details of Key Personnel

4.1

Noise Monitoring Equipment

4.2

Details of Noise Monitoring Stations

4.3

Action and Limit levels for Noise Monitoring

4.4

Summary of Noise Monitoring Results

5.1

Key Findings of Weekly ET Site Inspections in this reporting month

6.1

Summary of Environmental Licensing and Permit valid in this reporting month

7.1

Summary of Quantities of Waste for Disposal in this reporting month

9.1

Summary of Environmental Complaints and Prosecutions

 


 

Executive SUMMARY

 

Under the requirements of “Environmental Monitoring & Audit Manual (Final) – Construction of Secondary Boundary Fence and New Sections of Primary Boundary Fence and Boundary Patrol Road” (the EM&A Manual), impact environmental monitoring and audit is required to be implemented for theContract No.: SS Y307 – Construction of Secondary Boundary Fence and New Section of Primary Boundary Fence and Boundary Patrol Road (Phase 2)” (the Project).

 

This monthly Environmental Monitoring and Audit (EM&A) report No.13 was prepared by ETS-Testconsult Ltd (ET) for the Project. This report documented the findings of EM&A Works conducted during the Project from February 2014.

 

Site Activities

 

As informed by the Contractor, site activities were carried out in this reporting month:

 

§   Foundation;

§   Concrete works;

§   Metal works;

§   Backfilling works; and

§   Installation of metal works.

 

Environmental Monitoring Progress

 

The summary of the monitoring activities in this monitoring month is listed below:

 

·            Day-time Noise Monitoring (0700-1900 on normal weekday): 4 Occasions at LW02, MW02, WL01(R) and WL03

·            Weekly-site inspection: 4 Occasions

 

Noise Monitoring

 

No exceedance of Action and Limit Level of noise monitoring was recorded in this reporting month.

 

Site Inspection

 

Environmental site inspections conducted in this reporting month are presented as follows:

 

Concerned Parties

Dates of Audit / Inspection

ET Weekly site inspection

05, 12,19 and 26 February 2014

Monthly Joint site inspection

12 February 2014

 

In general, performance on environmental mitigation measures implemented was found to be satisfactory in this reporting month. The major findings observed during site inspections are presented in Section 5.0.

 

Environmental Complaints, Notification of summons and successful prosecutions

 

No complaint, notification of summons and prosecution with respect to environmental issues was received in this reporting month.

 

Change in Environmental Aspect in this Reporting Month

 

No change on environmental aspect was reported in this reporting month.

 

Future Key Issues

 

Based on the forecast of site works in the coming month, key issues to be considered are as follows:

·           Noise impact due to construction works;

·           Maintain good site practice to minimize environmental impacts at the site.

 


 

1.0        INTRODUCTION

 

China International Water & Electric Corp. (CWE) has appointed Environmental Team of ETS-Testconsult Limited (ETL) to undertake the Environmental Impact Monitoring for Contract No.: SS Y307 – Construction of a Secondary Boundary Fence and New Sections of Primary Boundary Fence and Boundary Patrol Road (Phase 2)” (the Project) under the requirements of “Environmental Monitoring & Audit Manual (Final) – Construction of Secondary Boundary Fence and New Sections of Primary Boundary Fence and Boundary Patrol Road” (the EM&A Manual) and “the Further Environmental Permit No. FEP-05/347/2009/A - Construction of a Secondary Boundary Fence and New Sections of Primary Boundary Fence and Boundary Patrol Road” (the FEP).

 

This report documented the findings of EM&A Works conducted in February 2014.

 

 

2.0          PROJECT INFORMATION

 

2.1        Project Background

 

ASD Contract SS Y307 namely “The Construction of a Secondary Boundary Fence and New Sections of Primary Boundary Fence and Boundary Patrol Road (Phase 2)” to be executed comprise the following works generally along the boundary from Ng Tung River to Ping Yuen River (Section 3A) and from Pak Fu Shan to Lin Man Hang (Section 3C):

 

§   Construction of secondary boundary fence along the existing boundary patrol road completed with vehicular and pedestrian gate;

§   Construction of new bituminous boundary patrol road to the northwest of Lin Ma Hang;

§   Construction of primary boundary fence along the northern side of the new boundary patrol road and secondary boundary fence along the southern side of the new boundary patrol road complete with electrical and manual vehicular and pedestrian gates;

§   Provision of security lighting posts and luminaries along the boundary patrol road together with associated power supply installation including pillar boxes, electrical cables, power distribution system and the like;

§   Reinstatement and modification of existing bituminous road;

§   Associated landscaping works including tree felling, transplanting existing trees and provision of ground cover;

§   Provision of drainage system along the new boundary patrol road and modification of existing catchpits, box culverts and the like;

§   Provision of builder’s works in a subsequent installation of CCTV system and Fence Protection System carried out by the Hong Kong Police Force (HKPF);

§   Erection of frontier closed area warning signages;

§   Demolition works to be executed comprise the following works generally along the existing boundary fence from Lok Ma Chau Control Point to Sha Tau Kok:

§   Demolition of original primary boundary fence and associated facilities to the south of Lok Ma Chau Loop and Hoo Hok Wai;

§   Demolition of existing police posts and the associated facilities;

§   Demolition of existing FCA warning signs;

§   Demolition of exiting check points at Lok Ma Chau and Shek Chung Au.

 

Surrounding the construction site, there are village houses at Mai Po, Ma Tso Lung, Lo Wu, Muk Wu Chuen Yiu, Chuk Yuen, Wang Lek and Sha Tau Kok, which are considered as noise sensitive receivers of this Project.

 

Areas of the Project present in Appendix G. Locations of environmental monitoring stations is shown in Figure 1.

 

2.2        Work Programme

 

Details of work programme are shown in Appendix D.


 

2.3       Project Organization

 

Organization chart with respect to the on-site environmental management is shown in Appendix A.

 

2.4       Contact Details of Key Personnel

 

The key personnel contact names and telephone numbers are shown in Table 2.1.

 

Table 2.1           Contact Details of Key Personnel

Project Role

Organization

Name of Key Staff

Tel. No.

Fax No.

Engineer’s Representative

Mott MacDonald

Mr. James Kam

Mr. F. Y. Wong

2828 5757

2827 1823

IEC

ENVIRON

Mr David Yeung

3465 2888

3465 2899

Contractor’s Agent

CWE

Mr. Chris Chan

5646 5790

2508 0987

ET Leader

ET (ETL)

Mr C. L. Lau

2946 7791

2695 3944

 

 

3.0       Work Progress in this reporting month

 

As informed by the Contractor, site activity was carried out in the reporting month:

 

§   Foundation;

§   Concrete works;

§   Metal works;

§   Backfilling works; and

§   Installation of metal works.

 

 

4.0        Impact Noise Monitoring

 

4.1        Monitoring Requirements

 

As the requirement in the EM&A Manual, impact noise monitoring was conducted for a weekly basis at designated monitoring locations.

 

4.2        Monitoring Equipment

 

Integrating Sound Level Meters used for impact noise monitoring were Type 1 sound level meters capable of giving a continuous readout of the noise level reading including equivalent continuous sound pressure level (Leq) and percentile sound pressure level (Lx). They complied with International Electro technical Commission Publications 651:1979 (Type1) and 804:1985 (Type1).

 

Table 4.1 summarized the noise monitoring equipment model used during the impact monitoring. Copies of calibration certificates and calibration summary for noise meters and calibrators used are attached in Appendix B1.

 

Table 4.1           Noise Monitoring Equipment

Equipment

Model

Sound Level Meter

Rion NL-31

Sound Level Calibrator

Rion NC-73

 

4.3       Monitoring Parameters, Duration and Frequency

 

Impact noise monitoring for the A-weighted levels Leq, L10 and L90 were recorded once per week. Data obtained from impact noise monitoring was processed and presented as below:

 

·         Daytime: three sets of 30-minute noise level monitored between 0700-1900 hrs on normal weekdays;

·         Evening-time*: three sets of 5-minute noise level monitored between 1900-2300 hrs ;

·         Night-time*: three sets of 5-minute noise level monitored between 2300-0700 hrs of next day; and

·         Holiday*: three sets of 5-minute noise level monitored between 0700-1900 hrs on holiday.

(*): Noise monitoring to be conducted only when there is construction work.


 

4.4       Monitoring Locations

 

There was eight noise monitoring stations, VH01, VH03, MTL01, LW02, MW02, WL01(R), WL03 and STK05, were required to perform impact noise monitoring during the construction phase.

 

The detail of noise monitoring locations is summarized in Table 4.2.

 

Table 4.2        Details of Noise Monitoring Stations

Noise Monitoring Station

Description

Section

Type of Measurement

VH01

Village House at Mai Po

Section 1

Façade

VH03

Village House at Mai Po

Section 1

Façade

MTL01

Village House at Ma Tso Lung

Section 2

Façade

LW02

House No.39 at Lo Wu

Section 3A

Free Field *

MW02

House No.11, Muk Wu Chuen Yiu

Section 3A

Free Field *

WL01(R)

Village House at Wang Lek

Section 3C

Free Field *

WL03

Village House at Wang Lek

Section 3C

Free Field *

STK05

Village House at Sha Tau Kok

Section 4

Free Field *

Remark (*):   The monitoring stations LW02, MW02, WL01(R), WL03 and STK05 are all free-field located outside the premises of the nearby NSRs since they are enclosed areas and not willing to be entered. 3 dB(A) correction had been added to the results if noise measurement was free-field.

 

In this reporting month, the major construction works were carried out at Section 3A and therefore the impact noise monitoring was implemented at LW02 and MW02. Since minor site works, such as site preparation and site clearance work, were carried out at Section 3C in this reporting month, noise monitoring performed at WL01(R) and WL03 were used as reference. No noise monitoring was required at MTL01 at Section 2 in this reporting month since no construction work was undertaken in this reporting month.

 

4.5        Monitoring Methodology

 

Instrumentation

 

Integrating Sound Level Meters were employed for noise monitoring.

 

Operation/Analysis Procedures

 

·         Sound Level Meter was set on a tripod at a height of 1.2m above the ground;

·          For free field measurement, the meter was positioned away from any nearby reflective surfaces.

·          The battery condition was checked to ensure the correct functioning of the meter:

·          Parameters such as frequency weighting, the time weighting and the measurement time were set as follows:

 

-         Frequency weighting :  A

-         Time weighting          :  Fast

-         Time measurement    :  30 mins

·           Prior to and after each noise measurement, the meter was calibrated using a Calibrator for 94 dB at 1000HZ.  If the difference in the calibration level before and after measurement was more than 1.0 dB(A), the measurement would be considered invalid and repeat measurement would be required after re-calibration or repair of the equipment;

·           During the monitoring period, the Leq, L10 and L90 were recorded. In addition, site conditions and noise sources were recorded on a standard record sheet;

·           3dB(A) correction had been added to the results if noise measurements were free-field; and

·           Noise monitoring would be cancelled in the presence of fog, rain, storm, wind with a steady speed exceeding 5m/s, or wind gusts exceeding 10m/s.

 

Maintenance and Calibration

 

·         The microphone head of the sound level meter and calibrator are cleaned with soft cloth at quarterly intervals; and

·         The meters are sent to supplier or HOKLAS laboratory to check and calibrated at yearly intervals.


 

4.6        Actions and Limit Levels

 

The Action and Limit Levels (AL Levels) were established in accordance to the Table 4.3 of the EM&A Manual. Table 4.4 presents the AL levels for noise monitoring.

 

Table 4.3           Action and Limit Levels for Noise Monitoring

Time Period

Action

Limit

0700 –1900 hrs on normal weekday (Day-time)

When one documented complaint is received

75 dB(A) *

1900-2300 hrs (Evening-time)

70 dB(A)

0700-1900 hrs on Holiday (Holiday-time)

70 dB(A)

Restricted hours (2300-0700 hrs of next day) (Night-time)

55 dB(A)

* reduce to 70dB(A) for school and 65dB(A) during school examination periods

 

4.7        Event-Action Plans

 

Should the results of the monitoring parameters at any designated monitoring stations indicate that the noise level criteria are exceeded, the actions in accordance with the Event and Action Plan that summarized in Appendix C should be carried out.

 

4.8        Results

 

4 occasions of Day-time noise monitoring at noise monitoring stations, LW02, MW02, WL01(R) and WL03 were carried out at this reporting month.

 

No Day-time noise monitoring results at all monitoring stations exceeded the Action Level since no documented complaints on noise issue were received during the reporting period. Besides, no exceedances in Limit Level were recorded according to the results from Day-time noise monitoring. Table 4.4 summaries the noise daytime monitoring results in the reporting period.

 

Table 4.4           Summary of Impact Noise Monitoring Results

Monitoring Parameter

Date

LW02

MW02

WL01(R)

WL03

Result

Exceed*

Result

Exceed*

Result

Exceed*

Result

Exceed*

Daytime

05/02/14

57.2

X

46.4

X

45.9

X

44.7

X

12/02/14

56.7

X

45.9

X

45.9

X

46.2

X

19/02/14

56.7

X

46.7

X

45.9

X

46.4

X

26/02/14

56.7

X

48.2

X

46.3

X

44.7

X

Remark      (*):       L = Limit Level Exceedance, A = Action Level Exceedance and X = not an Exceedance

 

 

5.0        Site Environmental Audit

 

During this reporting month, weekly site inspections were undertaken on 05, 12, 19 and 26 February 2014 by ET. Monthly joint site inspection at 12 February 2014 was carried out by IEC, CWE and ET. A summary of implementation status of mitigation measures on site inspections is presented in Appendix F.

 

5.1        Summary of the ET weekly site inspection findings

 

According to the summary of the ET weekly site inspections carried out in February 2014, it indicated that site practices of the Contractor were generally undertaken in an environmentally acceptable manner and the overall site environmental performance was satisfactory. Summaries of key findings of weekly ET site inspections in this month are described in Table 5.1.


 

Table 5.1        Key Findings of Weekly ET Site Inspections in this reporting month

Date

Key Findings

Action(s) Taken recommended by ET

Action(s) Taken by the Contractor during the site audit

Rectification Status by ET

05 February 2014

Temporary stock piles without covers were observed in the New Road site. (Previous item)

The Contractor was reminded to cover the stock piles or spray with water in order to prevent dust emission.

Temporary stock pile without covered observed in the New Road site was improved.

Closed

Oil drum without drip tray was observed near Gate No. 69 at Lo Wu site. (Previous item)

The Contractor was reminded to provide drip tray for oil drum to avoid leakage of oil.

Oil drum without drip tray observed in Lo Wu site was removed.

Closed

12 February 2014

Rubbish was observed near Gate No. 76 in Lo Wu site. (New item)

The Contractor was reminded to collect the rubbish regularly to keep good site practices.

---

Follow-up

Oil drum without drip tray was observed near Gate No. 76  in Lo Wu site. (New item)

The Contractor was reminded to provide drip tray for oil drum to avoid leakage of oil.

---

Follow-up

Rubbish was observed near Fence No. 127/Gate No. 69 in Lo Wu site. (New item)

The Contractor was reminded to collect the rubbish regularly to keep good site practices.

---

Follow-up

Oil drum without drip tray was observed near Fence No. 129/Gate No.68 in Lo Wu site. (New item)

The Contractor was reminded to provide drip tray for oil drum to avoid leakage of oil.

---

Follow-up

Oil drum without drip tray was observed near Fence No. 200/Gate No.47 in Pak Fu Shan site. (New item)

The Contractor was reminded to provide drip tray for oil drum to avoid leakage of oil.

---

Follow-up

19 February 2014

Rubbish was observed near Gate No. 76 in Lo Wu site. (Previous item)

The Contractor was reminded to collect the rubbish regularly to keep good site practices.

Rubbish observed near Gate No. 76 in Lo Wu site was collected.

Closed

Oil drum without drip tray was observed near Gate No. 76  in Lo Wu site. (Previous item)

The Contractor was reminded to provide drip tray for oil drum to avoid leakage of oil.

Oil drum without drip tray observed near Gate No. 76  in Lo Wu site was removed and drip tray was provided.

Closed

Rubbish was observed near Fence No. 127/Gate No. 69 in Lo Wu site. (Previous item)

The Contractor was reminded to collect the rubbish regularly to keep good site practices.

Rubbish observed near Fence No. 127/Gate No. 69 in Lo Wu site was collected.

Closed

Oil drum without drip tray was observed near Fence No. 129/Gate No.68 in Lo Wu site. (Previous item)

The Contractor was reminded to provide drip tray for oil drum to avoid leakage of oil.

Drip tray was provided for the oil drum near Fence No. 129/Gate No.68 in Lo Wu site.

Closed

Oil drum without drip tray was observed near Fence No. 200/Gate No.47 in Pak Fu Shan site. (Previous item)

The Contractor was reminded to provide drip tray for oil drum to avoid leakage of oil.

Oil drum without drip tray observed near Fence No. 200/Gate No.47 in Pak Fu Shan site was removed.

Closed

26 February 2014

No observation / defective item was recorded during the site inspection.


 

5.2        Recommendations on site inspection findings in Site Inspections of this month

 

Based on the site inspection findings, the recommendations are as below:

·       Minimize  noise impact due to construction works;

·       Clean the access road regularly;

·       Cover or water the stockpile;

·       Checking and maintaining all the site machines to prevent black smoke emission;

·       Providing briefing to the concerned site staff on remedial actions, such as handling method of chemicals and chemical waste;

·       Implement all necessary preventive measures to avoid oil leakage. In the event an oil leakage happens, the Contractor should properly remove the leaked oil and handle the contaminated soil and all materials using for this cleaning works as chemical waste;

·       Maintain good waste management at the site

·       Remove all stagnant water; and

·       Apply proper treatment facilities to wastewater before discharge.

 

 

6.0       Status of Environmental Permits

 

Permits/licenses valid in this reporting month are summarized in Table 6.1.

 

Table 6.1        Summary of Environmental Licensing and Permit valid in this reporting month

Description

Permit No.

Valid Period

Concerned Locations

From

To

Environmental Permit

FEP-05/347/2009/A

10/08/12

End of Project

Section 3 – from Ng Tung River to Ping Yuen River and from Pak Fu Shan to Lin Ma Hang

Wastewater Discharge Licence

W5/1G43/1

09/10/12

31/10/17

Section 3A and Section 3C (Effluent arising from Construction site Sedimentation Tank(s) and other necessary treatment facilities)

Chemical Waste Producer

5213-641-C1206-09

09/10/12

End of Project

Section 3A and Section 3C (Spent Paints, Spent Diesel and Spent Lubricating Oil)

Notification under APCO

Application had been submitted to EPD on 28/08/12 and approved from 30/08/12.

Notification under WCO

Application had been submitted to EPD on 28/08/12 and approved from 30/08/12.

 

 

7.0        Waste Management

 

7.1        Monthly Waste Summary

 

The quantities of waste generated from the Project in this month are summarized in Table 7.1 and monthly summary waste flow table present in Appendix H.

 

Table 7.1        Summary of Quantities of Waste generated in this reporting month

Type of Waste

Quantity

Cumulative Quantity from February 2013

Inert C&D Materials

Total Quantity Generated (in ‘000m3)

0

0.238

Hard Rocks and Large Broken Concrete (in ‘000m3)

0

0.03

Reused in the Contract (in ‘000m3)

0

0

Reused in other Projects (in ‘000m3)

0

0

Disposal as Public Fill (in ‘000m3)

0

0.208

Imported Fill (in ‘000m3)

0.052

0.052

C&D Waste

Metals (in ‘000kg)

0

0.02

Paper/Cardboard Packaging (in ‘000kg)

0.02

0.140

Plastics (in ‘000kg)

0

0

Chemical Waste (in ‘000kg)

0

0

Other, e.g. General Refuse (in ‘000m3)

0

0.9945


 

7.2        Advice on the Solid and Liquid Waste Management Status

 

The Contractor should provide sufficient preventive measures during equipment maintenance works so as to avoid oil leakage on the ground. In the event of any oil leakage, the Contractor should clean up the polluted soil and handle all the materials used for this cleaning works as chemical waste.

 

Besides, pre-cast drip trays were provided for oil drums at several areas, such as generator and chemical storage area. The Contractor should collect and dispose of any stagnant water accumulated in the drip trays and handle them as chemical waste.

 

The Contractor should use suitable containers with proper labels to store chemical wastes in accordance with Code of Practice on the Packaging, Labeling and Storage of Chemical Waste. The Contractor should also advise their workers of the proper procedures in handling the chemical waste.

 

All the trip tickets for chemical waste disposal were properly kept in the site office. No chemical waste disposal was undertaken in the reporting month.

 

The Contractor was reminded to increase the frequency of inspection and cleaning of the site drainage system, including desilting facilities. Moreover, the Contractor should apply approved pesticides in the stagnant water.

 

 

8.0        Environmental Non-conformance

 

8.1       Summary of Non-Conformance

 

No exceedance of Action and Limit Level of noise monitoring was recorded in this reporting month.

 

8.2        Summary of Environmental Complaints

 

No complaint was received in this reporting month.

 

8.3        Summary of Notification of Summons and Prosecution

 

There was no notification of summons respect to environmental issues registered in this month.

 

 

9.0        Implementation Status

 

9.1       Implementation Status of Environmental Mitigation Measures

 

An updated summary of the Environmental Mitigation Implementation Schedule (EMIS) is presented in Appendix F. Most of the necessary mitigation measures were implemented properly. Any deficiencies were noted in the remarks of the schedule.

 

9.2       Implementation Status of Event and Action Plan

 

No exceedance of Action and Limit Level of noise monitoring was recorded in this reporting month. Hence, no further action was required.

 

9.3        Implementation Status of Environmental Complaint, Notifications of Summons and Successful Prosecutions Handling

 

No complaint, notification of summons and successful prosecution were received in this reporting month. A summary of environmental complaints, notifications of summons and successful prosecutions was given in Table 9.1.

 

Table 9.1           Summary of Environmental Complaints and Prosecutions

Complaints logged

Summons served

Successful prosecution received

February 2014

Overall Cumulative from February 2013

February 2014

Overall Cumulative from February 2013

February 2014

Overall Cumulative from February 2013

0

0

0

0

0

0

 


 

10.0      Comments, Conclusions and recommendations

 

Comments and Conclusions

 

Impact noise monitoring was carried out at designated locations in accordance with the EM&A Manual in this reporting month.

 

No exceedance of Action and Limit Level of impact noise monitoring was recorded in this reporting month.

 

According to the ET weekly site inspections carried out in this reporting month, the Contractor generally implemented sufficient environmental mitigation measures.

 

No complaint, prosecution or notification of summon was received in this reporting month.

 

Recommendations

 

According to the environmental site inspections performed in the reporting month, the following recommendations were provided:

 

Air Quality

§  Ensure the frequency of water spraying on unloading areas and stockpiles to be sufficient to suppress the dust sources;

§  Provide proper maintenance for the powered mechanical equipment and barges to avoid emission of dark smoke; and

§  Implement the dust mitigation measures for the site activities.

 

Noise

§  Conduct noisy activities at a farther location from the NSRs.

 

Water Quality

§  Provide proper treatment for the wastewater discharge; and

§  Remove the stagnant water or provide approved pesticides for the stagnant water, if any.

 

Chemical and Waste Management

§   Remove waste materials from the site to avoid accumulation regularly;

§  Handle and store chemical wastes properly;

§  Remove unwanted material in the existing stockpiles and avoid further dumping of such material;

§  Provide and maintain sufficient drip trays for diesel drums, chemical containers, chemical waste storage drums and diesel operated generator set; and

§  Maintain good housekeeping at the works area..

 

 

11.0      Future Key Issues

 

11.1      Work Programme for the Coming Month

 

As informed by the Contractor, site activities proposed to be carried out in the coming month:

 

§   Foundation;

§   Concrete works;

§   Metal works;

§   Backfilling works; and

§   Installation of metal works.

 

11.2      Key Issues for the Coming Month

 

Key issues to be considered in the coming month include:

 

·            Minimize  noise impact due to construction works;

·            Clean the access road regularly;

·            Cover or water the stockpile;

·            Checking and maintaining all the site machines to prevent black smoke emission;

·            Providing briefing to the concerned site staff on remedial actions, such as handling method of chemicals and chemical waste;

·            Implement all necessary preventive measures to avoid oil leakage. In the event an oil leakage happens, the Contractor should properly remove the leaked oil and handle the contaminated soil and all materials using for this cleaning works as chemical waste;

·            Maintain good waste management at the site

·            Remove all stagnant water; and

·            Apply proper treatment facilities to wastewater before discharge.

 

Mitigation measures to be required in the coming month:

 

Air Quality Impact

§  To ensure implementation of the dust mitigation measures for the site activities;

§  To provide proper maintenance for vehicles and machines on site; and

§  To investigate any other dust sources around the air sensitive receivers

 

Noise

§  To switch off equipment if not in use;

§  To operate silent equipment; and

§  To re-schedule the work activities in the event of valid noise exceedance.

 

Water Quality Impact

§  To maintain the drainage system;

§  To provide covers for the drip trays to avoid stagnant water due to rainfall;

§  To provide proper treatment for wastewater from the area; and

§  To avoid any stagnant water or provide insecticide to avoid mosquito breeding.

 

Chemical and Waste Management

§  To remove waste from the site regularly;

§  To properly store and handle chemical wastes on site;

§  To provide and manage sufficiently sized drip trays for diesel drums or chemical containers;

§  To maintain proper housekeeping;

§  To remove the oil stains in the event of leakage and handle all materials using for this cleaning works as chemical waste; and

§  To identify C&D material by packaging, labeling, storage, transportation and disposal in accordance with statutory regulations.

 

 

 

- END OF REPORT -