`
Page
TABLE OF
CONTENTS
1.0 |
1 |
|
2.0 |
|
|
|
2.1 Project Background |
1 |
|
2.2 Work Programme |
1 |
|
2.3 Project Organization |
2 |
|
2.4 Contact Details of Key Personnel |
2 |
3.0 |
2 |
|
4.0 |
|
|
|
4.1
Monitoring Requirements |
2 |
|
4.2
Monitoring Equipment |
2 |
|
4.3
Monitoring Parameters, Duration and Frequency |
2 |
|
4.4
Monitoring Locations |
3 |
|
4.5
Monitoring Methodology |
3 |
|
4.6
Action and Limit levels |
4 |
|
4.7
Event-Action Plans |
4 |
|
4.8
Results |
4 |
5.0 |
4 |
|
|
5.1 Summary of the ET weekly site inspection findings |
4 – 5 |
|
5.2 Recommendations on site inspection findings in
Site Inspections of this month |
5 |
6.0 |
6 |
|
7.0 |
|
|
|
7.1 Monthly
Waste Summary |
6 |
|
7.2 Advice on the Solid and Liquid Waste
Management Status |
6 – 7 |
8.0 |
|
|
|
8.1 Summary of Non-Conformance |
7 |
|
8.2
Summary of Environmental Complaints |
7 |
|
8.3
Summary of Notification of Summons and Prosecution |
7 |
9.0 |
|
|
|
9.1
Implementation Status of Environmental Mitigation Measures |
7 |
|
9.2
Implementation Status of Event and Action Plan |
7 |
|
9.3
Implementation Status of Environmental Complaint, Notifications of Summons
and Successful Prosecutions Handling |
7 |
10.0 |
7 – 8 |
|
11.0 |
|
|
|
11.1 Work Programme for the Coming Month |
8 |
|
11.2 Key Issues for the Coming Month |
8 – 9 |
APPENDIX |
|
Organization Chart |
|
Calibration Certificates
for Impact Noise Monitoring Equipment |
|
Impact Noise Monitoring
Results |
|
Graphical Plots of
Impact Noise Monitoring Data |
|
Event-Action Plans |
|
Work Programme |
|
ET Weekly Site Inspection Records |
|
Implementation Schedule
of Mitigation Measures |
|
Site General Layout Plan |
|
Monthly Summary Waste Flow Table |
|
Monitoring Schedule for this Reporting Month and the Coming Month |
|
|
Figure 1 |
Locations of Noise Monitoring Stations |
Tables |
|
2.1 |
Contact
Details of Key Personnel |
4.1 |
Noise
Monitoring Equipment |
4.2 |
Details of Noise Monitoring
Stations |
4.3 |
Action
and Limit levels for Noise Monitoring |
4.4 |
Summary
of Noise Monitoring Results |
5.1 |
Key
Findings of Weekly ET Site Inspections in this reporting month |
6.1 |
Summary
of Environmental Licensing and Permit valid in this reporting month |
7.1 |
Summary
of Quantities of Waste for Disposal in this reporting month |
9.1 |
Summary of Environmental Complaints and
Prosecutions |
Under the requirements of “Environmental Monitoring & Audit Manual (Final)
– Construction of Secondary Boundary Fence and
New Sections of Primary Boundary Fence and Boundary Patrol Road” (the EM&A Manual), impact environmental monitoring and audit is required to be implemented for the “Contract No.: SS Y307 –
Construction of Secondary Boundary Fence and New Section of Primary Boundary
Fence and Boundary Patrol Road (Phase 2)” (the Project).
This monthly Environmental Monitoring and
Audit (EM&A) report No.13 was prepared by ETS-Testconsult Ltd (ET) for
the Project. This report documented the findings of EM&A Works conducted during
the Project from
February 2014.
Site Activities
As informed by the Contractor, site activities were
carried out in
this reporting month:
§
Foundation;
§
Concrete
works;
§
Metal
works;
§
Backfilling
works; and
§
Installation
of metal works.
Environmental Monitoring Progress
The summary of the monitoring activities
in this monitoring month is listed below:
·
Day-time Noise Monitoring (0700-1900
on normal weekday): 4 Occasions at LW02,
MW02, WL01(R) and WL03
·
Weekly-site inspection: 4 Occasions
Noise
Monitoring
No exceedance
of Action and Limit Level
of noise monitoring was recorded in this reporting month.
Site Inspection
Environmental site
inspections conducted in this reporting month are presented as follows:
Concerned Parties |
Dates of Audit / Inspection |
ET Weekly site inspection |
05,
12,19 and 26 February 2014 |
Monthly Joint
site inspection |
12
February 2014 |
In general, performance on environmental
mitigation measures implemented was found to be satisfactory in this reporting
month. The major findings observed
during site inspections are presented in Section 5.0.
Environmental Complaints, Notification of
summons and successful prosecutions
No complaint, notification of summons and prosecution with respect to environmental
issues was received in this reporting month.
Change in Environmental Aspect in this
Reporting Month
No change on environmental aspect was reported in this reporting month.
Future
Key Issues
Based on the forecast of site works in the
coming month, key issues to be considered are as follows:
·
Noise impact due to
construction works;
·
Maintain good site practice to minimize
environmental impacts at the site.
1.0 INTRODUCTION
China
International Water & Electric Corp. (CWE) has appointed Environmental
Team of ETS-Testconsult Limited (ETL) to undertake the Environmental Impact Monitoring for “Contract No.: SS Y307 – Construction of a Secondary Boundary Fence and
New Sections of Primary Boundary Fence and Boundary Patrol Road (Phase 2)” (the Project) under the requirements of “Environmental Monitoring & Audit Manual (Final) – Construction of Secondary Boundary Fence and New
Sections of Primary Boundary Fence and Boundary Patrol Road” (the EM&A Manual) and “the Further Environmental Permit No. FEP-05/347/2009/A
- Construction of
a Secondary Boundary Fence and New Sections of Primary Boundary Fence and
This report
documented the findings of EM&A Works conducted in
February 2014.
2.1 Project Background
ASD Contract SS Y307 namely “The Construction of a Secondary Boundary
Fence and New Sections of Primary Boundary Fence and Boundary Patrol Road
(Phase 2)” to be executed comprise the following works generally along the
boundary from Ng Tung River to Ping Yuen River (Section
§
Construction of secondary boundary
fence along the existing boundary patrol road completed with vehicular and
pedestrian gate;
§
Construction of new bituminous boundary
patrol road to the northwest of Lin Ma Hang;
§
Construction of primary boundary fence
along the northern side of the new boundary patrol road and secondary boundary
fence along the southern side of the new boundary patrol road complete with
electrical and manual vehicular and pedestrian gates;
§
Provision of security lighting posts
and luminaries along the boundary patrol road together with associated power
supply installation including pillar boxes, electrical cables, power
distribution system and the like;
§
Reinstatement and modification of
existing bituminous road;
§
Associated landscaping works including
tree felling, transplanting existing trees and provision of ground cover;
§
Provision of drainage system along the
new boundary patrol road and modification of existing catchpits,
box culverts and the like;
§
Provision of builder’s works in a
subsequent installation of CCTV system and Fence Protection System carried out
by the Hong Kong Police Force (HKPF);
§
Erection of frontier closed area
warning signages;
§
Demolition works to be executed comprise
the following works generally along the existing boundary fence from Lok Ma Chau Control Point to Sha
Tau Kok:
§ Demolition of original primary boundary fence and associated facilities
to the south of Lok Ma Chau Loop and Hoo Hok Wai;
§ Demolition of existing police posts and the associated facilities;
§ Demolition of existing FCA warning signs;
§ Demolition of exiting check points at Lok Ma
Chau and Shek Chung Au.
Surrounding the construction site, there are
village houses at
Areas of the Project present in
Appendix G. Locations of environmental monitoring stations is shown in Figure 1.
2.2 Work
Programme
Details of work programme are shown in Appendix D.
2.3 Project Organization
Organization chart with
respect to the on-site environmental management is shown in
Appendix A.
2.4 Contact Details of Key
Personnel
The key personnel contact names and
telephone numbers are shown in Table 2.1.
Table 2.1 Contact Details of Key Personnel
Project Role |
Organization |
Name of Key Staff |
Tel. No. |
Fax No. |
Engineer’s Representative |
Mott MacDonald |
Mr. James Kam Mr. F. Y. Wong |
2828 5757 |
2827 1823 |
IEC |
ENVIRON |
Mr David Yeung |
3465 2888 |
3465 2899 |
Contractor’s Agent |
CWE |
Mr. Chris Chan |
5646 5790 |
2508 0987 |
ET
Leader |
ET
(ETL) |
Mr
C. L. Lau |
2946
7791 |
2695
3944 |
3.0 Work Progress in this reporting month
As
informed by the Contractor, site activity was carried out in the
reporting month:
§
Foundation;
§
Concrete
works;
§
Metal
works;
§
Backfilling
works; and
§
Installation
of metal works.
4.1 Monitoring Requirements
As the
requirement in the EM&A Manual, impact noise monitoring
was conducted for a weekly basis at designated monitoring locations.
4.2 Monitoring Equipment
Integrating
Sound Level Meters used for impact noise monitoring were Type 1 sound level
meters capable of giving a continuous readout of the noise level reading including
equivalent continuous sound pressure level (Leq)
and percentile sound pressure level (Lx). They complied with International
Electro technical Commission Publications 651:1979 (Type1) and
804:1985 (Type1).
Table
4.1 summarized the noise monitoring equipment model used during the impact
monitoring. Copies of calibration certificates and calibration summary
for noise meters and calibrators used are attached in Appendix B1.
Table
4.1 Noise Monitoring Equipment
Equipment |
Model |
Sound Level Meter |
Rion NL-31 |
Sound Level Calibrator |
Rion NC-73 |
4.3 Monitoring Parameters, Duration and Frequency
Impact noise monitoring for the A-weighted levels Leq, L10 and L90 were
recorded once per week. Data obtained from impact noise monitoring was
processed and presented as below:
·
Daytime:
three sets of 30-minute noise level monitored between 0700-1900 hrs on normal
weekdays;
·
Evening-time*:
three sets of 5-minute noise level monitored between 1900-2300 hrs ;
·
Night-time*:
three sets of 5-minute noise level monitored between 2300-0700 hrs of next day;
and
·
(*): Noise monitoring to be conducted only when there is
construction work.
4.4 Monitoring Locations
There was
eight noise monitoring
stations, VH01, VH03, MTL01, LW02, MW02, WL01(R), WL03 and STK05, were
required to perform impact noise monitoring during the construction phase.
The detail of noise monitoring locations is summarized in Table 4.2.
Table
4.2 Details of Noise Monitoring Stations
Noise Monitoring Station |
Description |
Section |
Type of Measurement |
VH01 |
Village House at Mai Po |
Section 1 |
Façade
|
VH03 |
Village House at Mai Po |
Section 1 |
Façade
|
MTL01 |
Village House at Ma Tso Lung |
Section 2 |
Façade
|
LW02 |
House No.39 at Lo Wu |
Section |
Free Field * |
MW02 |
House No.11, Muk Wu Chuen Yiu |
Section |
Free Field * |
WL01(R) |
Village House at Wang Lek |
Section |
Free Field * |
WL03 |
Village House at Wang Lek |
Section |
Free Field * |
STK05 |
Village House at Sha
Tau Kok |
Section 4 |
Free Field * |
Remark (*): The monitoring stations LW02, MW02, WL01(R), WL03 and STK05 are
all free-field located outside the premises of the nearby NSRs since they are
enclosed areas and not willing to be entered. 3 dB(A)
correction had been added to the results if noise measurement was free-field.
In this reporting month, the major construction
works were carried out at Section
4.5 Monitoring Methodology
Instrumentation
Integrating Sound Level Meters were employed for noise
monitoring.
Operation/Analysis Procedures
·
Sound Level Meter was set on a tripod
at a height of
·
For free field measurement, the meter
was positioned away from any nearby reflective surfaces.
·
The battery condition was checked to
ensure the correct functioning of the meter:
·
Parameters such as frequency weighting,
the time weighting and the measurement time were set as follows:
-
Frequency weighting : A
-
Time weighting :
Fast
-
Time measurement : 30 mins
·
Prior to and after each noise
measurement, the meter was calibrated using a Calibrator for 94 dB at
1000HZ. If the difference in the calibration
level before and after measurement was more than 1.0 dB(A), the measurement would be considered invalid and
repeat measurement would be required after re-calibration or repair of the
equipment;
·
During the monitoring period, the Leq, L10 and L90 were recorded.
In addition, site conditions and noise sources were recorded on a standard
record sheet;
·
3dB(A)
correction had been added to the results if noise measurements were free-field;
and
·
Noise monitoring would be cancelled in
the presence of fog, rain, storm, wind with a steady
speed exceeding
Maintenance and Calibration
·
The microphone head of the sound level
meter and calibrator are cleaned with soft cloth at quarterly intervals; and
·
The meters are sent to supplier or
HOKLAS laboratory to check and calibrated at yearly intervals.
4.6 Actions and Limit Levels
The Action and Limit Levels (AL Levels) were established in
accordance to the Table
4.3 of the EM&A Manual. Table 4.4 presents the
Table 4.3 Action and Limit
Levels for Noise Monitoring
Time
Period |
Action |
Limit |
0700
–1900 hrs on normal
weekday (Day-time) |
When one
documented complaint is received |
75 dB(A)
* |
1900-2300
hrs (Evening-time) |
70 dB(A) |
|
0700-1900 hrs on |
70 dB(A) |
|
Restricted hours (2300-0700 hrs of next day) (Night-time) |
55 dB(A) |
* reduce to 70dB(A) for school and 65dB(A) during school examination
periods
4.7 Event-Action Plans
Should the results of the
monitoring parameters at any designated monitoring stations indicate that the
noise level criteria are exceeded, the actions in
accordance with the Event and Action Plan that summarized in Appendix C should be carried out.
4.8 Results
4 occasions of Day-time noise monitoring
at noise monitoring
stations, LW02, MW02, WL01(R) and WL03 were
carried out at this reporting month.
No
Day-time noise monitoring results at all monitoring stations exceeded the Action Level
since no documented complaints on noise issue were received during the reporting period. Besides, no exceedances in Limit Level were recorded according to the
results from Day-time noise monitoring. Table 4.4 summaries the noise daytime monitoring results in the
reporting period.
Table 4.4 Summary of Impact Noise Monitoring Results
Monitoring
Parameter |
Date |
LW02 |
MW02 |
WL01(R) |
WL03 |
||||
Result |
Exceed* |
Result |
Exceed* |
Result |
Exceed* |
Result |
Exceed* |
||
Daytime |
05/02/14 |
57.2 |
X |
46.4 |
X |
45.9 |
X |
44.7 |
X |
12/02/14 |
56.7 |
X |
45.9 |
X |
45.9 |
X |
46.2 |
X |
|
19/02/14 |
56.7 |
X |
46.7 |
X |
45.9 |
X |
46.4 |
X |
|
26/02/14 |
56.7 |
X |
48.2 |
X |
46.3 |
X |
44.7 |
X |
Remark (*): L = Limit Level Exceedance, A = Action Level Exceedance
and X = not an
Exceedance
During this reporting month, weekly site inspections were undertaken on 05, 12, 19 and 26 February 2014 by ET. Monthly joint site
inspection at 12 February 2014 was carried out by IEC, CWE and ET. A summary of
implementation status of mitigation measures on
site inspections is presented in Appendix F.
5.1 Summary of the
ET weekly site
inspection findings
According
to the summary of the ET weekly site inspections carried out in February 2014, it
indicated that site practices of the Contractor were generally undertaken in an
environmentally acceptable manner and the overall site environmental
performance was satisfactory. Summaries of key findings of
weekly ET site inspections in
this month are described in Table 5.1.
Table 5.1 Key Findings of Weekly
ET Site
Inspections in this reporting month
Date |
Key
Findings |
Action(s) Taken
recommended by ET |
Action(s) Taken by the Contractor during the site audit |
Rectification Status by ET |
05 February
2014 |
Temporary stock piles without covers were observed in
the |
The Contractor was reminded to cover the stock piles
or spray with water in order to prevent dust emission. |
Temporary stock pile
without covered observed in the |
Closed |
Oil drum without drip tray was observed near Gate No.
69 at Lo Wu site. (Previous item) |
The Contractor was reminded to provide drip tray for
oil drum to avoid leakage of oil. |
Oil drum without drip tray observed in Lo Wu site was
removed. |
Closed |
|
12 February
2014 |
Rubbish was observed near Gate No. |
The Contractor was reminded to collect the rubbish
regularly to keep good site practices. |
--- |
Follow-up |
Oil drum without drip tray was observed near Gate No.
|
The Contractor was reminded to provide drip tray for
oil drum to avoid leakage of oil. |
--- |
Follow-up |
|
Rubbish was observed near Fence No. 127/Gate No. |
The Contractor was reminded to collect the rubbish
regularly to keep good site practices. |
--- |
Follow-up |
|
Oil drum without drip tray was observed near Fence
No. 129/Gate No |
The Contractor was reminded to provide drip tray for
oil drum to avoid leakage of oil. |
--- |
Follow-up |
|
Oil drum without drip tray was observed near Fence
No. 200/Gate No |
The Contractor was reminded to provide drip tray for
oil drum to avoid leakage of oil. |
--- |
Follow-up |
|
19 February
2014 |
Rubbish was observed near Gate No. |
The Contractor was reminded to collect the rubbish
regularly to keep good site practices. |
Rubbish observed near Gate No. |
Closed |
Oil drum without drip tray was observed near Gate No.
|
The Contractor was reminded to provide drip tray for
oil drum to avoid leakage of oil. |
Oil drum without drip tray observed near Gate No. |
Closed |
|
Rubbish was observed near Fence No. 127/Gate No. |
The Contractor was reminded to collect the rubbish
regularly to keep good site practices. |
Rubbish observed near Fence No. 127/Gate No. |
Closed |
|
Oil drum without drip tray was observed near Fence
No. 129/Gate No |
The Contractor was reminded to provide drip tray for
oil drum to avoid leakage of oil. |
Drip tray was provided for the oil drum near Fence No.
129/Gate No |
Closed |
|
Oil drum without drip tray was observed near Fence
No. 200/Gate No |
The Contractor was reminded to provide drip tray for
oil drum to avoid leakage of oil. |
Oil drum without drip tray observed near Fence No.
200/Gate No |
Closed |
|
26 February
2014 |
No observation / defective item was
recorded during the site inspection. |
5.2 Recommendations on site inspection
findings in Site Inspections of this month
Based
on the site inspection findings, the recommendations are as below:
· Minimize noise
impact due to construction works;
· Clean the access road regularly;
· Cover or water the stockpile;
· Checking
and maintaining all the site machines to prevent black smoke emission;
· Providing
briefing to the concerned site staff on remedial actions, such as handling
method of chemicals and chemical waste;
· Implement all necessary
preventive measures to avoid oil leakage. In the event an oil leakage happens,
the Contractor should properly remove the leaked oil and handle the
contaminated soil and all materials using for this cleaning works as chemical
waste;
·
Maintain good waste management at the site
· Remove all stagnant water; and
· Apply proper treatment facilities to wastewater before discharge.
6.0 Status
of Environmental Permits
Permits/licenses valid in this reporting month
are summarized in Table 6.1.
Table 6.1 Summary of Environmental Licensing and
Permit valid in this reporting month
Description |
Permit No. |
Valid Period |
Concerned Locations |
|
From |
To |
|||
Environmental Permit |
FEP-05/347/2009/A |
|
End of Project |
Section 3 – from Ng Tung River to |
Wastewater Discharge Licence |
W5/ |
|
|
Section |
Chemical Waste Producer |
5213-641-C1206-09 |
|
End of Project |
Section |
Notification under APCO |
Application
had been submitted to EPD on |
|||
Notification under WCO |
Application
had been submitted to EPD on |
7.0 Waste Management
7.1 Monthly
Waste Summary
The quantities of waste generated
from the Project in
this month are summarized in Table 7.1 and monthly
summary waste flow table present in Appendix H.
Table
7.1 Summary of Quantities of Waste generated in this reporting month
Type of Waste |
Quantity |
Cumulative Quantity from February 2013 |
|
Inert C&D Materials |
Total Quantity Generated (in ‘ |
0 |
0.238 |
Hard Rocks and Large Broken Concrete (in ‘ |
0 |
0.03 |
|
Reused in the Contract (in ‘ |
0 |
0 |
|
Reused in other Projects (in ‘ |
0 |
0 |
|
Disposal as Public Fill (in ‘ |
0 |
0.208 |
|
Imported Fill (in ‘ |
0.052 |
0.052 |
|
C&D Waste |
Metals (in ‘ |
0 |
0.02 |
Paper/Cardboard Packaging (in ‘ |
0.02 |
0.140 |
|
Plastics (in ‘ |
0 |
0 |
|
Chemical Waste (in
‘ |
0 |
0 |
|
Other, e.g. General Refuse (in ‘ |
0 |
0.9945 |
7.2 Advice on the
Solid and Liquid Waste Management Status
The Contractor
should provide sufficient preventive measures during equipment maintenance
works so as to avoid oil leakage on the ground. In the event of any oil
leakage, the Contractor should clean up the polluted soil and handle all the
materials used for this cleaning works as chemical waste.
Besides,
pre-cast drip trays were provided for oil drums at several areas, such as generator and chemical storage area. The Contractor should collect and
dispose of any stagnant water accumulated in the drip trays and handle them as
chemical waste.
The Contractor
should use suitable containers with proper labels to store chemical wastes in
accordance with Code of Practice on the Packaging, Labeling and Storage of
Chemical Waste. The Contractor should also advise their workers of the proper
procedures in handling the chemical waste.
All the trip
tickets for chemical waste disposal were properly kept in the site office. No
chemical waste disposal was undertaken in the reporting month.
The Contractor
was reminded to increase the frequency of inspection and cleaning of the site
drainage system, including desilting facilities. Moreover, the Contractor
should apply approved pesticides in the stagnant water.
8.0 Environmental Non-conformance
8.1 Summary of Non-Conformance
No exceedance
of Action and Limit Level
of noise monitoring was recorded in this reporting month.
8.2 Summary of
Environmental Complaints
No complaint was received in
this reporting month.
8.3 Summary of Notification of Summons and
Prosecution
There was no notification of summons respect to environmental
issues registered in this month.
9.1 Implementation
Status of Environmental Mitigation Measures
An updated summary of the
Environmental Mitigation Implementation Schedule (EMIS) is presented in
Appendix F. Most of the necessary
mitigation measures were implemented properly. Any deficiencies were noted in
the remarks of the schedule.
9.2 Implementation
Status of Event and Action Plan
No exceedance
of Action and Limit Level
of noise monitoring was recorded in this reporting month. Hence, no further action was required.
9.3 Implementation
Status of Environmental Complaint, Notifications of Summons and Successful
Prosecutions Handling
No complaint, notification of summons
and successful prosecution were received in this reporting month. A summary of
environmental complaints, notifications of summons and successful prosecutions
was given in Table 9.1.
Table 9.1 Summary of
Environmental Complaints and Prosecutions
Complaints logged |
Summons served |
Successful prosecution received |
|||
February 2014 |
Overall Cumulative
from February 2013 |
February 2014 |
Overall Cumulative
from February 2013 |
February 2014 |
Overall Cumulative
from February 2013 |
0 |
0 |
0 |
0 |
0 |
0 |
10.0 Comments, Conclusions and recommendations
Comments and Conclusions
Impact noise monitoring was carried out at
designated locations in accordance with the EM&A Manual in this reporting
month.
No exceedance of Action
and Limit Level of impact noise monitoring was recorded
in this reporting month.
According to
the ET weekly site inspections carried out in this reporting month, the
Contractor generally
implemented sufficient environmental mitigation measures.
No complaint, prosecution or notification of summon was received in
this reporting month.
Recommendations
According to the
environmental site inspections performed in the reporting month, the following
recommendations were provided:
Air Quality
§ Ensure the frequency of
water spraying on unloading areas and stockpiles to be sufficient to suppress
the dust sources;
§ Provide proper maintenance
for the powered mechanical equipment and barges to avoid emission of dark
smoke; and
§ Implement the dust
mitigation measures for the site activities.
Noise
§ Conduct noisy activities at
a farther location from the NSRs.
Water Quality
§ Provide proper treatment
for the wastewater discharge; and
§ Remove the stagnant water
or provide approved pesticides for the stagnant water, if any.
Chemical and Waste Management
§ Remove waste materials from
the site to avoid accumulation regularly;
§ Handle and store chemical
wastes properly;
§ Remove unwanted material in
the existing stockpiles and avoid further dumping of such material;
§ Provide and maintain
sufficient drip trays for diesel drums, chemical containers, chemical waste
storage drums and diesel operated generator set; and
§ Maintain good housekeeping
at the works
area..
11.0 Future Key
Issues
11.1 Work Programme for the Coming
Month
As informed by the Contractor, site activities proposed
to be carried out in
the coming
month:
§
Foundation;
§
Concrete
works;
§
Metal
works;
§
Backfilling
works; and
§
Installation
of metal works.
11.2 Key Issues for the Coming
Month
Key issues to
be considered in the coming month include:
·
Minimize noise impact due
to construction works;
·
Clean the
access road regularly;
·
Cover or
water the stockpile;
·
Checking and maintaining all the site
machines to prevent black smoke emission;
·
Providing briefing to the concerned site
staff on remedial actions, such as handling method of chemicals and chemical
waste;
·
Implement
all necessary preventive measures to avoid oil leakage. In the event an oil
leakage happens, the Contractor should properly remove the leaked oil and
handle the contaminated soil and all materials using for this cleaning works as
chemical waste;
·
Maintain good waste management at the site
·
Remove all stagnant water; and
·
Apply proper
treatment facilities to wastewater before discharge.
Mitigation measures to be required in the coming month:
Air Quality Impact
§ To ensure
implementation of the dust mitigation measures for the site activities;
§ To provide
proper maintenance for vehicles and machines on site; and
§ To investigate
any other dust sources around the air sensitive receivers
Noise
§ To switch off
equipment if not in use;
§ To operate
silent equipment; and
§ To re-schedule
the work activities in the event of valid noise exceedance.
Water Quality Impact
§ To maintain the
drainage system;
§ To provide
covers for the drip trays to avoid stagnant water due to rainfall;
§ To provide
proper treatment for wastewater from the area; and
§ To avoid any
stagnant water or provide insecticide to avoid mosquito breeding.
Chemical and Waste
Management
§ To remove waste
from the site regularly;
§ To properly
store and handle chemical wastes on site;
§ To provide and
manage sufficiently sized drip trays for diesel drums or chemical containers;
§ To maintain
proper housekeeping;
§ To remove the
oil stains in the event of leakage and handle all materials using for this
cleaning works as chemical waste; and
§ To identify
C&D material by packaging, labeling, storage, transportation and disposal
in accordance with statutory regulations.
- END OF
REPORT -