1.1 Purpose of the Report
1.2 Structure of the Report
2.1 Background
2.2 General Site Description
2.3 Construction Programme and Activities
2.4 Project Organisation
2.5 Status of Environmental Licences, Notification and Permits
3 Environmental
Monitoring Requirement
3.1 Water Quality Monitoring
4 Implementation
Status of The environmental protection requirements
5.1 Waste Management
6 Environmental
Site Inspection
7 Environmental
Non-conformance
7.1 Summary of Monitoring Exceedance
7.2 Summary of environmental non-compliance
7.3 Summary of Environmental Complaint
7.4 Summary of Environmental Summon and successful prosecution
LIST OF ANNEXES
EXECUTIVE SUMMARY
The construction works of CCGT Unit No. 1 of the Additional Gas-fired Generation Units
Project at the Black Point Power Station
commenced on 5 December 2016. This is the second quarterly Environmental
Monitoring and Audit (EM&A) report presenting the EM&A works carried
out during the period from 1 March 2017 to 31 May 2017 in accordance with the EM&A Manual and the requirements of EP-507/2016 and
FEP-01/507/2016.
Summary of the Construction Works undertaken during the Reporting Period
The major construction works undertaken during the reporting period
include:
Construction Activities undertaken |
l
Piling works; l
Demolition of
warehouse; l
A&A (building)
works of warehouse; and l
Excavation
and lateral support for drainage works |
Environmental Site Inspection
Joint
weekly site inspections were conducted by representatives of the Contractor,
CAPCO Project Team and ET on 2, 9, 16, 23 and 30 March; 6, 13, 20
and 27 April; and 4, 11, 18
and 25 May 2017. The representative of
the IEC joined the site inspections on
16 March, 20
April and 18
May 2017. Details of the audit findings and
implementation status are presented in Section 6.
Environmental Exceedance/Non-conformance/Complaint/Summons and
Prosecution
No non-compliance event was recorded during the reporting period.
No complaint was received during the reporting period.
No
summon or prosecution was received in this reporting period.
The
Castle Peak Power Company Limited (CAPCO) is a joint venture between CLP Power
Hong Kong Limited (CLP) and China Southern Power Grid Company Limited with CLP
as the operator. ERM-Hong Kong, Limited (ERM) and Mott MacDonald Hong Kong Limited was appointed
by CAPCO as the Environmental Team (ET) and the Independent Environmental Checker (IEC),
respectively, to undertake the Environmental Monitoring and Audit (EM&A)
activities for the installation of CCGT Unit No. 1 of the Additional Gas-fired Generation Units Project at the Black Point Power
Station (BPPS) (“the Project”).
This is the second quarterly EM&A report which
summarises the audit findings during the reporting period from 1 March 2017 to
31 May 2017.
Section
1 : Introduction
It details the purpose and structure of the report.
Section
2 : Project
Information
It summarises the background and scope of the project, site
description, project organisation and contact details, construction programme, construction
works undertaken and status of the Environmental Permits/Licenses during the
reporting period.
Section
3 : Environmental
Monitoring Requirement
It briefly introduces the environmental monitoring requirements
for the Project.
Section
4 : Implementation
Status of the Environmental Protection
Requirements
It summarises the implementation of environmental protection
measures during the reporting period.
Section
5 : Monitoring
Results
It summarises the monitoring results obtained in the reporting period.
Section
6 : Environmental
Site Inspection
It summarises the audit findings of the weekly site inspections
undertaken within the reporting period.
Section
7 : Environmental
Non-conformance
It summarises any monitoring exceedance, environmental complaints
and summons within the reporting period.
Section 8 : Conclusions
The scope of the Project involves the
phased construction and operation of up to two additional combined cycle gas turbine
(CCGT) units (with an installed capacity of up to 600 MW each) at the
BPPS. The additional generation units
will be of CCGT configuration using natural gas as the primary fuel. It is a Designated Project under the Environmental Impact Assessment Ordinance
(Cap. 499) (EIAO). The
current EM&A
Programme only includes the CCGT Unit No. 1.
An
EIA of the Additional Gas-fired Generation Units Project was prepared in
accordance with the EIA Study Brief (No. ESB-286/2015) and the Technical
Memorandum of the Environmental Impact Assessment Process (EIAO-TM)
and submitted under the EIAO in February 2010.
Subsequent to the approval of the EIA (EIAO Register Number
AEIAR-197/2016), an Environmental Permit (EP-507/2016) (EP) for CCGT Unit
No. 1 was granted by the Director of Environmental Protection (DEP) on 14 June
2016. A Further Environmental Permit
(FEP-01/507/2016) (FEP) was granted to the Contractor, Chun Wo
Foundations Limited, of the CCGT Unit No. 1 on 9 December 2016.
The proposed location for the Project is
within the existing boundaries of the BPPS site. The size of the land reserved for the
additional generation units and the associated facilities (the Project Site) is
about 40,000 m2. Construction
works for CCGT Unit No. 1 is currently ongoing at the Project Site.
The works area for the Project is shown in
Annex A.
A summary of the major construction activities undertaken in this reporting
period is shown in Table 2.1.
The construction programme is presented in Annex B.
Table 2.1 Summary of the Construction
Activities Undertaken during the Reporting Period
Construction
Activities undertaken |
l
Piling works; l
Demolition of
warehouse; l
A&A
(building) works of warehouse; and l
Excavation and
lateral support for drainage works |
The project organizational chart and contact
details are shown in Annex
C.
A summary of the valid permits, licences,
and/or notifications on environmental protection for this Project during the
reporting period is presented in Table 2.2.
Table 2.2 Summary of the Status of Valid Environmental Licence,
Notification, Permit and Documentations
Permit/ Licences/ Notification |
Reference |
Validity Period |
Remarks |
Environmental Permit |
EP-507/2016 |
Throughout the Contract |
Permit granted on 14 Jun 2016 |
Further Environmental Permit |
FEP-01/507/2016 |
Throughout the Contract |
Permit granted on 9 Dec 2016 |
Notification Pursuant
to Section 3(1) of the Air Pollution Control (Construction Dust)
Regulation |
410023 |
Throughout the Contract |
Notification received on 15 Nov 2016 |
Wastewater
Discharge Licence |
WT00026627-2016 |
To 31 Jan 2022 |
Licence granted on 13 Jan 2017 |
Chemical Waste
Producer Registration |
5213-432-C3243-13 |
Throughout the Contract |
Registration approved on 9 Jan 2017 |
Billing
Account for Disposal of Construction Waste |
7026814 |
Throughout the Contract |
Approved on 30 Dec 2016 |
Construction
Noise Permit |
GW-RW0039-17 |
3 Feb 2017 – 31 Jul 2017 |
Permit granted on 1 Feb 2017 |
|
PP-RW0001-17 |
6 Feb 2017 – 5 Aug 2017 |
Permit granted on 3 Feb 2017 |
In accordance with the EM&A Manual, monitoring works is required at a
frequency of once per week on first year of commissioning of the CCGT Unit No.1. The monitoring details including monitoring requirement, locations of monitoring stations will be confirmed and approved by EPD before commissioning of the CCGT Unit No.1.
The Contractor has implemented all the environmental mitigation measures
and requirements as stated in the EIA Report, Environmental Permit (EP) and
EM&A Manual for the installation of CCGT Unit No.1. The mitigation measures recommended in the
EIA report and required by the EP are considered effective in minimising environmental
impacts. The implementation status of
the environmental mitigation measures for this Works Contract during the
reporting period is summarised in Annex D.
The status of the required submissions under the EP for the
Project during the reporting period is presented in Table 4.1.
Table 4.1 Status of Required Submissions
under the Project
EP Condition |
Submission |
Submission Date |
EM&A
Manual (AEIAR-197/2016) |
1st Quarterly EM&A Report |
11 April |
Condition 3.2 under Environmental Permit |
4th Monthly EM&A Report |
11 April 2017 |
5th Monthly EM&A Report |
8 May 2017 |
|
6th Monthly EM&A Report |
12 June 2017 |
The waste generated from this Project includes inert construction
and demolition (C&D) materials, and non-inert C&D materials. Non-inert C&D materials are made up of general
refuse and recyclable wastes such as plastics and paper/cardboard packaging
waste. Steel materials generated from
the project are also grouped into non-inert C&D materials as the materials
were not disposed of with other inert C&D materials.
With reference
to relevant handling records and trip tickets of this Project, the quantities
of different types of waste generated in the reporting period are summarised in
Table 5.1. Details of
waste management data are presented in Annex E.
Table 5.1 Quantities of Waste Generated from the
Project
Reporting Month |
Quantity |
|||||
Inert C&D Materials (a) (b) |
Chemical Waste (d) |
Non-inert C&D Materials |
||||
General
Refuse (c) |
Recycled materials |
|||||
Paper/cardboard |
Plastics |
Metals |
||||
|
in
'000m3 |
in
'000 kg |
in
'000m3 |
in
'000 kg |
in
'000 kg |
in
'000 kg |
March
2017 |
5.285 |
0 |
0.001 |
0.004 |
0.003 |
44.552 |
April
2017 |
0.720 |
0 |
0.022 |
0 |
0 |
22.160 |
May
2017 |
0 |
0 |
0.003 |
0 |
0 |
31.750 |
Total |
6.005 |
0
|
0.026 |
0.004 |
0.003 |
98.462 |
Notes: (a) Inert
C&D materials include bricks, concrete, building debris, rubble and
excavated spoil. (b) The
inert C&D materials generated from the Project was sent to Tuen Mun Area 38 Fill Bank
during the reporting period. (c) General
refuse generated from the Project was sent to WENT
landfill during the reporting period. (d)
Chemical waste includes waste oil.
It is assumed density of waste oil to be 0.8 kg/L. |
The estimated amount of waste generated from the
Project predicted by EIA Report and the actual cumulative quantities of waste
generated from the construction phase of the Project during the reporting period
are presented in Table 5.2. Mitigation measures recommended in EIA Report
were implemented by the Contractor as far as practicable and were considered
effective in reducing the total quantity of wastes generated during the
reporting period.
Table
5.2 Comparison of
Estimated Amount of Waste
Generated for Construction of CCGT Unit No.1 and Actual Amount Generated during
the Reporting Period
Type of
Material |
Estimated
Amount for Project |
Actual
Amount during Reporting Period |
Total Amount of Inert C&D Materials
disposed as Public Fill (a) (in
'000m3) |
80.96 |
6.005 |
Amount of Inert C&D Materials Reused in
the Contract (in '000m3) |
8.89 |
0.048 |
Amount of Inert C&D Materials Reused in
Other Projects (in '000m3) |
- |
0 |
Total Amount of Non-Inert C&D Materials
and General Refuse disposed at WENT Landfill (b) |
1.522 |
0.026 |
Chemical Waste (c) |
10.20 |
0 |
Notes: (a) Inert
C&D materials include site clearance waste, excavated materials, building
works generated from construction of
CCGT
Unit No.1 for the entire project. (b) Non-inert
C&D materials include site clearance waste, excavated materials, building
works generated from construction period of
CCGT
Unit No.1 for the entire project. The amount of general refuse was estimated
780 kg per day for construction of
CCGT
Unit No.1. There are 72 working days in the reporting period. (c) The
total amount of chemical waste was estimated 3,400 kg per month. There are 3
months in the reporting period. |
Joint weekly site
inspections were conducted by representatives of the Contractor, CAPCO Project
Team and ET on 2, 9, 16, 23 and 30 March; 6, 13, 20
and 27 April;
and 4, 11, 18 and 25 May 2017. The representative of the IEC joined the site
inspections on 16 March, 20
April and 18 May 2017. No non-compliance
was recorded during the site inspections.
Findings and recommendations
for the site inspections in this reporting period are summarised as follows:
2 March 2017
· There were no major observations.
9 March 2017
· There were no major observations.
16 March 2017
· There were no major observations.
Regarding the planter audit, CAPCO was recommended to:
· keep close monitoring on BPT932; and
· remove
guying wires from tree trunk of BPT942.
23 March 2017
The Contractor was reminded to:
· provide a drip tray underneath the air compressor;
· dispose
of the oily mud as chemical waste with a proper chemical label and temporarily
stored in the chemical waste storage before disposal.
30 March 2017
· The Contractor was reminded to cover the stockpiles of dusty materials
properly.
6 April 2017
· There were no major observations.
13 April 2017
· There were no major observations.
20 April 2017
· There were no major observations.
Regarding the planter audit, CAPCO was recommended to:
· remove
epiphytes from BPT764.
27 April 2017
· There were no major observations.
4 May 2017
· There were no major observations.
11 May 2017
· There were no major observations.
18 May 2017
· There were no major observations.
Regarding the planter audit, CAPCO was recommended to:
· remove the shrubs from the planters as far as possible;
· conduct close monitoring for BPT800 and BPT946;
· remove the parasitic vine, Cassytha filiformis, from BPT771; and
· remove
the broken branch from BPT768 due to safety reason.
25 May 2017
· There were no major observations.
All follow-up actions
requested by ET and IEC during the site inspections were undertaken as
reported by CAPCO and the Contractor.
The abovementioned environmental issues had been addressed and mitigated
during the reporting period.
No environmental monitoring is required
during construction of CCGT Unit No. 1.
No non-compliance event was recorded during the reporting period.
No environmental complaint was received during the reporting
period.
No summon or prosecution was received during the
reporting period.
This
second quarterly Environmental Monitoring
and Audit (EM&A) Report presents the EM&A works undertaken during the
period from 1 March 2017 to 31 May 2017 in accordance with the EM&A Manual and the requirements of EP-507/2016 and
FEP-01/507/2016.
No non-compliance event was recorded during the reporting period.
No environmental complaint, summon
or prosecution was received during the reporting period.
The Contractor has implemented possible and feasible mitigation
measures to mitigate the potential environmental impacts during construction. The ET will continue to keep track of the
EM&A programme to ensure compliance of environmental requirements and the
effectiveness and efficiency of the mitigation measures implemented. If necessary, the Contractor will provide
more mitigation measures to further alleviate the impacts.