Contents

1                      Introduction                                                                          

1.1                   Purpose of the Report                                                     

1.2                   Structure of the Report                                                

2                      Project Information                                                          

2.1                   Background                                                                           

2.2                   General Site Description                                                

2.3                   Construction Programme and Activities               

2.4                   Project Organisation                                                       

2.5                   Status of Environmental Licences, Notification and Permits      

3                      Environmental Monitoring Requirement                

3.1                   Water Quality Monitoring                                              

4                      Implementation Status of The environmental protection requirements 

5                      Monitoring Results                                                            

5.1                   Waste Management                                                             

6                      Environmental Site Inspection                                     

7                      Environmental Non-conformance                             

7.1                   Summary of Monitoring Exceedance                         

7.2                   Summary of environmental non-compliance        

7.3                   Summary of Environmental Complaint                    

7.4                   Summary of Environmental Summon and successful prosecution     

8                      Conclusions                                                                           

LIST OF ANNEXES

Annex A

Works Area for installation of CCGT Unit No. 1 at the Black Point Power Station

Annex B

Construction Programme for the Reporting Period and Coming Months

Annex C

Project Organization for EM&A Implementation

Annex D

Summary of Implementation Status of Environmental Mitigation

Annex E

Waste Flow Table

 

EXECUTIVE SUMMARY

The construction works of CCGT Unit No. 1 of the Additional Gas-fired Generation Units Project at the Black Point Power Station commenced on 5 December 2016.  This is the second quarterly Environmental Monitoring and Audit (EM&A) report presenting the EM&A works carried out during the period from 1 March 2017 to 31 May 2017 in accordance with the EM&A Manual and the requirements of EP-507/2016 and FEP-01/507/2016.

Summary of the Construction Works undertaken during the Reporting Period

The major construction works undertaken during the reporting period include:

Construction Activities undertaken

l  Piling works;

l  Demolition of warehouse;

l  A&A (building) works of warehouse; and

l  Excavation and lateral support for drainage works

Environmental Site Inspection

Joint weekly site inspections were conducted by representatives of the Contractor, CAPCO Project Team and ET on 2, 9, 16, 23 and 30 March; 6, 13, 20 and 27 April; and 4, 11, 18 and 25 May 2017.  The representative of the IEC joined the site inspections on 16 March, 20 April and 18 May 2017.  Details of the audit findings and implementation status are presented in Section 6.

Environmental Exceedance/Non-conformance/Complaint/Summons and Prosecution

No non-compliance event was recorded during the reporting period.

No complaint was received during the reporting period.

No summon or prosecution was received in this reporting period.

 

1                                          Introduction

The Castle Peak Power Company Limited (CAPCO) is a joint venture between CLP Power Hong Kong Limited (CLP) and China Southern Power Grid Company Limited with CLP as the operator.  ERM-Hong Kong, Limited (ERM) and Mott MacDonald Hong Kong Limited was appointed by CAPCO as the Environmental Team (ET) and the Independent Environmental Checker (IEC), respectively, to undertake the Environmental Monitoring and Audit (EM&A) activities for the installation of CCGT Unit No. 1 of the Additional Gas-fired Generation Units Project at the Black Point Power Station (BPPS) (“the Project”). 

1.1                                    Purpose of the Report

This is the second quarterly EM&A report which summarises the audit findings during the reporting period from 1 March 2017 to 31 May 2017.

1.2                                    Structure of the Report

Section 1 :      Introduction

It details the purpose and structure of the report.

 

Section 2 :      Project Information

It summarises the background and scope of the project, site description, project organisation and contact details, construction programme, construction works undertaken and status of the Environmental Permits/Licenses during the reporting period.

 

Section 3 :      Environmental Monitoring Requirement

It briefly introduces the environmental monitoring requirements for the Project.

 

Section 4 :      Implementation Status of the Environmental Protection  Requirements

It summarises the implementation of environmental protection measures during the reporting period.

 

Section 5 :      Monitoring Results

It summarises the monitoring results obtained in the reporting period.

 

Section 6 :      Environmental Site Inspection

It summarises the audit findings of the weekly site inspections undertaken within the reporting period.

 


Section 7 :      Environmental Non-conformance

It summarises any monitoring exceedance, environmental complaints and summons within the reporting period.

 

 

Section 8 :      Conclusions

2                                          Project Information

2.1                                    Background

The scope of the Project involves the phased construction and operation of up to two additional combined cycle gas turbine (CCGT) units (with an installed capacity of up to 600 MW each) at the BPPS.  The additional generation units will be of CCGT configuration using natural gas as the primary fuel.  It is a Designated Project under the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO).  The current EM&A Programme only includes the CCGT Unit No. 1.

An EIA of the Additional Gas-fired Generation Units Project was prepared in accordance with the EIA Study Brief (No. ESB-286/2015) and the Technical Memorandum of the Environmental Impact Assessment Process (EIAO-TM) and submitted under the EIAO in February 2010.  Subsequent to the approval of the EIA (EIAO Register Number AEIAR-197/2016), an Environmental Permit (EP-507/2016) (EP) for CCGT Unit No. 1 was granted by the Director of Environmental Protection (DEP) on 14 June 2016.  A Further Environmental Permit (FEP-01/507/2016) (FEP) was granted to the Contractor, Chun Wo Foundations Limited, of the CCGT Unit No. 1 on 9 December 2016.

2.2                                    General Site Description 

The proposed location for the Project is within the existing boundaries of the BPPS site.  The size of the land reserved for the additional generation units and the associated facilities (the Project Site) is about 40,000 m2.  Construction works for CCGT Unit No. 1 is currently ongoing at the Project Site.

The works area for the Project is shown in Annex A.

2.3                                    Construction Programme and Activities

A summary of the major construction activities undertaken in this reporting period is shown in Table 2.1.  The construction programme is presented in Annex B.

Table 2.1        Summary of the Construction Activities Undertaken during the Reporting Period

Construction Activities undertaken

l    Piling works;

l    Demolition of warehouse;

l    A&A (building) works of warehouse; and

l    Excavation and lateral support for drainage works

2.4                                    Project Organisation

The project organizational chart and contact details are shown in Annex C.

2.5                                    Status of Environmental Licences, Notification and Permits

A summary of the valid permits, licences, and/or notifications on environmental protection for this Project during the reporting period is presented in Table 2.2.

Table 2.2        Summary of the Status of Valid Environmental Licence, Notification, Permit and Documentations

Permit/ Licences/ Notification

Reference

Validity Period

Remarks

Environmental Permit

 

EP-507/2016

Throughout the Contract

Permit granted on 14 Jun 2016

 

Further Environmental Permit

 

FEP-01/507/2016

Throughout the Contract

Permit granted on 9 Dec 2016

Notification Pursuant to Section 3(1) of the Air  Pollution Control (Construction Dust) Regulation

410023

Throughout the Contract

Notification received on 15 Nov 2016

Wastewater Discharge Licence

WT00026627-2016

To 31 Jan 2022

Licence granted on 13 Jan 2017

Chemical Waste Producer Registration

5213-432-C3243-13

Throughout the Contract

Registration approved on 9 Jan 2017

Billing Account for Disposal of Construction Waste

7026814

Throughout the Contract

Approved on 30 Dec 2016

Construction Noise Permit

GW-RW0039-17

3 Feb 2017 – 31 Jul 2017

Permit granted on 1 Feb 2017

 

PP-RW0001-17

6 Feb 2017 – 5 Aug 2017

Permit granted on 3 Feb 2017

3                                          Environmental Monitoring Requirement

3.1                                    Water Quality Monitoring

In accordance with the EM&A Manual, monitoring works is required at a frequency of once per week on first year of commissioning of the CCGT Unit No.1.  The monitoring details including monitoring requirement, locations of monitoring stations will be confirmed and approved by EPD before commissioning of the CCGT Unit No.1.

 

 

4                                          Implementation Status of The environmental protection requirements

The Contractor has implemented all the environmental mitigation measures and requirements as stated in the EIA Report, Environmental Permit (EP) and EM&A Manual for the installation of CCGT Unit No.1.  The mitigation measures recommended in the EIA report and required by the EP are considered effective in minimising environmental impacts.  The implementation status of the environmental mitigation measures for this Works Contract during the reporting period is summarised in Annex D. 

The status of the required submissions under the EP for the Project during the reporting period is presented in Table 4.1. 

Table 4.1        Status of Required Submissions under the Project

EP Condition

Submission

Submission Date

EM&A Manual (AEIAR-197/2016)

1st Quarterly EM&A Report

11 April

Condition 3.2 under Environmental Permit
No. EP-507/2016 and
FEP-01/507/2016

4th Monthly EM&A Report

11 April 2017

5th Monthly EM&A Report

8 May 2017

6th Monthly EM&A Report

12 June 2017

 

5                                          Monitoring Results

5.1                                    Waste Management

The waste generated from this Project includes inert construction and demolition (C&D) materials, and non-inert C&D materials.  Non-inert C&D materials are made up of general refuse and recyclable wastes such as plastics and paper/cardboard packaging waste.  Steel materials generated from the project are also grouped into non-inert C&D materials as the materials were not disposed of with other inert C&D materials. 

With reference to relevant handling records and trip tickets of this Project, the quantities of different types of waste generated in the reporting period are summarised in Table 5.1.  Details of waste management data are presented in Annex E.

Table 5.1    Quantities of Waste Generated from the Project

Reporting Month

Quantity

Inert C&D Materials (a) (b)

Chemical Waste (d)

Non-inert C&D Materials

General Refuse (c)

Recycled materials

Paper/cardboard

Plastics

Metals

 

in '000m3

in '000 kg

in '000m3

in '000 kg

in '000 kg

in '000 kg

March 2017

5.285

0

0.001

0.004

0.003

44.552

April 2017

0.720

0

0.022

0

0

22.160

May 2017

0

0

0.003

0

0

31.750

Total

6.005

0

0.026

0.004

0.003

98.462

Notes:

(a)      Inert C&D materials include bricks, concrete, building debris, rubble and excavated spoil. 

(b)      The inert C&D materials generated from the Project was sent to Tuen Mun Area 38 Fill Bank during the reporting period.

(c)      General refuse generated from the Project was sent to WENT landfill during the reporting period.

(d)      Chemical waste includes waste oil.  It is assumed density of waste oil to be 0.8 kg/L.

The estimated amount of waste generated from the Project predicted by EIA Report and the actual cumulative quantities of waste generated from the construction phase of the Project during the reporting period are presented in Table 5.2.  Mitigation measures recommended in EIA Report were implemented by the Contractor as far as practicable and were considered effective in reducing the total quantity of wastes generated during the reporting period.

Table 5.2        Comparison of Estimated Amount of Waste Generated for Construction of CCGT Unit No.1 and Actual Amount Generated during the Reporting Period

Type of Material

Estimated Amount for Project 

Actual Amount during Reporting Period

Total Amount of Inert C&D Materials disposed as Public Fill (a) (in '000m3)

80.96

6.005

Amount of Inert C&D Materials Reused in the Contract (in '000m3)

8.89

0.048

Amount of Inert C&D Materials Reused in Other Projects (in '000m3)

-

0

Total Amount of Non-Inert C&D Materials and General Refuse disposed at WENT Landfill (b)
(
in '000m3)

1.522

0.026

Chemical Waste (c)
(in ''000kg)

10.20

0

Notes:

(a)      Inert C&D materials include site clearance waste, excavated materials, building works generated from construction of CCGT Unit No.1 for the entire project.  

(b)      Non-inert C&D materials include site clearance waste, excavated materials, building works generated from construction period of CCGT Unit No.1 for the entire project. The amount of general refuse was estimated 780 kg per day for construction of CCGT Unit No.1. There are 72 working days in the reporting period.

(c)      The total amount of chemical waste was estimated 3,400 kg per month. There are 3 months in the reporting period.

 

6                                          Environmental Site Inspection

Joint weekly site inspections were conducted by representatives of the Contractor, CAPCO Project Team and ET on 2, 9, 16, 23 and 30 March; 6, 13, 20 and 27 April; and 4, 11, 18 and 25 May 2017.  The representative of the IEC joined the site inspections on 16 March, 20 April and 18 May 2017.  No non-compliance was recorded during the site inspections.

Findings and recommendations for the site inspections in this reporting period are summarised as follows:

2 March 2017

·      There were no major observations.

9 March 2017

·      There were no major observations.

16 March 2017

·      There were no major observations.

Regarding the planter audit, CAPCO was recommended to:

·      keep close monitoring on BPT932; and

·      remove guying wires from tree trunk of BPT942.

23 March 2017

The Contractor was reminded to:

·      provide a drip tray underneath the air compressor;

·      dispose of the oily mud as chemical waste with a proper chemical label and temporarily stored in the chemical waste storage before disposal.

30 March 2017

·      The Contractor was reminded to cover the stockpiles of dusty materials properly.

6 April 2017

·      There were no major observations.

13 April 2017

·      There were no major observations.

20 April 2017

·      There were no major observations.

Regarding the planter audit, CAPCO was recommended to:

·      remove epiphytes from BPT764.

27 April 2017

·      There were no major observations.

4 May 2017

·      There were no major observations.

11 May 2017

·      There were no major observations.

18 May 2017

·      There were no major observations.

Regarding the planter audit, CAPCO was recommended to:

·      remove the shrubs from the planters as far as possible;

·      conduct close monitoring for BPT800 and BPT946;

·      remove the parasitic vine, Cassytha filiformis, from BPT771; and

·      remove the broken branch from BPT768 due to safety reason.

25 May 2017

·      There were no major observations.

All follow-up actions requested by ET and IEC during the site inspections were undertaken as reported by CAPCO and the Contractor.  The abovementioned environmental issues had been addressed and mitigated during the reporting period.

7                                          Environmental Non-conformance

7.1                                    Summary of Monitoring Exceedance

No environmental monitoring is required during construction of CCGT Unit No. 1.

7.2                                    Summary of environmental non-compliance

No non-compliance event was recorded during the reporting period.

7.3                                    Summary of Environmental Complaint

No environmental complaint was received during the reporting period.

7.4                                    Summary of Environmental Summon and successful prosecution

No summon or prosecution was received during the reporting period.

8                                          Conclusions

This second quarterly Environmental Monitoring and Audit (EM&A) Report presents the EM&A works undertaken during the period from 1 March 2017 to 31 May 2017 in accordance with the EM&A Manual and the requirements of EP-507/2016 and FEP-01/507/2016.

No non-compliance event was recorded during the reporting period.

No environmental complaint, summon or prosecution was received during the reporting period.

The Contractor has implemented possible and feasible mitigation measures to mitigate the potential environmental impacts during construction.  The ET will continue to keep track of the EM&A programme to ensure compliance of environmental requirements and the effectiveness and efficiency of the mitigation measures implemented.  If necessary, the Contractor will provide more mitigation measures to further alleviate the impacts.