Construction of Yuen Long Bypass Floodway
Environmental Impact Monitoring
Exceedance Summary
Date |
Station |
Parameter |
Measurement
Result |
Compliance
Level |
Level
exceeded |
Exceedance
due to Project |
15 August 06 |
W1 |
DO |
3.8 mg/L |
>
4 mg/L |
Compliance |
No |
(a) Statement of exceedance |
The DO level at Station W1
did not complied with the Compliance level. |
(b) Causes of
exceedance |
According to our field observation, the non-compliance
was due
to natural fluctuation of water quality at ·
There was no construction activity adjacent to the station during
monitoring. ·
The measured DO level was within the range recorded in the baseline
monitoring, i.e. 2.2 to 9.4mg/L |
(c) Action
required under the action plan |
N/A |