Appendix
M - Complaint Log
Log
Ref. |
Location |
Received
Date |
Details
of Complaint |
Investigation/Mitigation
Action |
Status |
30825-1 |
Fish Pond No. 9 |
25 Aug 03 |
EPD received a complaint about the malodour emitted from dead fishes at ponds due to the Project
on The complaint was concerning malodour
emitted from fish ponds next to Hung Mo Kiu on |
The ET contacted the complaint on Information about the complaint was sent to the
Contractor on The Contractor confirmed that the malodour was generated from pond No. 9 which is close to
the The ET had carried out a site investigation on |
Closed |
40112_16 |
Kong Tau Tsuen |
12 Jan 04 16 Jan 04 |
EPD Ref.: EP3/N06/TW/1118-04 On 3rd, 5th, 10th
and 15th January 2004, the EPD received a total of four
environmental complaints about the dust nuisance produced from the site of
the Project at Kong Tau Tsuen.
The EPD referred the complaints to the IEC on 10th and The investigation report was submitted to EPD on |
According to IEC’s weekly
site audit and ET’s monthly site audit in the concerned periods, no air
quality violation was observed. Kong Tau Tsuen itself is a designated dust monitoring station.
Regular dust monitoring were conducted on 3rd,
5th, 6th, 9th, 12th, 13th,
15th and 16th January 2004. Although 1-hr TSP Action
Level exceedances were recorded on 5th
and The 1-hr TSP Limit Level exceedance
on |
Closed |
40113 |
Tai Shu Ha Road West |
13 Jan 04 |
On The investigation report was submitted to EPD on |
For the 1-hr TSP monitoring on According to IEC’s weekly
site audit and ET’s monthly site audit in the concerned periods, no air
quality violation was observed. According to Contractor’s investigation and ET’s
monthly site audit, There is also no evidence showing that the parked
dump truck as complained was from the Project “Widening of Yuen Long Highway”
or the captioned Project. The exhaust gas emission might due to road traffic
at |
Closed |
40116 |
|
16 Jan 04 |
EPD Ref.: EP3/N06/TW/771-04 On The investigation report was submitted to EPD on |
For the 1-hr TSP monitoring on According to IEC’s weekly
site audit and ET’s monthly site audit in the concerned periods, no air
quality violation was observed. Although lack of wheel washing facilities and dust
emission were observed by EPD on |
Closed |
40205 |
Kong Tau Tsuen |
5 Feb 04 |
EPD Ref.: EP3/N06/TW/2050-04 On The complaint was about the noise nuisance produced
from loading/unloading activities by the lorries at the construction site.
The complainant indicated that such noise problem had happened between The investigation report was submitted to EPD on |
According to the information provided by the
Contractor, there was no construction activity on the site in the duration as
mentioned by the complainant. Instead, all of the construction activities
were limited in the period of |
Closed |
40206 |
|
6 Feb 04 |
EPD Ref.: EP3/N06/TW/2034-04 On The investigation report was submitted to EPD on |
According to the information provided by the
Contractor, the construction site of “Pok Oi Hospital Extension” is located adjacent to the
captioned project. There is no clear indication of the muddy effluent
discharge from which construction site. Since there was no clear evidence indicating that
the muddy effluent was came from the Project, the ET and the Contractor has
concluded that the effluent might not be due to the Project. In order to
prevent the discharge of muddy effluent to public roads, the Contractor has
employed a full-time labour to clean the site exit
at |
Closed |
40216 |
|
16 Feb 04 |
EPD Ref.: EP3/N06/TW/2622-04 On The investigation report was submitted to EPD on |
According to the site investigation by IEC and ET on
|
Closed |
40309 |
Sheung Yau Tin Tsuen |
9 Mar 04 |
EPD Ref.: EP3/N06/TW/4574-04 On The investigation report was submitted to EPD on |
The Contractor has agreed with the complainant, Mr.
Lam, and the following mitigation measures are applied:- ·
Routing
of dump trucks is separated from the village access in order to minimize the
dust nuisance to villagers; ·
Frequency
of water spraying at both haul road and village access is increased; ·
Labours are employed to clear the muddy water; and ·
Wheel
washing facilities are provided at the site entrance. |
Closed |
40316 |
Kong Tau Tsuen |
16 Mar 04 |
EPD Ref.: EP3/N06/TW/5044-04 On The investigation report was submitted to EPD on |
Based on the information provided by the Contractor,
the frequency of water spraying was increased in early morning times. According to ET’s site inspection, no violation of
air quality was observed at Kong Tau Tsuen. No dust exceedance was
recorded during regular monitoring. The ET concluded that the dust nuisance was
rectified and no further action is required. |
Closed |
40326_29 |
|
26 Mar 04 29 Mar 04 |
EPD Ref.: EP3/N06/TW/6015-04; and EP3/N06/TW/6076-04 On 25th and The investigation report was submitted to EPD on |
Based on the information provided the Contractor,
concreting works were carried out on that period. Some vehicles leaving the
site may cause dust nuisance during a short period of time. A full-time labour has been employed for wheel washing works at the
site exit and a water truck would be used to clean the road surface if
necessary. The Contractor has implemented mitigation measures
and no dust nuisance was observed in the ET’s latest site investigation. |
Closed |
40507 |
Chuk San Tsuen |
7 May 04 |
EPD Ref.: EP3/N06/TW/6649-04 On The investigation report was submitted to EPD on |
Based on the information provided by the Contractor,
the situation was due to a heavy rainstorm on the complaint date. A large
volume of surface runoff flowed from upstream of the construction site, passing
through an unpaved area and discharge to Chuk San Tsuen. The situation was rectified on the next day. The Contractor has already provided all possible
treatment facilities in order to prevent muddy water discharge. The captioned
complaint is concluded as an exceptional incidence due to heavy rainstorm. |
Closed |
40615 |
Yeung |
15 Jun 04 |
EPD Ref.: EP3/N06/TW/11909-04 On The investigation report was submitted to EPD on |
The Contractor noted that the complaint was about
the dust nuisance at a lotus pond near CH22+00(L). The pond owner concerned
about disturbance to his lotus due to the backfilling activities. The Contractor has implemented mitigation measures
and no dust nuisance was observed in the ET’s latest site investigation. |
Closed |
40707 |
Tai Shu Ha |
7 Jul 04 |
EPD Ref.: EP3/N06/TW/13356-04 On The investigation report was submitted to EPD on |
According to further discussion with the
complainant, he concerned about the muddy water caused by dump trucks came
from an access ramp during rainy days. Wetted mud was attached in the wheels
of the dump truck and then deposited on the pedestrian road. However, the access ramp and dump truck as mentioned
by the complainant is belonging the Project of “Widening of Yuen Long
Highway” but not the captioned project. Nevertheless, the Contractor will
wash the road every time after rainstorm. Watering will be provided during
sunny days in order to prevent dust nuisance. |
Closed |
40817 |
|
17 Aug 04 |
EPD Ref.: EP3/N06/RN/15829-04 On The investigation report was submitted on |
Having further discussion between ET and EPD, it is
confirmed that the concerned area in the captioned complaint is According to ET’s investigation, the dump trucks and
vehicles causing dust nuisance as mentioned by the complainant were
unidentified. During the site audits conducted by ET and IEC, no
vehicle leaving the site was observed at It is believed that the Contractor has provided
wheel washing and road washing. However, particular incidents might happen
due to violation by sub-contractors of the captioned project and other
adjoining construction projects. |
Closed |
40830 |
Kung Um Road Nullah |
30 Aug 04 |
EPD Ref.: EP3/N06/RN/15829-04 On The investigation report was submitted on |
There are four construction sites locating near the nullah. This is no evident showing the muddy water as
complained (i.e. on 9 and The construction site of the captioned project is
located at |
Closed |
41213 |
Village Entrance of Kong Tau
San Tsuen |
13 December 04 |
EPD Ref.: EP3/N06/RN/25885-04 On The investigation report was submitted on |
According to the Contractor, water browser was
spraying water on the road section between subway and the village entrance of
Kong Tau San Tsuen in order
to suppress the dusty materials on ground to further prevent the fugitive
dust emission from ground. During the operation of water browser, water was
injected from truck to the road surface preventing and obstructing
pedestrians/ villagers accessing to the village entrance directly. The environmental complaint is not supported based
on the available information from the EPO, the RSS and the Contractor.
However, it is recommended that the Contractor should take special cares and
attention to the passers-by in particular pedestrians/ villagers during the
operation of water browser. The scale and coverage of spraying should be
limited to allow sufficient access for the pedestrians and villagers whenever
possible. |
Closed |
41229 |
Site Area Adjacent to Pok Oi Hospital |
29 December 04 |
DSD ref.: DP/8/7070CD/DC0206/5 DSD received a public complaint on The investigation report was submitted on |
The Contractor
has taken action to control and ensure all the vehicles leaving the site have
undergone the wheel washing process within the wheel washing facility
immediately. The problem has been rectified immediately by the Contractor who
has also informed the complainant afterwards. The Contractor
was reminded to confirm all the construction water including wheel washing
water within site boundary and provide sufficient and adequate treatment
before discharge. The Contractor
should strictly control all the vehicles leaving the site to complete the
wheel washing process within the wheel washing facility in order to prevent
the water flowing onto the footway. Sufficient
environmental training should also be provided to all vehicle drivers and
worker who is responsible for wheel washing. All relevant
parties including RE, IEC and ET should monitor such item closely |
Closed |
50205 |
The existing channel connecting to box culvert BC11 |
|
DSD’s Ref.: DP/8/7070CD/DC0206/88 On The
investigation report was submitted on |
According to the Contractor, construction works for box culvert BC11 which will connect to the existing live channel has been conducted. In order to avoid the pollution of the water in such channel due to the Project during construction, a sandbag bund, a pump and a plastic conduit were provided to divert the water which beyond the site boundary to Access Ramp AR7. This is an acceptable mitigation measure to prevent the pollution of local water in channel. The sandbag bund along the site
boundary was provided to serve as a sump pit to collect the water in the
channel. A layer of foam was formed on the surface layer of the accumulated
water. Such layer of foam was formed due to the poor quality of water in live
channel. It was also believed that such foam was wrongly considered as the
sediment (as stated in the complaint) in the water. However, the Contractor was reminded to
clean and remove such layer of foam frequently to maintain a good house
keeping on site. The Contractor should also spray the anti-mosquito repellent
on the accumulated water if necessary. |
Closed |
51229 |
Ha Yau Tin Tsuen |
|
On The
investigation report was
submitted on (Remarks: Due to the failure of email systems, the
ET Leader received the notice of complaint on |
It is believed that the dust complaint
was due to wind erosion by strong wind and low relative humidity. Although
minor construction works were taken place near the complaint area, such
activities are unexpected to be a main dust source. Furthermore, the
Contractor has already provided measures on the complaint area and no major
dust problem was identified during the site audit on It is recommended the Contractor should take special precaution on all haul roads, stockpiles and dry surfaces during dry weather especially when strong wind exists. |
Closed |