1.         INTRODUCTION

Background

 

1.1              Serious flooding has occurred in and around Yuen Long Town at least seven times over the last fifteen years. Government studies including the Northwest New Territories (NWNT) Base Strategy Studies, TELADFLOCCOSS I and II and the NWNT Village Flood Protection Study have identified the major causes of flooding and recommended appropriate mitigation measures. The studies identified that the capacity of the Yuen Long Nullah drainage system was inadequate mainly due to rapid urban growth over the last 20 years which has reduced the flood plain storage capacities and increased runoff volumes. In addition Yuen Long Town has a relatively low ground level and the drainage design standards and methods used at the time were less rigorous than present design requirements. The studies recommended the construction of a Bypass Floodway as the most cost-effective option for providing additional drainage capacity to cater for present needs and to provide additional capacity for new development in the area to the south of Yuen Long.

 

1.2              The Yuen Long Bypass Floodway is therefore to be designed to divert part of the flows entering the Yuen Long Drainage system from the south of Yuen Long into the Kam Tin River Floodway, which is at present under construction, to reduce the risk of flooding in Yuen Long Town. The Project site layout is shown in Figure 1.1.

 

1.3              The Project works mainly comprise the construction and operation of a drainage channel (YLBF) from the south side of Yuen Long to the Kam Tin River.  The Project works was scheduled to commence in March 2003.

 

1.4              According to the EIAO, this Project is a designated project. The Further Environmental Permit (FEP) No. FEP 01-075-2003 was issued on 6 February 2003 and Variation of Environmental Permit (EP-01/075/2003/A) was issued on 19 May 2003 for this project to the Sun Fook Kong (Civil) Limited (hereinafter called the “Contractor”) as Permit Holder. An Updated Environmental Monitoring and Audit Manual (Updated EM&A Manual) was prepared to fulfill requirement stipulated in the Particular Specification Clause 1.106(6).

 

1.5              Cinotech Consultants Limited was commissioned by Sun Fook Kong (Civil) Limited to provide professional services for “Contract No. DC/2002/06 – Environmental Team (ET) for Construction of the Yuen Long Bypass Floodway”.  This Environmental Monitoring and Audit Reports were prepared by Cinotech for the Project prior to the commencement of any construction activity for the Yuen Long Bypass Floodway in accordance with the Updated EM&A Manual.

Project Organizations

 

1.6              Different parties with different levels of involvement in the project organization include:

·          Engineer or Engineer’s Representative (E/ER) – Drainage Services Department (DSD)

·          Environmental Team (ET) – Cinotech Consultants Limited

·          Independent Environmental Checker (IEC) – CH2M HILL Hong Kong Limited

·          Contractor – Sun Fook Kong (Civil) Ltd.

 

1.7              The responsibilities of respective parties are detailed in Section 1 of the Updated EM&A Manual and the project organization chart is presented in Figure 1.2.

1.8              The key contacts of the Project are shown in Table 1.1.

 

Table 1.1     Key Project Contacts

Party

Name

Role

Phone No.

Fax No.

DSD

Mr. Nelson IP

Engineer Representative

2594 7576

2827 8700

ET

Dr. Priscilla Choy

ET Leader

2151 2083

3107 1388

Mr. Kenneth Lam

Audit Team Leader

2151 2078

3107 1388

Mr. Henry Leung

Monitoring Team Leader

9779 7340

3107 1388

IEC

Mr. David Yeung

Independent Environmental Checker

2507 2203

2507 2293

Contractor

Mr. Wallace Lee

Project Manager

2448 0683

2448 0260

Mr. Horace Lee

Assistant Engineer

2448 0683

2448 0260

Construction Programme

1.9              The construction activities undertaken in the reporting month were:

 

·            Construction of footpath and railing;

·            Installation of plumbing & irrigation points;

·            Paving and road works; and

·            Landscape works

Summary of EM&A Requirements

1.10          The EM&A programme requires construction phase monitoring for air quality, construction noise, water quality and environmental site audits. The Updated EM&A Manual requirements for each parameter are described in following sections, including:

·          All monitoring parameters;

·          Action and Limit levels for all environmental parameters;

·          Event / Action Plans;

·          Environmental mitigation measures, as recommended in the project EIA study final report; and

·          Environmental requirements in contract documents.

1.11          The advice on the implementation status of environmental protection and pollution control/mitigation measures is summarized in Section 5 of this report.

1.12          This report presents the monitoring results, observations, locations, equipments, period, methodology and QA/QC procedures of the required monitoring parameters, namely dust, water quality and noise levels and audit works for the Project in August 2006.