1.1
Serious flooding has occurred
in and around
1.2
The Yuen Long Bypass Floodway
is therefore to be designed to divert part of the flows entering the Yuen Long
Drainage system from the south of Yuen Long into the Kam
Tin River Floodway, which is at present under construction, to reduce the risk
of flooding in
1.3
The Project works mainly
comprise the construction and operation of a drainage channel (YLBF) from the
south side of Yuen Long to the
1.4
According to the EIAO, this
Project is a designated project. The Further Environmental Permit (FEP) No. FEP
01-075-2003 was issued on
1.5
Cinotech Consultants Limited was commissioned by Sun Fook
Kong (Civil) Limited to provide professional services for “Contract No.
DC/2002/06 – Environmental Team (ET) for Construction of the Yuen Long Bypass
Floodway”. This Environmental
Monitoring and Audit Reports were prepared by Cinotech
for the Project prior to the commencement of any construction activity for the
Yuen Long Bypass Floodway in accordance with the Updated EM&A Manual.
Project Organizations
1.6
Different parties with
different levels of involvement in the project organization include:
·
Engineer or Engineer’s
Representative (E/ER) – Drainage Services Department (DSD)
·
Environmental Team (ET) – Cinotech Consultants Limited
·
Independent Environmental
Checker (IEC) – CH2M HILL Hong Kong Limited
·
Contractor – Sun Fook Kong (Civil) Ltd.
1.7
The responsibilities of
respective parties are detailed in Section 1 of the Updated EM&A Manual and
the project organization chart is presented in Figure 1.2.
1.8
The key contacts of the Project
are shown in Table 1.1.
Table 1.1 Key
Project Contacts
Name |
Role |
Phone
No. |
Fax
No. |
|
DSD |
Mr.
Nelson IP |
Engineer
Representative |
2594
7576 |
2827
8700 |
ET |
Dr.
Priscilla Choy |
ET
Leader |
2151
2083 |
3107
1388 |
Mr.
Kenneth Lam |
Audit
Team Leader |
2151
2078 |
3107
1388 |
|
Mr.
Henry Leung |
Monitoring
Team Leader |
9779
7340 |
3107
1388 |
|
IEC |
Mr.
David Yeung |
Independent
Environmental Checker |
2507
2203 |
2507
2293 |
Contractor |
Mr.
Wallace Lee |
Project
Manager |
2448
0683 |
2448
0260 |
Mr.
Horace Lee |
Assistant
Engineer |
2448
0683 |
2448
0260 |
1.9
The construction activities
undertaken in the reporting month were:
·
Construction of footpath and
railing;
·
Installation of plumbing &
irrigation points;
·
Paving and road works; and
·
Landscape works
Summary of EM&A Requirements
1.10
The EM&A programme requires construction phase monitoring for air
quality, construction noise, water quality and environmental site audits. The Updated
EM&A Manual requirements for each parameter are described in following
sections, including:
·
All monitoring parameters;
·
Action and Limit levels for all
environmental parameters;
·
Event / Action Plans;
·
Environmental mitigation
measures, as recommended in the project EIA study final report; and
·
Environmental requirements in
contract documents.
1.12
This report presents the
monitoring results, observations, locations, equipments, period, methodology
and QA/QC procedures of the required monitoring parameters, namely dust, water
quality and noise levels and audit works for the Project in August 2006.