6.         FUTURE KEY ISSUES

Key Issues for the Coming Month

 

6.1              Key issues to be considered in the coming month include:

 

·          Generation of dust from stockpiles, haul road and vehicles movement on-site;

·          Noise from operation equipment and machinery on-site;

·          Regular removal of demolished wastes;

·          Regular removal of mud, sand and silt along drainage channel;

·          Wastewater discharge from site;

·          Storage of chemicals/fuel and chemical waste/waste oil on site; and

·          Surface runoff from site and wheel washing bay.

Monitoring Schedule for the Next Month

6.2              The environmental monitoring schedule for the next month is shown in Appendix C.