4.0        Marine Water Quality Monitoring

 

4.1        Monitoring Locations

 

The EIA conducted for the Project has identified a number of monitoring locations that may portentially be affected by construction and operational activities as summarized in Table 4.1 and shown in Figure TS 2031.

 

Table 4.1           Summary of Monitoring Locations

Station

Easting

Northing

M1

806244

827080

M2

806329

826408

M3

806235

826089

C1

806116

827618

C2

806034

825308

 

Control station C1 should be the upstream control station for all monitoring stations during mid-ebb and Control Station C2 should be the upstream control station for all monitoring stations during mid-flood.

 

 

4.2               Monitoring Parameters

 

Monitoring parameters for marine water quality monitoring have been set out in the Project are summarized as follow:

 

            Table 4.2           Marine water quality monitoring parameters

Parameter

Duration

No. of Locations

Depth

Dissolved Oxygen, DO (mg/L)

2 tides/day,

3 days/week

5

3

Turbidity (NTU)

Suspended Solids (mg/L)

 

 

4.3        Environmental Quality Performance Limits

 

The marine water quality criteria, namely Action and Limit (A/L) levels, determined according to the baseline study carried out by ET are presented in the table below.

 

Table 4.3          Water Quality Action and Limit Levels

Parameter

Action Level

Limit Level

Dissolved Oxygen (DO), mg/L

Surface & Middle

4 mg/L

 

Bottom

2.86 mg/L

Surface & Middle

4 mg/L

 

Bottom

2 mg/L

Suspended Solids (SS), mg/L

(Depth-averaged)

44 mg/L or 120% of the upstream control station’s SS at the same tide on the same day

49 mg/L or 130% of the upstream control station’s SS at the same tide on the same day

Turbidity, NTU

(Depth-averaged)

37.4 NTU or 120% of the upstream control station’s turbidity at the same tide on the same day

46.2 NTU or 130% of the upstream control station’s turbidity at the same tide on the same day

 

 

4.4        Event-Action Plans

 

Event-Action Plans are presented in Appendix E. 

 

 

4.5        Monitoring Results: Non-compliance against Action/Limit Levels

 

The results of DO, turbidity and SS are interpreted and present in terms of tidal depth average. The summary of marine water quality exceedances over the course of the Project is shown in Table 4.4.

 

Table 4.4      Summary of Marine Water Quality Exceedances over the course of the Project

Station

Exceedance Level

DO

Turbidity

SS

Flood

Ebb

Flood

Ebb

Flood

Ebb

C1

Action

0

0

0

0

0

0

Limit

0

0

1

0

1

0

M1

Action

0

0

0

1

0

0

Limit

0

0

1

0

1

0

M2

Action

0

0

0

1

0

0

Limit

0

0

1

0

1

0

M3

Action

0

0

0

0

0

0

Limit

0

0

1

0

1

0

C2

Action

1

0

0

0

0

0

Limit

0

0

1

0

1

0

Total

Action

1

0

0

2

0

0

Limit

0

0

5

0

5

0

 

According to the summary of marine water monitoring results, thirteen exceedances of DO, Turbidity and SS were recorded during the Project.

 

 

4.6               Graphical Plots and Statistical Analysis of the trends of monitored parameters during the Project

 

The Graphical Plots shown in Appendix B represent the trends in DO (Surface & Middle and Bottom), Turbidity and SS during the course of the Project including the baseline monitoring and post-project monitoring.

 

According the graphical plots of the monitored parameters, it is found that a few exceedances of surface-middle DO, Turbidity and SS were recorded during the reporting period but they are not work-related. Since the trends of graphics of monitored parameters at baseline monitoring, impact monitoring and post-project monitoring are almost the same, this indicates that no adverse environmental impact was introduce to the surrounding environment from the construction works.

 


 

4.7               Explanation of Exceedances

 

Monitoring Date

Tide

Exceedance parameters

Locations

Explanation

Implementation of Event and Action Plan

13/06/03

Mid-ebb

Turbidity

M2

After ET’s investigation, it was found that no construction works were carried out. No visible foam, oil, grease, litter or other objectionable matter were observed near the construction site. Therefore, it has proved that the exceedance was not related to the construction work.

 

After discussing with the RE, the IE and the Contractor, it was concluded that no further mitigation measures should be taken since the exceedance was not works-related.

20/06/03

Mid-flood

Dissolved Oxygen

C2

After the ET’s investigation and discussion between the IE and ET, C2 was up-stream control station during mid-flood and the exceedance of dissolved oxygen (Surface and Middle) was not due to the construction works.

 

After discussing with the RE, the IE and the Contractor, it was concluded that no further mitigation measures should be taken since the exceedance was not works-related.

27/06/03

Mid-flood

Turbidity

 and

Suspended Solids

C1, M1, M2, M3 and C2

After ET’s investigation, it was found that no construction works were carried out. No visible foam, oil, grease, litter or other objectionable matter were observed near the construction site. During the monitoring, ET found that the wave was so strong that settled solids were stirred up from the seabed to the water column. Therefore, the exceedance was not work-related.

 

After discussing with the RE, the IE and the Contractor, it was concluded that no further mitigation measures should be taken since the exceedance was not works-related.

03/11/03

Mid-Ebb

Turbidity

M1

 

During the marine water quality monitoring at 03/11/2003, ET found that the major construction works was demolishing existing pier. No visible foam, oil, grease, litter or other objectionable matter were observed near the monitoring stations. Comparing the monitoring results of the same tide, the turbidity at M1 was lower than 120% of upstream control station C1. Besides, the Turbidity result at monitoring station M2 which is closer to the existing pier was found lower than monitoring station M1 and within the Action and Limit Level, indicating that the water quality impact due the construction works was not significant and did not cause adversely effect on water quality near the site. Therefore, the exceedance was not work-related.

 

After discussing with the IEC and the Contractor, it was concluded that no further mitigation measures should be taken since the exceedance was not works-related.