7.0               Waste Management

 

7.1       Waste Management Audit

 

Waste management audit was carried out by the ET. A summary of the implementation status of the mitigation measures on waste management is presented in Appendix F.

 

7.2               Records of Waste Quantities

 

All types of wastes arising from the construction work are classified into the following:

 

·          General refuses;

·          Chemical waste;

·          Construction & demolition (C&D) material.

 

The summary of waste for disposal over the course of the Project is summarized in Table 7.1.

 

Table 7.1        Summary of Quantities of Waste for Disposal over the course of the Project

Type of Waste

Quantity

Disposal Location

Dredged Materials (Contaminated) (m3)

0

Nil

Dredged Materials (Uncontaminated) (m3)

1000

East Sha Chau : Mud Pit Ivb

C&D Material (Inert) (m3)

0

Nil

C&D material (Non-inert) (m3)

5

Public Refuse Collection Point

50

Landfill Site

General Refuse (m3)

36

Public Refuse Collection Point

Chemical Waste (m3)

0

Nil

 

 

7.3               Summary of dredged sediment volume during the Construction Works

 

The summary of daily dredged sediment volume during the construction stage is summarized in Table 7.2.

 

Table 7.2        Summary of Daily Dredged Sediment Volume during the construction stage

Date

Dredged Sediment Volume (m3)

Disposal Volume (m3)

12/06/2003

300

0

13/06/2003

200

0

14/06/2003

0

500

16/06/2003

350

0

17/06/2003

150

0

18/06/2003

250

500

19/06/2003

250

0

20/06/2003

0

500

26/06/2003

100

0

27/06/2003

400

0

28/06/2003

0

500

22/09/2003

500

0

23/09/2003

0

500

24/09/2003

500

500

Total Volume

3000

3000