Executive SUMMARY
This Final EM&A Review Report has been prepared by
the Environmental Team (ET) of ETS-Testconsult Ltd for environmental
monitoring, included Post-project monitoring, under the Environmental Permit
No. EP-150/2002/A (the EP) for “ Construction of Jetty at Lung Kwu Chau (CED
Contract No.: CV/2002/11) ” (The Project) over the course of the Project.
Construction Progress
The major construction works in the course of the project included:
·
Dredging of the jetty, catwalk foundation and
approach channel;
·
Excavation of the footpath’s foundation;
·
Backfilling of the jetty and the catwalk;
·
Construction of the new jetty;
·
Demolition of old jetty.
Environmental Monitoring Progress
The monitoring activities over the course of the Project are
summarized below:
·
Baseline
marine water quality monitoring: 12 Occasions at 5 designated locations;
·
Impact
marine water quality monitoring: 20 Occasions at 5 designated locations;
·
Post-project
marine water quality monitoring: 12 Occasions at 5 designated locations;
·
Site
inspection: 17 Occasions.
Marine Water Monitoring
There were thirteen exceedances of Action
and Limit Level of the monitoring parameters recorded over the course of the
Project but all of them were not work-related.
Site Inspection
Environmental audits and inspections conducted
in this reporting month are summarized as follows:
Concerned Parties |
Dates of Audit /
Inspection |
CED / WKC&T / ET |
13/6, 20/6, 27/6, 04/7,
11/7, 18/7, 25/7, 01/8, 22/8, 19/9, 26/9, 17/10, 24/10, 31/10, 7/11, 14/11,
21/11 |
According to the site inspection, it
indicated that site practices of the WKC&T were generally undertaken in an
environmentally acceptable manner and the overall site environmental performance
was satisfactory over the course of the Project.
Environmental Complaints and Notification of Summons and
Successful Prosecutions
No environmental complaints were received
and no notification of summons and prosecutions with respect to environmental
issues were registered over the course of the Project.