5.               ENVIRONMENTAL SITE INSPECTION

 

Site Inspections

 

5.1               Site inspection was carried out on a weekly basis to monitor the timely implementation of proper environmental pollution control and mitigation measures for the Project. In the month, five site inspections were carried out. The summary of weekly environmental site inspections observations and environmental site inspection checklists are attached in Appendix [INCLUDE SITE INSPECTION RECORDS IN APPENDIX H]J.

Review of Environmental Monitoring Procedures

 

5.2               The monitoring works conducted by the Environmental Team were inspected regularly. Observations have been recorded for the monitoring works as follows:

 

Air Quality Monitoring

·         The monitoring team recorded the observations around the monitoring stations within and outside of the construction site.

·         The monitoring team recorded the temperature and general weather condition on the monitoring day.

 

Noise Monitoring

·         The monitoring team recorded the observations around the monitoring stations, which might affect the results.

·         Major noise sources were identified and recorded.

Advice on Waste Management Status

 

5.3               The actual quantities of uncontaminated sediment, contaminated sediment, inert C&D materials and C&D wastes generated by activities of the Project in the month are provided in Table 5.1. Trip ticket system was implemented for all offsite waste disposal.

 

Table 5.1          Summary of Waste Disposal in The Month

 

Type of Waste Material

Disposed Quantity

Destination

Uncontaminated sediments

Nil

Not Applicable

Contaminated sediments

Nil

Not Applicable

Inert C&D materials

1,105m3

Tuen Mun Area 38

Non-inert C&D waste

Metals

103.79kg

Recycling companies

Paper/cardboard packaging

Nil

Not Applicable

Plastics

Nil

Not Applicable

Chemical waste

Nil

Not Applicable

Others, e.g. general refuse

123m3

WENT Landfill

 

Status Environmental Licences and Permits

[INCLUDE ANY NEW LICENSE & PERMIT INFORMATION IN REPORTING MONTH]

5.4               The status of all permits/licences obtained/in-use in the month is summarised in Appendix K. [INCLUDE ALL LICENSE & PERMIT INFORMATION IN APPENDIX M]

Implementation Status of Environmental Mitigation Measures

 

5.5               An updated summary of the Environmental Mitigation Implementation Schedule (EMIS) is presented in Appendix L.

 

5.6               [INCLUDE EMIS FOR REPORTING MONTH IN APPENDIX I] During the weekly site inspection conducted by the Environmental Team in the month, the following observations and recommendations were made.

 

Resource Management [INCLUDE AIR QUALITY SITE OBSERVATIONS IN REPORTING MONTH, SOME TYPICAL EXAMPLES SHOWN BELOW FOR REFERENCE]

 

·         No observations and recommendations were made during the weekly site inspections in the month.

 

 [REVISE STATEMENT TO REPORT ON CONTRACTOR’S IMPLEMENTATION STATUS OF MITIGATION MEASURES]

Material Storage/Spillage/Leakage [INCLUDE AIR QUALITY SITE OBSERVATIONS IN REPORTING MONTH, SOME TYPICAL EXAMPLES SHOWN BELOW FOR REFERENCE]

 

·         Accumulated construction waste was found at area B and broken tree branches and leaves were found at gully of C66 and on carriageway at TTA32. The Contractor was reminded to improve housekeeping on site.

·         Oil seepage was observed from a generator and a few oil drums. The Contractor was reminded to clean up the oil spillage as soon as possible.

·         Water was observed accumulated in drip trays with generator and oil drums. The Contractor was reminded to remove them as soon as possible.

·         Oil seepage was observed from a generator set on deck at Grid 6. The Contractor was reminded to clear the oil stain and dispose of as chemical waste.

 

Waste Management [INCLUDE AIR QUALITY SITE OBSERVATIONS IN REPORTING MONTH, SOME TYPICAL EXAMPLES SHOWN BELOW FOR REFERENCE]

 

·         Sand was found on carriageway at TTA12 and TTA3. General refuse was found at F17, deadleaves were found at C545 behind the temple and untidy condition was found at C143. The Contractor was reminded to improve housekeeping at the locations.

 

Water Pollution [INCLUDE AIR QUALITY SITE OBSERVATIONS IN REPORTING MONTH, SOME TYPICAL EXAMPLES SHOWN BELOW FOR REFERENCE]

 

·         Blockage of catchpits were found at TTA3, C66 (outfall BB & EE) and C6. The Contractor was reminded to properly maintain the drainage system to prevent flooding.

·         Deadleaves were found inside u-channel at TTA58-S2. The Contractor was reminded to properly maintain the drainage system.

·         Broken concrete and leaves were found inside u-channel at TTA3 and C6/C66 and gullies at F16 were found blocked. The Contractor was reminded to properly maintain the drainage system.

·         Deadleaves were found inside u-channel at TTA3. The Contractor was reminded to properly maintain the drainage system.

 

Air Emissions [INCLUDE AIR QUALITY SITE OBSERVATIONS IN REPORTING MONTH, SOME TYPICAL EXAMPLES SHOWN BELOW FOR REFERENCE]

 

·         Mud trail was found at the site entrance of F17. The Contractor was reminded to provide wheel-washing at site exits to prevent dust emission.

 

Noise/Vibration [INCLUDE AIR QUALITY SITE OBSERVATIONS IN REPORTING MONTH, SOME TYPICAL EXAMPLES SHOWN BELOW FOR REFERENCE]

 

·         No observations and recommendations were made during the weekly site inspections in the month.

 

 

Abnormal/Emergency [INCLUDE AIR QUALITY SITE OBSERVATIONS IN REPORTING MONTH, SOME TYPICAL EXAMPLES SHOWN BELOW FOR REFERENCE]

 

·         No observations and recommendations were made during the weekly site inspections in the month.

 

Miscellaneous

 [INCLUDE AIR QUALITY SITE OBSERVATIONS IN REPORTING MONTH, SOME TYPICAL EXAMPLES SHOWN BELOW FOR REFERENCE]

·         Stagnant water was found at Grid 9 site entrance. The Contractor was reminded to clear the stagnant water or level the ground to prevent mosquitoes breeding.

·         Stagnant water was found in the refuse collection bin at Grid 6, inside cachpit at F16 and in the excavated trench at TTA58-S2. The Contractor was reminded to remove the stagnant water to prevent mosquitoes breeding.

·         The Contractor was reminded to improve housekeeping at Grid 8 and clear the sand deposited at site office area.

·         Stagnant water was found inside chamber of Grid 8, excavated trench at TTA58-S2, inside u-channel at F17 and inside catchpit at F16. The Contractor was reminded to remove the stagnant water to prevent mosquitoes breeding.

Summary of Exceedances of Environmental Quality Performance Limit

 

5.7               The Event and Action Plans for air quality and noise are presented in Appendix M.

 

5.8               One Action level exceedance was recorded on 24-hour TSP at AM1 on 22 August 2006. The exceedance was considered not related to the Project.

 

Summary of Environmental Complaints, Notifications of Summons and Successful Prosecutions

 

5.9               Figure 5.1 presents the environmental complaint flow diagram of the Project.

 

5.10            No environmental complaint, notification of summons and successful prosecution was received in the reporting month.