5.               ENVIRONMENTAL SITE INSPECTION

 

Site Inspections

 

5.1               Site inspection was carried out on a weekly basis to monitor the timely implementation of proper environmental pollution control and mitigation measures for the Project. In the month, five site inspections were carried out. The summary of weekly environmental site inspections observations and environmental site inspection checklists are attached in Appendix H[INCLUDE SITE INSPECTION RECORDS IN APPENDIX H]HHHHHH.

 

Review of Environmental Monitoring Procedures

 

5.2               The monitoring works conducted by the Environmental Team were inspected regularly. Observations have been recorded for the monitoring works as follows:

 

Air Quality Monitoring

·         The monitoring team recorded the observations around the monitoring stations within and outside of the construction site.

·         The monitoring team recorded the temperature and general weather condition on the monitoring day.

 

Noise Monitoring

·         The monitoring team recorded the observations around the monitoring stations, which might affect the results.

·         Major noise sources were identified and recorded.

 

Advice on Waste Management Status

 

5.3               The actual quantities of uncontaminated sediment, contaminated sediment, inert C&D materials and C&D wastes generated by activities of the Project in the month are provided in Table 5.1. Trip ticket system was implemented for all offsite waste disposal.

 

Table 5.1          Summary of Waste Disposal in The Month

 

Type of Waste Material

Disposed Quantity

Destination

Uncontaminated sediments

Nil

Not Applicable

Contaminated sediments

Nil

Not Applicable

Inert C&D materials

1,080m3

Tuen Mun Area 38

Non-inert C&D waste

Metals

30.06kg

Recycling companies

Paper/cardboard packaging

Nil

Not Applicable

Plastics

Nil

Not Applicable

Chemical waste

Nil

Not Applicable

Others, e.g. general refuse

95m3

WENT Landfill

 

Status Environmental Licences and Permits

[INCLUDE ANY NEW LICENSE & PERMIT INFORMATION IN REPORTING MONTH]

5.4               The status of all permits/licences obtained/in-use in the month is summarised in Appendix I. [INCLUDE ALL LICENSE & PERMIT INFORMATION IN APPENDIX M]

 

Implementation Status of Environmental Mitigation Measures

 

5.5               An updated summary of the Environmental Mitigation Implementation Schedule (EMIS) is presented in Appendix J.

 

5.6               [INCLUDE EMIS FOR REPORTING MONTH IN APPENDIX I] During the weekly site inspection conducted by the Environmental Team in the month, the following observations and recommendations were made.

Resource Management [INCLUDE AIR QUALITY SITE OBSERVATIONS IN REPORTING MONTH, SOME TYPICAL EXAMPLES SHOWN BELOW FOR REFERENCE]

 

·         No observations and recommendations were made during the weekly site inspections in the month.

 

 [REVISE STATEMENT TO REPORT ON CONTRACTOR’S IMPLEMENTATION STATUS OF MITIGATION MEASURES]

Material Storage/Spillage/Leakage [INCLUDE AIR QUALITY SITE OBSERVATIONS IN REPORTING MONTH, SOME TYPICAL EXAMPLES SHOWN BELOW FOR REFERENCE]

 

·         One oil drum was found without drip tray on deck at Grid 8. The Contractor was reminded to provide drip tray to all chemical drums on site.

·         Oil seepage was observed from a drip tray holding an oil drum at Grid 6 (WB) and oil stain was noted underneath a drip tray holding a generator at Grid 6 (EB). The Contractor was requested to clear the seeped oil / oil stain.

·         The Contractor was requested to provide drip tray to an oil drum at Grid 6 (WB).

·         The Contractor was requested to clear the oil left inside the drip tray at Grid 6 (WB & EB) and handle the cleared oil as chemical waste.

·         Two oil containers were found placed on bareground without drip tray at Gate 2. The Contractor was reminded to properly store the chemicals.

 

Waste Management [INCLUDE AIR QUALITY SITE OBSERVATIONS IN REPORTING MONTH, SOME TYPICAL EXAMPLES SHOWN BELOW FOR REFERENCE]

 

·         Leaves were found beside carriageway at TTA31-2A, TTA31-1A and at Hong Fai Road Junction. C&D materials were found at FR17, TTA31-2A and corner of Hong Fai Road. The Contractor was reminded to improve housekeeping.

·         C&D waste gathered and sorted at Grid 9 had to be collected properly for disposal.

·         Untidy condition was found at Grid 1. The Contractor was reminded to improve housekeeping.

·         C&D waste was found on Slope of TTA3. The Contractor was reminded to improve housekeeping.

·         C&D waste and stockpile of cement bags were found at Chainage 2200-2600. Leaves were found along the side of carriageway at TTA31 and along footpath at TTA31-2. The Contractor was reminded to improve housekeeping on site.

 

Water Pollution [INCLUDE AIR QUALITY SITE OBSERVATIONS IN REPORTING MONTH, SOME TYPICAL EXAMPLES SHOWN BELOW FOR REFERENCE]

 

·         Tarpaulin sheets and C&D materials were found inside u-channel at TTA3 and leaves were found in u-channel at TTA47-S2. The Contractor was reminded to properly maintain the drainage system.

·         Leaves and sand were found inside the u-channel and carchpit at TTA3. The Contractor was reminded to properly maintain the drainage system.

·         Gullies at TTA31 were found blocked by leaves. The Contractor was reminded to properly maintain the drainage system.

 

Air Emissions [INCLUDE AIR QUALITY SITE OBSERVATIONS IN REPORTING MONTH, SOME TYPICAL EXAMPLES SHOWN BELOW FOR REFERENCE]

 

·         Grey smoke was found emitted from an excavator at Gate 1. The Contractor was reminded to properly maintain the plants on site.

·         The Contractor was advised to provide tarpaulin cover to stockpile of fill material at Grid 1.

·         Stockpile of fine material was found at Chainage 2200 without cover. The Contractor was reminded to cover the stockpile.

 

Noise/Vibration [INCLUDE AIR QUALITY SITE OBSERVATIONS IN REPORTING MONTH, SOME TYPICAL EXAMPLES SHOWN BELOW FOR REFERENCE]

 

·         No observations and recommendations were made during the weekly site inspections in the month.

 

 

Abnormal/Emergency [INCLUDE AIR QUALITY SITE OBSERVATIONS IN REPORTING MONTH, SOME TYPICAL EXAMPLES SHOWN BELOW FOR REFERENCE]

 

·         No observations and recommendations were made during the weekly site inspections in the month.

 

Miscellaneous

 [INCLUDE AIR QUALITY SITE OBSERVATIONS IN REPORTING MONTH, SOME TYPICAL EXAMPLES SHOWN BELOW FOR REFERENCE]

·         The Contractor was reminded to remove the stagnant water in the wheel-washing bay at Gate 2 to prevent mosquitoes breeding.

·         One concrete chute washing was observed without collection at Chainage 2100. The Contractor was reminded to collect the washwater and treat prior to discharge.

·         Water ponding was found at Gate 1 and on deck at Grid 3. The Contractor was reminded to remove the stagnant water.

 

Summary of Exceedances of Environmental Quality Performance Limit

 

5.7               The Event and Action Plans for air quality and noise are presented in Appendix K.

 

5.8               No exceedance of impact 1-hour and 24-hour TSP and noise monitoring was recorded in the reporting month.

 

Summary of Environmental Complaints, Notifications of Summons and Successful Prosecutions

 

5.9               Figure 5.1 presents the environmental complaint flow diagram of the Project.

 

5.10            No environmental complaint, notification of summons and successful prosecution was received in the reporting month.