5.1
Site inspection was carried out on a weekly basis to monitor
the timely implementation of proper environmental pollution control and
mitigation measures for the Project. In the month, four site inspections were
carried out. The summary of weekly environmental site inspections observations
and environmental site inspection checklists are attached in Appendix H
Review of
Environmental Monitoring Procedures
5.2
The monitoring works conducted by the Environmental Team
were inspected regularly. Observations have been recorded for the monitoring
works as follows:
Air Quality
Monitoring
·
The
monitoring team recorded the observations around the monitoring stations within
and outside of the construction site.
·
The
monitoring team recorded the temperature and general weather condition on the
monitoring day.
Noise Monitoring
·
The
monitoring team recorded the observations around the monitoring stations, which
might affect the results.
·
Major
noise sources were identified and recorded.
Advice on
Waste Management Status
5.3
The actual quantities of uncontaminated sediment, contaminated
sediment, inert C&D materials and C&D wastes generated by activities of
the Project in the month are provided in Table 5.1. Trip ticket system was
implemented for all offsite waste disposal.
Table 5.1 Summary of Waste Disposal in The Month
Type of Waste Material |
Disposed Quantity |
Destination |
|
Uncontaminated sediments |
Nil |
Not Applicable |
|
Contaminated sediments |
Nil |
Not Applicable |
|
Inert C&D materials |
1,505m3 |
Tuen Mun Area 38 |
|
Non-inert
C&D waste |
Metals |
30.02kg |
Recycling companies |
Paper/cardboard packaging |
Nil |
Not Applicable |
|
Plastics |
Nil |
Not Applicable |
|
Chemical waste |
Nil |
Not Applicable |
|
Others, e.g. general refuse |
60m3 |
WENT Landfill |
[INPUT SOLID WASTE DISPOSAL QUANTITIES &
DESTINATIONS WITH CONTRACTOR’S WASTE DISPOSAL INFORMATION IN REPORTING MONTH]
Status
Environmental Licences and Permits
5.4
The status of all permits/licences obtained/in-use in the
month is summarised in Appendix I.
Implementation
Status of Environmental Mitigation Measures
5.5
An updated summary of the Environmental Mitigation
Implementation Schedule (EMIS) is presented in Appendix J.
5.6
During the weekly site inspection conducted by the
Environmental Team in the month, the following observations and recommendations
were made.
Resource Management
·
No
observations and recommendations were made during the weekly site inspections
in the month.
Material
Storage/Spillage/Leakage
·
Oil stain was found under the drip tray for a generator at TTA3. The
Contractor was reminded to clear the oil stain.
Waste Management
·
Small amount of general refuse was observed at Grid 7. The Contractor
was requested to properly collect the general refuse scattered at Grid 7 and
properly maintain the housekeeping on site.
·
Sand was found on carriageway at Gate 1 and Chainage
2000-2200 and 2400-2600. Leaves were found on carriageway at
Water Pollution
·
Water was leaked from a hose at Grid 7 due to lack of valve control. The
Contractor was requested to install the valve control for the hose to avoid the
wastage of water.
·
Muddy water and leaves were found inside catchpits
of TTA3. The Contractor was reminded to properly maintain the drainage system
and prevent any muddy discharge.
·
Mud was found inside u-channel at TTA3. The Contractor was reminded to
properly maintain the drainage system.
·
Leaves and rubbish was found inside the u-channel at TTA3 and FR17. The
Contractor was reminded to properly maintain the drainage system.
Air Emissions
·
Mud trails were found at site exits of Gate 1, Gate 2 and Chainage 3075. The Contractor was reminded to exercise
wheel-wash at all site exits and clear the mud trails.
·
Fugitive dust was observed during pavement breaking at C6/C66 and during
vehicle movement at unpaved area near Gate 2. The Contractor was reminded to
provide water spraying to dusty operation and along unpaved roads.
·
Stockpile of fine materials was found at Gate 1 without cover. The
Contractor was reminded to properly cover the fine material to prevent dust
emission.
Noise/Vibration
·
Two air compressors were found operating with flaps opened. The
Contractor was reminded to close the flaps o plants on site during operation.
Abnormal/Emergency
·
No
observations and recommendations were made during the weekly site inspections
in the month.
Miscellaneous
·
No
observations and recommendations were made during the weekly site inspections
in the month.
Summary of Exceedances of Environmental Quality
Performance Limit
5.7
The Event and Action Plans for air quality and noise are
presented in Appendix K.
5.8
No exceedance of impact 1-hour TSP
and noise monitoring was recorded in the reporting month. One Action and one
limit level exceedances on 24-hour TSP were recorded
in the reporting month. Both exceedances were
considered not related to the Project.
Summary of
Environmental Complaints, Notifications of Summons and Successful Prosecutions
5.9
Figure 5.1 presents the environmental complaint flow diagram
of the Project.
5.10
No environmental complaint, notification of summons and
successful prosecution was received in the reporting month.