5.1
Site inspection was carried out on a weekly basis to monitor
the timely implementation of proper environmental pollution control and
mitigation measures for the Project. In the month, four site inspections were
carried out. The summary of weekly environmental site inspections observations
and environmental site inspection checklists are attached in Appendix H
Review of
Environmental Monitoring Procedures
5.2
The monitoring works conducted by the Environmental Team
were inspected regularly. Observations have been recorded for the monitoring
works as follows:
Air Quality
Monitoring
·
The
monitoring team recorded the observations around the monitoring stations within
and outside of the construction site.
·
The
monitoring team recorded the temperature and general weather condition on the
monitoring day.
Noise Monitoring
·
The
monitoring team recorded the observations around the monitoring stations, which
might affect the results.
·
Major
noise sources were identified and recorded.
Advice on
Waste Management Status
5.3
The actual quantities of uncontaminated sediment,
contaminated sediment, inert C&D materials and C&D wastes generated by
activities of the Project in the month are provided in Table 5.1. Trip ticket
system was implemented for all offsite waste disposal.
Table 5.1 Summary of Waste Disposal in The Month
Type of Waste Material |
Disposed Quantity |
Destination |
|
Uncontaminated sediments |
Nil |
Not Applicable |
|
Contaminated sediments |
Nil |
Not Applicable |
|
Inert C&D materials |
1,595m3 |
Tuen Mun Area 38 |
|
Non-inert
C&D waste |
Metals |
Nil |
Recycling companies |
Paper/cardboard packaging |
Nil |
Not Applicable |
|
Plastics |
Nil |
Not Applicable |
|
Chemical waste |
Nil |
Not Applicable |
|
Others, e.g. general refuse |
5m3 |
WENT Landfill |
[INPUT SOLID WASTE DISPOSAL QUANTITIES &
DESTINATIONS WITH CONTRACTOR’S WASTE DISPOSAL INFORMATION IN REPORTING MONTH]
Status
Environmental Licences and Permits
5.4
The status of all permits/licences obtained/in-use in the
month is summarised in Appendix I.
Implementation
Status of Environmental Mitigation Measures
5.5
An updated summary of the Environmental Mitigation
Implementation Schedule (EMIS) is presented in Appendix J.
5.6
During the weekly site inspection conducted by the
Environmental Team in the month, the following observations and recommendations
were made.
Resource Management
·
No
observations and recommendations were made during the weekly site inspections
in the month.
Material
Storage/Spillage/Leakage
·
C&D materials were found on pedestrian walkway at TTA3, FR17 and Chainage 2200-2300. The Contractor was reminded to improve
housekeeping on site.
Waste Management
·
Sand was found on pedestrian walkway at C545 and Chainage
2070. Leaves were found on the edge of carriageway at TTA31 and at
·
The Contractor was reminded to clear the C&D waste at site entrance
of Chainage 2000.
Water Pollution
·
Rubbish and leaves were found inside u-channel at TTA3 and FR17. The Contractor
was reminded to properly maintain the drainage system.
Air Emissions
·
Stockpile of fine material was found at Tai Lam Kok
and fugitive dust was observed during dumping of these materials at the
stockpile. The Contractor was reminded to remove the stockpile or dampen the
dusty stockpile / operation.
·
Mud trails were observed outside the site exit of Gate 1 and Siu Lam roundabout. The Contractor was requested to
properly practice wheel-washing for vehicle before leaving the site.
·
Fugitive dust was observed from wind erosion or vehicle movement on the
unpaved area at Eastbound from Grid 9 to Tai Lam Kok.
The Contractor was advised to increase water spraying frequency.
·
Stockpile of sand was observed at CH1900 seafront footpath. The Contracor was requested to cover the idle stockpile.
·
Unpaved area at Chainage 2000 was not
dampened. The Contractor was reminded to provide water spraying to prevent dust
emission.
Noise/Vibration
·
No
observations and recommendations were made during the weekly site inspections
in the month.
Abnormal/Emergency
·
No
observations and recommendations were made during the weekly site inspections
in the month.
Miscellaneous
·
No
observations and recommendations were made during the weekly site inspections
in the month.
Summary of Exceedances of Environmental Quality
Performance Limit
5.7
The Event and Action Plans for air quality and noise are
presented in Appendix K.
5.8
No exceedance of impact 1-hour TSP
and noise monitoring was recorded in the reporting month. One Action level exceedance on 24-hour TSP were
recorded in the reporting month. The exceedance was
considered not related to the Project.
Summary of
Environmental Complaints, Notifications of Summons and Successful Prosecutions
5.9
Figure 5.1 presents the environmental complaint flow diagram
of the Project.
5.10
No environmental complaint, notification of summons and
successful prosecution was received in the reporting month.