7.1
Environmental monitoring and audit was performed in January 2007.
All monitoring and audit results in the month were checked and reviewed.
7.2
All 1-hour TSP monitoring results recorded in the month
complied with the Action and Limit Levels. One Action level exceedance on
24-hour TSP was recorded in the reporting month.
7.3
All noise monitoring results recorded in the month complied
with the Action and Limit Levels.
7.4
Water quality monitoring was
suspended since 1 December 2005 as there is no rock and sand excavation at the
inter-tidal zone for the construction of Slope 6SW-D/FR 17.
In general, the Contractor
satisfactorily implemented all the required mitigation measure and was
reasonably responsive to the ET’s recommendations on any discrepancy observed
during the weekly environmental site inspection.
No environmental complaint, notification of summons and successful prosecution was received in the reporting month.
7.9
According to results of weekly environmental site
inspections performed in the month and the construction programme for the
coming month, recommendations for air quality, construction noise, water
quality and chemical and waste management are detailed in Section 6.1.