5.1
Site inspection was carried out on a weekly basis to monitor
the timely implementation of proper environmental pollution control and
mitigation measures for the Project. In the month, five site inspections were
carried out. The summary of weekly environmental site inspections observations
and environmental site inspection checklists are attached in Appendix H
Review of
Environmental Monitoring Procedures
5.2
The monitoring works conducted by the Environmental Team
were inspected regularly. Observations have been recorded for the monitoring
works as follows:
Air Quality
Monitoring
·
The
monitoring team recorded the observations around the monitoring stations within
and outside of the construction site.
·
The
monitoring team recorded the temperature and general weather condition on the
monitoring day.
Noise Monitoring
·
The
monitoring team recorded the observations around the monitoring stations, which
might affect the results.
·
Major
noise sources were identified and recorded.
Advice on
Waste Management Status
5.3
The actual quantities of uncontaminated sediment,
contaminated sediment, inert C&D materials and C&D wastes generated by
activities of the Project in the month are provided in Table 5.1. Trip ticket
system was implemented for all offsite waste disposal.
Table 5.1 Summary of Waste Disposal in The Month
Type of Waste Material |
Disposed Quantity |
Destination |
|
Uncontaminated sediments |
Nil |
Not Applicable |
|
Contaminated sediments |
Nil |
Not Applicable |
|
Inert C&D materials |
1020m3 |
Tuen Mun Area 38 |
|
Non-inert
C&D waste |
Metals |
27790kg |
Recycling companies |
Paper/cardboard packaging |
Nil |
Not Applicable |
|
Plastics |
Nil |
Not Applicable |
|
Chemical waste |
Nil |
Not Applicable |
|
Others, e.g. general refuse |
125m3 |
WENT Landfill |
Status
Environmental Licences and Permits
5.4
The status of all permits/licences obtained/in-use in the
month is summarised in Appendix I.
Implementation
Status of Environmental Mitigation Measures
5.5
An updated summary of the Environmental Mitigation
Implementation Schedule (EMIS) is presented in Appendix J.
5.6
During the weekly site inspection conducted by the
Environmental Team in the month, the following observations and recommendations
were made.
Resource Management
·
No
observations and recommendations were made during the weekly site inspections
in the month.
Material
Storage/Spillage/Leakage
·
Soil runoff was found on pedestrial walkway at
Gate 1. The Contractor was reminded to improve housekeeping.
·
One oil drum at Tai Lam Kok was found without
drip tray. The Contractor was reminded to provide drip tray to all chemicals.
·
Soil / asphalt was found deposited at the site
exit of Siu Lam roundabout. The Contractor was
reminded to clear the deposited soil.
Waste Management
·
C&D waste was found on slope of TTA3, Chainage
2200 and Tai Lam Kok roundabout carpark.
The Contractor was reminded to clear the C&D waste regularly.
·
Refuse was found at FR17. The Contractor was reminded to clear the
refuse regularly.
·
C&D waste was found behind the temple. Refuse and C&D waste was
found at F17. The Contractor was reminded to regularly remove the refuse and
C&D waste off-site.
·
The Contractor was reminded to remove the skip which was full of general
refuse.
Water Pollution
·
Leaves were found inside catchpit and
u-channel at TTA3. The Contractor was reminded to properly maintain the
drainage system.
Air Emissions
·
Fugitive dust was observed during vehicles movement and excavation at
Gate 1. The Contractor was reminded to provide sufficient water spraying.
·
Mud trails were observed at site exit at Siu
Lam Roundabout. The Contractor was reminded to provide wheel-wash to all site
exits.
Noise/Vibration
·
No
observations and recommendations were made during the weekly site inspections
in the month.
Abnormal/Emergency
·
No
observations and recommendations were made during the weekly site inspections
in the month.
Miscellaneous
·
No
observations and recommendations were made during the weekly site inspections
in the month.
Summary of Exceedances of
Environmental Quality Performance Limit
5.7
The Event and Action Plans for air quality and noise are
presented in Appendix K.
5.8
No exceedance of impact 1-hour and
24-hour TSP and noise monitoring was recorded in the reporting month.
Summary of
Environmental Complaints, Notifications of Summons and Successful Prosecutions
5.9
Figure 5.1 presents the environmental complaint flow diagram
of the Project.
5.10
No environmental complaint, notification of summons and
successful prosecution was received in the reporting month.