Appendix H              Summary of Weekly Environmental Site Inspection Observations in March 2007

 

Inspection date

Observation

Contractor’s Follow-up Action

1

6

15

22

29

Ö

 

 

 

 

C&D waste found on slope of TTA3, Chainage 2200 and Tai Lam Kok Roundabout carpark.

Clear the C&D waste regularly.

Ö

 

Ö

Ö

Ö

Leaves were found inside catchpit and u-channel at TTA3.

Properly maintain the drainage system

 

Ö

 

 

 

Fugitive dust was observed during vehicles movement and excavation at Gate 1.

Provide sufficient water spraying.

 

Ö

 

 

 

Mud trails were observed at site exit at Siu Lam Roundabout.

Provide wheel-washing to all site exit.

 

 

Ö

 

 

Soil runoff was found on pedestrian walkway at Gate 1.

Improve housekeeping on site.

 

 

Ö

 

Ö

Refuse was found at FR17.

Clear the refuse regularly.

 

 

 

Ö

 

C&D waste was found behind the temple. Refuse and C&D waste found at F17.

Regularly remove the refuse and C&D waste off-site.

 

 

 

 

Ö

Skip was found full of general refuse at Gate 1.

Regularly remove the refuse off site.

 

 

 

 

Ö

One oil drum at Tai Lam Kok was found without drip tray.

Provide drip tray to all chemicals.

 

 

 

 

Ö

Soil / asphalt found deposited at the site exit of Siu Lam Roundabout.

Clear the deposited soil.