Inspection date |
Observation |
Contractor’s Follow-up
Action |
|||
7 |
14 |
21 |
28 |
||
Ö |
|
|
|
Stockpile of excavated
material was found next to the catchpit at TTA3. |
Cover or remove the
stockpile. |
Ö |
Ö |
Ö |
Ö |
Accumulated C&D waste
was found at C6/C66 near Gate 2 and at FR17. |
Regularly remove the
waste off-site. |
|
Ö |
|
Ö |
Sand runoff to
carriageway was found at TTA3. |
Clear the sand and
prevent further runoff. |
|
|
Ö |
|
Fugitive dust was
observed during vehicle movement along the unpaved area at C6/C66. |
Provide water spraying
for dust suppression. |