6.                  FUTURE KEY ISSUES

 

Key Issues for Coming Month

 

6.1               Key issues to be considered in the coming month include: [INCLUDE KEY ENVIRONMENTAL ISSUES IN COMING REPORTING MONTH IDENTIFIED IN CONSTRUCTION PROGRAMME, SOME TYPICAL EXAMPLES SHOWN FOR REFERENCE]

 

·         Prevention of generation of dust from activities on-site;

·         Minimize noise impact from operating equipment and machinery on-site;

·         Prevention of site surface runoffs and wastewater from entering public drainage;

·         Removal of stagnant water on site to prevent mosquitoes breeding; and

·         Management of chemicals and avoidance of oil spillage.

 

Environmental Monitoring and Audit Schedule for the Coming Months

 

6.2               The tentative schedules for environmental monitoring and audit for the next three months are provided in Appendix D. [INCLUDE MONITORING SCHEDULES FOR NEXT THREE REPORTING MONTHS IN APPENDIX C]