Inspection date |
Observation |
Contractor’s Follow-up
Action |
|||
4 |
11 |
18 |
25 |
||
Ö |
|
|
|
A dump truck was observed
leaving the site at Gate 2 without wheel-wash. |
Provide proper wheel-wash
to vehicles leaving the site. |
Ö |
|
|
Ö |
Stockpiles of C&D
waste were found at C6/C66. |
Clear the C&D waste
off-site regularly. |
|
Ö |
Ö |
Ö |
Mud trails observed
outside the site exit at Gate 2. |
Provide wheel-washing at
all site exits. |
|
Ö |
Ö |
|
Skip near Gate 2 was
found full of refuse. |
Remove the refuse
off-site more frequently. |
|
Ö |
Ö |
|
Two oil drums behind the
sub-contractor’s site office were found next to the oil drums. Oil stain was
also found at the u-channel construction area near Chainage 2400. |
Properly store the
chemicals and clear the oil stains. |
|
|
|
Ö |
General refuse and leaves
were found inside the u-channel at C6/C66. |
Clear the waste to
prevent blockage of the drainage channel. |