Appendix N - Complaint Log
Log Ref. |
Location |
Received Date |
Details of Complaint |
Investigation/Mitigation Action |
Status |
30422-1 |
Garden Villa, |
|
The complaint (EPD complaint ref. N01/TN/00004192-03), which was
transferred by EPD to ET on 22nd
April 2003, was raised by a
resident living at Garden
Villa on 22nd April 2003 concerning construction activity during
general holidays (18th to 21st April 2003) at Portion
2C, the concerned works area near Garden Villa at Tai Po Road. |
Based on the monitoring results on The ET will continue monitoring under the EM&A
programme. In case there is any
exceedance or complaint reported, procedures stipulated in the Event Action
Plans and the complaint handling procedure of the EM&A Manual will be
strictly followed. |
Closed |
30506-1 |
Garden Villa, |
|
The complaint (EPD complaint ref. N01/TN/00004856-03), which was
transferred by EPD to ET on 6th
May 2003, was raised by a
resident living at Garden
Villa on 5th May 2003 concerning construction noise during general
holidays (1st May to 4th May 2003) at Portion 2C, the
concerned works area near Garden Villa at Tai Po Road and construction waste
accumulated on the footpath outside Garden Villa. |
No construction work was carried out and A
Construction Noise Permit (CNP no. GW-TN0504-2002) was granted by the Contractor
on The Contractor
has cleared the moulds from the footpath and placed all of them inside the
site boundary upon receiving the complaint on The ET will continue monitoring under the EM&A
programme. In case there is any
exceedance or complaint reported, procedures stipulated in the Event Action
Plans and the complaint handling procedure of the EM&A Manual will be
strictly followed. |
Closed |
30714 |
Garden Villa, |
|
The complaint, which was transferred by
ER to ET on |
The mitigation measures did not apply effective to
prevent the dust generation at the concerned area during the soil nail. It was recommended that ER should continue
monitoring the Contractor to implement the mitigation measures to avoid dust
generation; the Contractor should continue implementing the mitigation
measures to avoid dust generation, and minimize the disturbance generated by
the construction activities at TAR1. |
Closed |
30808 |
|
|
The complaint (EPD Complaint Ref. N01/TN/00011396-03), which was
transferred by the EPD to the ET on |
Based on the information stated in the
Environmental Review Report, the tree cutting activities were considered
necessary and the ecological impact of tree cutting was limited. According to the Contractor’s Method
Statement for tree felling and transplanting, which had been commented from
ET and Engineer Representative (ER), the tree felling and transplanting had
been under the supervision of ER and the tree being felled or transplanted
were clearly labeled.
Photographic records for the tree being affected were kept. Based on the information provided by the
ER, the concerned area mainly included abandoned farm land and an existing
stream covered with grass and shrubs. No individual tree identified to be
retained had been felled. The complaint was considered to be
invalid. |
Closed |
30826 |
Garden Villa |
|
An environmental complaint was received
by the ER on |
According to the ET’s investigation, the
complaint was considered to be valid.
However, there was no noise Limit Level exceedance in August 2003 at
the concerned area. Additional noise measurement conducted on To minimize the noise disturbance from
the rock breaking activities, mitigation measures were then provided by the
Contractor. |
Closed |
30901 |
Garden Villa |
|
A public complaint was received by the
EPD on |
According to the ET’s investigation
report, the complaint was considered to be valid. However, the information provided by
the Contractor stated that no Powered Mechanical Equipment was used on Sunday
except that wire mesh installation works were carried out at the concerned
area. In addition, the measured
noise levels and dust levels were below the respective environmental limit in
August 2003 at the concerned area.
Further dust measurement was conducted on Mitigation measures were recommended to
the Contractor. An additional
regular continuous construction dust monitoring was also recommended and has
been working since |
Closed |
30905 |
Garden Villa |
|
An environmental complaint via the
Honourable Cheng Kar Foo and Leung Wing Hung and was received by TDD on |
According to the ET’s investigation
report, the complaint was considered to be valid. However, the measured noise levels and
dust levels were below the respective environmental limits in August and
September 2003. Mitigation measures were recommended to
the Contractor. An additional
regular continuous construction dust monitoring was also recommended and has
been working since |
Closed |
31003 |
Golden Time
Villa |
|
An environmental complaint was raised by
a resident of Golden Time Villa and was received by TDD on |
According to the ET’s investigation, the
animal wildlife recorded for the Project was limited and no species of
conservation interest was found. Avifauna, reptile, amphibian and butterfly
species in the area were all common in |
Closed |
31229 |
Hin Keng Estate |
|
An environmental complaint was raised by
residents of Hin Keng Estate and was received by EPD (EPD complaint ref.:
N01/TN/00022004-03) on |
According to ET’s investigation report, a
noise measurement at Hin Keng Estate was conducted on ·
space
out noisy equipment and position it as far away as possible from the
sensitive receivers; ·
avoid
concurrent uses of noisy equipment near the sensitive area; ·
ensure
the equipment are maintaining in good operation condition; ·
turne
off any idle equipment on site; ·
provide
mitigation measures to the rock-breaking activities; and ·
continuously
keep ET informed for the construction works to be carried out. |
Closed |
31231a |
|
|
An environmental
complaint was received by EPD (EPD complaint ref. N01/TN/00019795-03) on |
According to Contractor’s information,
the Contractor has implemented mitigation measures to suppress the dust
generation. These include ·
Exhaust
of dump trucks for internal use were slightly verified in order to avoid it
directing to the ground, but horizontally; ·
All
bared slope was hydroseeded; and ·
Frequency
of watering for haul road was increased. |
Closed |
31231b |
|
|
An environmental
complaint was received by EPD (EPD complaint ref. N01/TN/00019858-03) on |
According to Contractor’s information,
the Contractor has implemented mitigation measures to suppress the dust
generation. These include ·
Exhaust
of dump trucks for internal use were slightly verified in order to avoid it
directing to the ground, but horizontally; ·
All
bared slope was hydroseeded; and ·
Frequency
of watering for haul road was increased. |
Closed |
40323 |
|
|
An environmental complaint was received
by EPD on |
According to ET’s investigation report,
the Contractor has enhanced mitigation measures as follows:- ·
Arrange
water spraying during the loading and unloading of dusty materials; ·
Increase
the frequency for haul road watering; ·
Provide
a brush machine to remove the dusty materials on the steep road; ·
Arrange
workers to spray water at rock breaking area; and ·
Arrange
workers at site entrance for wheel washing. No non-compliance of dust level recorded and observed
after implementation of mitigations. |
Closed |
40506 |
Hin Keng Estate |
|
On |
According to ET’s investigation report,
the Contractor has enhanced mitigation measures as follows:- ·
To
cover the gap between the steel sheet panels of the blasting door to reduce
dust nuisance; ·
To
inform Hin Keng Estate of the time of blasting in advance; ·
To
provide water spraying in the blasting door during blasting time; and ·
To
provide acoustic absorption material at the inner surface of the blasting
door. No non-compliance of noise level recorded
and observed after implementation of mitigations. |
Closed |
40517 |
|
|
On |
The complaint was a public complaint at |
Closed |
40630 |
Hin Keng Estate |
|
On |
According to the information provided by the
Contractor, blasting activities were taken place on 23, 26 and The Contractor has erected a blasting door for both
the tunnel before the commencement of blasting works in order to enclose the
dust and reduce the noise level. The blasting door is made of steel plate
with fiberglass filled in between. In addition, a water pipe has been
installed inside the tunnel, which can produce aerosol to form a water screen
for dust suppression. During blasting, water screen will be operated
throughout the period until dust is settled. Water will be sprayed outside
the open ground of the tunnel. The blasting door is only allowed to re-open
at least 15 minutes after blasting. Additional water spraying will be
provided after opening the blasting door. After received the complaint, the Contractor has
installed an additional water screen on |
Closed |
40713 |
Hin Keng Estate |
|
On |
The Contractor
has provided the following mitigations:- ·
To
cover the gap between the steel sheet panels of the blasting door to reduce
dust nuisance; ·
To
inform Hin Keng Estate of the time of blasting in advance; ·
To
provide water spraying in the blasting door during blasting time; and ·
To
provide acoustic absorption material at the inner surface of the blasting
door. Based on the information provided by the ER on |
Closed |
40723 |
Garden Villa |
|
On |
On 26 July 2004, the Contractor has relocated the
truck queue from top of TAR1 to downhill in front of wheel washing bay, where
is much far away from Garden Villa. The increased notional distance is about
200m. A noise measurement was conducted on the same day at |
Closed |
41201 |
Construction
site which near K. K. Terrace |
|
Complaint
regarding the noise nuisance was received on |
According to
the RSS and the Contractor, one unit Rock Drill (hydraulic)
was operated inside T1N tunnel and one unit Pneumatic Breaker was operated
inside T2N tunnel during the time period of There is
insufficient evidence to establish the complaint based on the available
information from the “Notice of Complaint”, the RSS, the Contractor and
monitoring records. However, it is recommended the Contractor should notify
the nearby residents in advance with the working schedule of construction
work during restricted hours and strictly comply with all noise mitigation
measures. |
Closed |
50308 |
Garden Villa |
|
Complaint
regarding the noise and dust nuisance was received on 8th March 2005at |
Dust: According to the site inspection on The Contractor should also cover the trucks with canvas sheet once the
C&D waste was laden before passing adjacent to Garden Villa. The Contractor should strictly
implement the penalty system and further review and tighten up the system if
no obvious improvement is made. Noise:
Based on the available
information, no sufficient evidence could establish the noise complaint from
the “Notice of Complaint”, the Contractor and monitoring records. The Contractor
was recommended to notify the nearby residents in advance of the working schedule of construction
work during the restricted hours and strictly comply with all necessary noise
mitigation measures. |
Closed |
50330 |
Garden Villa |
|
Complaint
regarding the noise nuisance was received on |
According to
the information provided by the Resident Site Staff, trucks from R8-SHT
contract are not allowed to exit via TAR1 before |
Closed |
50425 |
|
|
Complaint
regarding the dust nuisance was
received on |
The records of
the RSS and the Contractor showed that blasting works have been conducted on the
date of complaint ( According to
the Contractor’s investigation, a reversion of tunnel air flow was observed
due to seasonal change, such that air kept flowing from the direction of
Garden Villa towards Upon receipt
of the complaint, all blasting works were stopped until water curtain for
tunnel tubes in the 1.
the area within 30m from the blasting area will
be wetted with water prior to blasting; 2.
sufficient time will be allowed for dust to
settle before opening the blasting protection doors; and 3.
water curtain will be operated. Based on the site observed, the RSS considered that the implemented
measures by the Contractor were effective. |
Closed |
50509 |
The Police |
|
Complaint
regarding the noise nuisance was
received on |
The records of
the ER and the Contractor showed that bridge launching operation was being
carried out over the East and Ma On Shan (MOS) Rail near Tai Wai Deport during
the time of concern. CNP no. GW-RN0140-05
was issued to the Contractor in accordance with the Noise Control
Ordinance. According to the
Contractor’s information, the PME groups D to K of the CNP were operated intermittently
during that night. In addition, it was complied with Condition 3di of CNP.
Also, there is no action or limit level exceedance was recorded based on the
record from ET. Nevertheless, the Contractor was reminded to ensure the compliance of
CNP conditions for carrying out construction work during restricted
hours. The following measures are
proposed: ·
Trainings
shall be provided to the site supervisors, frontline staff and relevant
subcontractors as regards the conditions stipulated in the CNPs obtained as
well as the relevant requirements stipulated in the Noise Control Ordinance. ·
The Contractor shall establish and implement a
checking system for carrying out construction works during restricted
hours. The conditions stipulated
in the CNP shall be checked by a designated staff on site. The effectiveness of the system shall
be reviewed regularly. |
Closed |
50509 |
The Police |
|
|
The Contractor was also reminded to
continuously implement their practice as regards the advance notification to
the nearby residents of the night time works. In addition, the Contractor should adopt
good site practice to minimize the construction noise impact, such as: ·
To space out noisy equipment and position it as
far away as possible from the sensitive receivers; ·
To avoid concurrent uses of noisy equipment near
the sensitive area; ·
To ensure the equipment are maintaining in good
operation condition; and ·
To turn off any idle equipment on site. |
Closed |
50513 |
Golden Villa |
|
Complaint
regarding the noise nuisance at the representative of residents of Golden
Villa was received on |
The site of
concern was likely to be the Sha Tin Height Tunnel. According to the Contractor’s
information, tunnel excavation works including the rock drill and charging of
explosive were undertaken after 2300 hours in the tunnels. It was believed
that the nuisance was caused by the vibration due to drilling works. The
nuisance was more significant as the excavation face at south bound tunnel
came closer towards Upon receipt
of the complaint, the Contractor had already stopped all drilling works after
|
Closed |
51026 |
Exit of TAR1 next to |
|
Complaint was
received by CEDD on |
After the site
investigation by the RSS, it was confirmed that the source of the muddy water
was this newly constructed wheel washing bay. Water in the wheel washing bay was
brought onto the ensuing concrete pavement by lorries passing through it and
the water fall onto The complaint
was considered valid and corrective and preventive actions were taken by the
Contractor: 1.
all vehicles exiting from TAR1 were stopped using
the wheel washing bay to prevent any further overflowing of muddy water from
the bay. 2.
a water browser was immediately deployed by the
Contractor to clear the muddy water and the debris deposited on the concerned
section of 3.
A concrete bund was constructed along the lower
side of the wheel washing bay to reduce the amount of water overflowing. 4.
a small ditch was formed across the lower side of
the vehicular exit in order to collect the overflowed water and prevent it
from falling onto public road. The Contractor
was reminded to closely monitor the situation and review the effectiveness of
the mitigation measures. |
Closed |
51118 |
Near |
A complaint of same nature was forwarded by EPD on 29th Nov
05. |
Complaint
regards the nighttime construction noise due to construction works near |
As advised by
RSS, at the concern ( According to
the RSS, a valid CNP no. GW-RN0436-05 has been checked. All the PME and the type of lorry
involved in the works complied with the CNP requirements. The complaint
was considered valid and preventive actions were taken by the Contractor: 1.
re-spected the steel plates installed at the
movement joints of the bridge deck and ensured that they are securely fixed.
Such as , install steel bars to fix the steel plates. 2.
rubber pads will be provided at the movement
joints to minimize noise generation due to vibration of the steel plates. 3.
close supervision to ensure care handling of
construction materials will be provided on site. As advised by
the RSS, the bridge launching work has been completed and no similar type of
work will be carried out during the nighttime in future. |
Closed |
60207 |
|
|
The complaint
was concerned the construction dust and noise generated from a construction
site near Tin San Village during daytime between 0700 hours and 1900 hours.
It was received on |
According to
the RSS, the site of concern was the Proposed Retaining Wall No.5 (located at
The ET had
arranged ad-hoc noise measurements on 8th, 9th, 14th
and 16th Feb 06 at The complaint
was considered valid and rectification actions were taken by the Contractor,
including: a) All flaps of
the air compressors would be closed all the time; b) Idled machines
would be switched to minimize generation of unnecessary noise; c) Two air
compressors were relocated to farther area on 8 Feb 06; d) Temporary
noise barriers were erected on 11 Feb 06; e) Self
monitoring of noise levels during the pilling operation; f)
Additional dust screens were installed along the
public road on 8 Feb 06; g) Public notices
were distributed to the residents and the business establishment at During ET’s ad-hoc inspections, the abovementioned mitigation measures
were found in place and the public footpath beside the site areas was found clean
and free dusty materials. As advised by the Contractor, a total of 10 piles are required to be
constructed for the Proposed Retaining Wall No.5, thus this pilling activity
would be completed by April 2006.
The situation would be continuously reviewed by the Contractor, RSS
and the ET. |
Closed |
60501 |
North and south bound
carriageway of |
|
The complaint
was referred by ER on |
According to
ER’s record, the major construction activity at the concerned area was the
underground drainage work at When heavy
vehicles passed over the decks, the noise was generated due to clashing of
the steel plates. It was the source of noise nuisance. The complaint
was considered valid and corrective and preventive actions were taken by the
Contractor: 1.
Conducted inspection to the temporary steel
plates; and 2.
Steel plates were welded together and fixed in
position. In addition,
the Contractor had informed the complaint that mitigation measures were
taken. No further complaint on
the same issue had been received again. During ET’s ad-hoc inspections, the abovementioned mitigation measures
were found in place. As advised by
the RSS, the drainage works would be completed at the concerned area by the
end of August 2006. Thus, the
Contractor was reminded to continuously implement their practice to prevent
noise nuisance generation due to the construction works. |
Closed |
60626 |
near |
|
The Complaint
was received by EPD on 19th June 2006 and referred to ET Team on 26th
June 2006, which was about general construction noise and flytipping/dumping
of construction wastes caused by construction work near Tin Sum Village, at
Che Kung Miu Road. |
According to
the ER’s record, the major construction activities included lying of drain
pipe, removal and erection of framework.
However, only hand held tools were used when formwork were erected to
wall of RW5 Bay 12& 14. As advised by
the RSS, the waste skip was provided to stock some timbers at the concerned
area. i.e. beside the KCRC boundary wall. Besides, on
load of construction waste was disposed on Site
inspection on the Contractor’s mitigation measure was carried out by ET on 28th
and Base on the
information collected, the complaint was considered not justifiable. However, the
Contractor was reminded to continuously provide good site practice to
minimize construction noise/waste impact. |
Closed |
60828 |
Sha Tin Heights Southern
Tunnel near |
|
The public complaint
was received on |
According to
the RSS information, the Southbound Tunnel was not for traffic and water
spray onto road surface was implemented at least once a day. According to the Contractor’s information, the Northbound Tunnel was currently used as a vehicle access to
the A site inspection was conducted on Based on the
above information, the complaint was considered to be invalid. However, the
Contractor was reminded to continuously provide good site practice to
minimize construction air impact. |
Closed |