1.1
Sha Tin Heights Tunnel and Approaches (SHT) (hereinafter
the Project) forms part of the Route 8 (Formerly Route 9) between Cheung Sha Wan and Sha Tin project,
which will be a new expressway connecting west Kowloon
and Sha Tin. It will be the fourth external link
between Sha Tin and
1.2
The Project works mainly comprise the
site formation for a toll plaza at the valley of Sha
Tin Heights, the construction of
1.3 The Route 8 (Formerly Route 9) (between Cheung Sha Wan and Sha Tin) project is a Designated Project under the Environmental Impact Assessment Ordinance (Cap. 449, EIAO). An environmental impact assessment (EIA) report had been prepared in 1998 for the Route 8 (Formerly Route 9) project to consider the key issues of noise, air quality, water quality, ecological, construction waste, landscape and visual, land use and culture impacts, and identify possible mitigation measures. An updated Final EIA report was subsequently completed in August 1999 to cater for some changes in the main portion. The 1998 and 1999 Route 8 (Formerly Route 9) EIA (R9 EIA Reports) reports were included in the EIA register under the EIAO as report number EIA-135/BC and AEIAR-022/1999 respectively. EM&A Manuals for each of the R9 EIA reports were also included as part of the EIA reports in the register.
1.4
Subsequent to the endorsement
of the R9 EIA reports by EPD in November 1999, the R9 project was deferred to
start in 2002/2003 for completion by 2006/07. The implementation of the Route 8
(Formerly Route 9) project was then separated into the SHT and R9K
portions. Meanwhile further design
amendments had also been proposed for the R9S during the detailed design stage
to resolve various engineering constraints. In view of these changes, an
Environmental Review on the SHT was undertaken to update the findings of the R9
EIA reports. The Environmental
Review report for SHT was completed in September 2001 and an Environmental
Permit No. EP-104/2001 was issued on
1.5
The works of the SHT is
constructed under CEDD’s construction Contract No. ST
89/02 “
1.6 Cinotech Consultants Limited (Cinotech) was commissioned by CEDD to undertake the Environmental Team (ET) Services for the Project. This is the forty-seventh monthly EM&A report summarizing the EM&A works for the Project in September 2006.
Project Organizations
1.7 Different parties with different levels of involvement in the project organization include:
·
Project Proponent –
· Engineer or Engineer’s Representative (E/ER) – Maunsell Consultants Asia Limited (MCAL)
· Environmental Team (ET) – Cinotech Consultants Limited
·
Independent Environmental
Checker (IEC) – CH
· Contractor – China State-China Railway Joint Venture
1.8 The responsibilities of respective parties are detailed in Section 2 of the EM&A Manual (1998) and Section 1.8 of the EM&A Manual (1999). The project organization chart is presented in Figure 3.
1.9 The key contacts of the Project are shown in Table 1.1.
Table 1.1 Key
Project Contacts
Name |
Role |
Phone
No. |
Fax
No. |
|
CEDD |
Ms.
Joanna Kwok |
Permit
Holder |
2301 1383 |
2739 0076 |
Mr.
Robert Choy |
Project
Coordinator |
2301 1373 |
2721 8630 |
|
MCAL |
Mr.
Francis Leong |
The
Engineer |
2685 6517 |
2691 2649 |
Mr.
K.Y. Chan |
Engineer’s
Representative |
9750 0557 |
2697 4106 |
|
Mr.
S. K. Lo |
9751 9638 |
2697 4106 |
||
ET |
Dr.
Priscilla Choy |
The
ET Leader |
2151 2083 |
3107 1388 |
Ms.
Attle Hui |
Audit
Team Leader |
2151 2093 |
3107 1388 |
|
Mr.
Henry Leung |
Monitoring
Team Leader |
9779 7340 |
3107 1388 |
|
IEC |
Mr.
David Yeung |
Independent
Environmental Checker |
2507 2203 |
2507 2293 |
Contractor |
Mr.
David Lau |
Senior
Project Manager |
2601 7917 |
2697 1592 |
24-hour
Hotline |
9759 9852 |
- |
1.10 The construction activities undertaken in the reporting month were:
·
Bridge works;
·
Construction of Retaining Wall at CKM;
·
Rising existing manhole level at CKM;
·
Drainage works; and
·
Demolition of
1.11 The EM&A programme requires construction phase monitoring for air quality and noise and environmental site audit. The EM&A requirements for each parameter are described in following sections, including:
· All monitoring parameters;
· Action and Limit levels for all environmental parameters;
· Event / Action Plans;
· Environmental mitigation measures, as recommended in the project EIA study final report; and
· Environmental requirements in the contract documents.
1.13 This report presents the monitoring results, observations, locations, equipments, periods, methodologies and QA/QC procedures of the required monitoring parameters, namely dust and noise levels and audit works for the Project in September 2006.