TABLE OF CONTENTS
Environmental Monitoring Works
Implementation Status of Environmental
Mitigation Measures
Environmental Complaints and Prosecution
Summary of the EM&A Requirements
Implementation Status
of Environmental Mitigation Measures
Status of
Environmental Licensing and Permitting
Implementation Status
of Environmental Complaint Handling Procedures
3. CONCLUSIONS AND
RECOMMENDATIONS
List of Tables
Table 2.1 Summary
of Environmental Notification, Licensing and Permit Status
List of
Figures
Figure 1.1 Location of Water Recreation Centre
Figure 1.2 Project Organization
List of Appendices
Appendix A Contact of Key Environmental Personnel
Appendix B Summary of Environmental Mitigation Implementation Schedule
Appendix C Complaint Flow Diagram and Complaint Log
This is the hundred-second monthly Environmental Monitoring and Audit
(EM&A) report prepared by AECOM Asia Co. Ltd. (integrating the operation of
ENSR Asia (HK) Ltd.), the designated Environmental Team (ET), for the project “Provision
of EM&A Services at Water Recreation Centre”. The Water Recreation Centre (WRC) commenced operation on 16 August
2005.
This report presents
the results of environmental audit works conducted between 16 January 2014 and
15 February 2014.
Environmental Licensing and Permitting
Environmental permit (No. EP-01/097/2001/C)
was issued to the Hongkong International Theme Parks Limited (
Monthly
environmental site inspection was carried out on 13 February 2014. Environmental
mitigation measures as recommended in the EIA report, Operational EM&A Plan
and EP-01/097/2001/C were
properly implemented.
No
complaint, summons or prosecution related to environmental issues was made
against the Project in the reporting period.
The operator of WRC
is reminded to continue to implement measures as recommended in the EIA Report, Operational EM&A Plan and
EP-01/097/2001/C.
1.1
AECOM Asia Co. Ltd. (integrating the operation of ENSR Asia (HK) Ltd.) (hereinafter referred as the “ET”) was appointed by Hongkong International Theme Park Ltd. (
1.2
The WRC is a portion of the Contract for “Theme Park and Associated
Infrastructures at Penny’s Bay”, which encompasses an area of approximately
1.3
Following approval of the EIA, an Environmental Permit (EP) was issued
to the Civil Engineering Department (CED) (now Civil and Engineering
Development Department (CEDD) and the subsequent variation of the permit no.
EP-097/2001/B and EP-138/2002/C contain the requirements and obligations on the
Environmental Monitoring and Audit (EM&A) during the operation of the WRC.
Under the Contract for “Theme Park and Associated Infrastructures at Penny’s
Bay”, the WRC and ancillary facilities were designed and constructed under the
supervision of CEDD and the WRC would be turned over from CEDD to
1.4
This report presents the results of environmental audit works conducted
between 16 January 2014 and 15 February 2014.
1.5
The structure of the environmental management team is
shown in Figure 1.2. Contacts of key environmental staff of the Project are
shown in Appendix A.
1.6 The latest EM&A programme requires environmental audit at the WRC. The purpose of the audit was to ensure all environmental mitigation measures, as recommended in the EIA report, Operational EM&A Plan and EP-01/097/2001/C, were properly implemented.
1.7
Site audit and the status of environmental licensing
and permits are described in Section 2.
1.8
Summary of the advice on the implementation status of
environmental protection and pollution control/mitigation measures is
summarised in Section 2 of the Report.
2.1
Site audit was carried out on a
monthly basis to monitor environmental issues to ensure that all mitigation
measures were implemented timely and properly.
2.2
Monthly site inspection was
carried out on 13 February 2014. Environmental
mitigation measures for water quality, waste management, landscape
and visual, as recommended in the EIA report, Operational EM&A Plan and EP were properly implemented. There
was no specific observation requiring following up action. In general, the
condition of the WRC was satisfactory:
·
No floating
refuse was observed.
·
No uncontrolled surface runoff into the lake was
observed.
·
No algicide was applied to the WRC.
·
No discharge was made from the WRC
into marine water.
·
No improper storage of oil/chemicals
was observed.
·
Environmental
Permit was kept in the site office and was available for inspection upon
request.
2.3
A summary of
the Environmental Mitigation Implementation Schedule (EMIS) is presented in
Appendix B.
2.4
All
permits/licences/notifications obtained as of the reporting period are
summarised in Table 2.1
Table 2.1 Summary of
Environmental Notification, Licensing and Permit Status
Permit No. |
Valid Period |
Description |
Status |
|
From |
To |
|||
Environmental
Permit |
||||
EP-01/097/2001/C |
19 Oct. 05 |
- |
Operation of an approximately |
Valid |
Chemical
Waste Registration |
||||
9499-973-H3095-01 |
29 Jul. 05 |
- |
Theme
Park at Penny’s Bay |
Valid |
2.5
Waste management of WRC was implemented as stipulated
in the Waste Management Plan.
2.6
As waste management of WRC was undertaken as part of
the overall Theme Park Resort waste management scheme, records of waste
handling and disposal would be reported in the Theme Park EM&A Report.
2.7
Appendix C presents the
environmental complaint flow diagram of the Project.
2.8
No complaint, summons or prosecution related to
environmental issues was received or made against the Project in the reporting
period.
3.1
Environmental audit was carried out on 13 February 2014
in accordance with the Operation EM&A Plan. No non-compliance was observed
during the inspection. In general, the
condition of the WRC was satisfactory.
3.2
Environmental mitigation measures as recommended
in the EIA Report, Operational EM&A Plan and EP were properly
implemented.
3.3
No complaint, summons or prosecution related to
environmental issues was made against the Project in the reporting period.
3.4 The operator of WRC is reminded to continue to implement measures as recommended in EIA Report and EP.