EXECUTIVE SUMMARY

 

Introduction

 

This is the fifth monthly Environmental Monitoring and Audit (EM&A) report prepared by Maunsell Environmental Management Consultants Limited (MEMCL) for the “Temporary Construction Waste Sorting Facility at Tseung Kwan O Area 137” (the Project). This report documents the findings of EM&A Works conducted during the impact period in March 2006 for Tseung Kwan O Area 137.

 

As advised by the Contractor, the project commenced on 12 November 2005. The construction activities in March 2006 were:

 

l             Temporary access road construction including road kerb and U-channel;

l             Widening of temporary access road;

l             Installation of surveillance system and public address system;

l             Construction of Engineer’s site office and car parking area;

l             Operation of Construction Waste Sorting Facilities (CWSF) by manual sorting; and

l             Installation of steel fence along the access road.

 

Environmental Monitoring Works

 

Air Quality

 

1-hr TSP Monitoring

 

All the monitoring data complied with the AL levels in the reporting month. The 1-hr TSP monitoring results remained at an acceptable level during the construction of the temporary CWSF.

 

24-hr TSP Monitoring

 

There were three limit level exceedances recorded on 13, 24 and 30 March 2006 at monitoring station TKO1. Exceedances recorded were considered related to the Project.

 

Complaints, Non-compliance and Prosecutions

 

No environmental complaints, non-compliances or prosecutions were received in the reporting month.

 

Permits and Licences

 

No new permit or license was obtained / applied in the reporting month.

 

Environmental Site Inspection

 

Site inspections were carried out weekly by the ET to ensure proper implementation of environmental mitigation measures specified in the EM&A Manual and compliance with relevant environmental legislation.

 

There were 5 site inspections conducted in March 2006. Due to the dry weather condition, fugitive dust was occasionally observed along the haul road. Dust was also generated during transferring and dumping of materials. Water spraying should be provided to all dusty operation and the water spraying frequency should be increased.

 

The trapezoidal channel was filled with waste, the Contractor agreed to remove all waste in the channel by April 2006. Water ponding was found outside the site office after rain events and stagnant water was found inside the trapezoidal channel at Area A. The Contractor was reminded to clear the stagnant water. Rubbish scattered in Area A should also be cleared.

 

Future Key Issues

 

The weather is expected to be wet and windy in the forthcoming month and as such, the Contractor should provide preventive measures to prevent surface runoff, such as bunding around the site boundaries ensure functional temporary drainage system is in place around the site and to maintain sufficient dust suppression measures for vehicle movement along haul roads and during sorting activities. It is recommended to implement sufficient mitigation measures to eliminate dust emission from dump truck traffic and sorting activities.

 

It is also recommended to implement all necessary preventive measures to avoid oil leakage on ground/soil, such as provision of drip trays for all oil drums/chemical containers and placement of tarpaulin sheets on the ground during maintenance of equipment on site. In the event of any oil leakage problem, the Contractor should properly remove the leaked oil and handle the contaminated soil as chemical waste.