2.0               PROJECT INFORMATION

 

2.1               Scope of the Project

 

The scale and scope of the Project as stated in the EP include:

§         Site clearance;

§         Construction of a temporary storm water system;

§         Stockpiling of 6 million m3 of public fill;

§         Setting up two barging points: one at the Tseung Kwan O Basin (TKO Basin) and one at the Construction and Demolition Material Sorting Facility (C&DMSF) for transporting the stockpiled public fill by barges;

§         Setting up a temporary barging point at the existing Explosive Off-loading Barging Point located in the south-eastern part of Area 137 for the period of May 2004 to December 2004 for transporting the stockpiled public fill by barge;

§         Construction and operation of a Construction and Demolition Material Sorting Facility (C&DMSF);

§         Setting up a Construction and Demolition Material Crushing Facility at the TKO Basin; and

§         Remove the temporary fill bank.

 

2.2               Site Description

 

Tseung Kwan O Area 137 is located at the southern end of Wan Po Road. In the vicinity of the site are other industrial uses such as SENT landfill, TKO Industrial Estate, etc. Both Island Resort and Fullview Garden are also situated at more than 1.8km from the site. Other existing ASRs and NSRs, including resident developments and schools, are located at a further distance away from TKO Area 137.

 

2.3               Construction Programme

 

Details of construction programme are shown in Appendix G.

 

2.4                   Project Organization and Management Structure

 

The organization chart and lines of communication with respect to the on-site environmental management and monitoring program are shown in Appendix A.

 

2.5       Contact Details of Key Personnel

 

The key personnel contact names and telephone numbers are shown in Table 2.1.

 

Table 2.1           Contact Details of Key Personnel

Organization

Name of Key Staff

Project Role

Tel. No.

Fax No.

CEDD

Mr. Roy Tse

Engineer

2623 9268

2714 0113

IEC (BMT)

Mr Ben Ridley

IEC

2815 2221

2815 3377

Contractor (CCL)

Mr. C P Lam

Project Manager

2398 8001

9212 9417

2398 8301

ET (ETL)

Mr C. L. Lau

ET Leader

2946 7791

2695 3944