4.0
AIR QUALITY MONITORING
4.1 Monitoring
Requirement
TSP levels were
monitored in the reporting month in accordance with the EM&A Manual. Table
4.5 shows the Action and Limit Levels for the environmental monitoring works.
4.2 Monitoring Equipment
Both
1-hour and 24-hour TSP air quality monitoring was performed using a GMWS2310
High Volume Air Sampler (HVS) located at each of the designated monitoring
station. Table 4.1 summarizes the equipment used in the air quality monitoring
programme. A copy of the calibration certificates for the HVS and portable dust
meter are attached in Appendix B1.
Table 4.1 Air Quality Monitoring Equipment
Equipment |
Model and Make |
HVS |
Greasby GMWS2310 |
Calibrator |
Tisch TE-5025A |
Wind Data Logger |
Davis Weather Monitor II |
4.3 Monitoring Parameters, Frequency and Duration
Table 4.2 summarizes the monitoring parameters, monitoring duration and
frequencies of air quality monitoring.
Table
4.2 Monitoring parameters,
duration, frequency of air quality monitoring
Parameter |
Duration |
Frequency |
24-hr
TSP |
24 hr |
Once
every six days |
1-hr TSP |
1 hr |
Three
times per day every six days |
4.4 Monitoring Locations and Schedule
Table
4.3 tabulates the air quality monitoring locations of this project.
Table 4.3 Air quality
monitoring locations
Monitoring station |
Location |
AA1 |
Outside CEDD Site Office |
AA2 |
Site Egress |
During
the reporting month, 1-hr and 24-hr TSP monitoring were carried out as the
schedule. The details for 24-hr
and 1-hr TSP monitoring carried out in this reporting month are
summarized in table 4.4.
Table
4.4 Monitoring Schedule for the
air quality monitoring stations
Air quality monitoring stations |
Location |
Monitoring
Period |
|
||||||||||
24-hr TSP |
1-hr TSP |
|
|||||||||||
Start |
Finish |
Date |
Start |
Finish |
|
||||||||
Date |
Time |
Date |
Time |
|
|||||||||
AA1 |
Outside
CEDD Site Office |
--- |
02/03/06 |
11:00 |
12:00 |
||||||||
13:00 |
14:00 |
||||||||||||
15:00 |
16:00 |
||||||||||||
08/03/06 |
08:30 |
09:30 |
|
||||||||||
09:40 |
10:40 |
|
|||||||||||
11:00 |
12:00 |
|
|||||||||||
14/03/06 |
11:00 |
12:00 |
|
||||||||||
15:30 |
16:30 |
|
|||||||||||
16:40 |
17:40 |
|
|||||||||||
20/03/06 |
11:00 |
12:00 |
|
||||||||||
13:15 |
14:15 |
|
|||||||||||
14:30 |
15:30 |
|
|||||||||||
24/03/06 |
11:00 |
12:00 |
|
||||||||||
13:00 |
14:00 |
|
|||||||||||
14:02 |
15:02 |
|
|||||||||||
30/03/06 |
09:45 |
10:45 |
|
||||||||||
11:00 |
12:00 |
|
|||||||||||
13:00 |
14:00 |
|
|||||||||||
AA2 |
Site Egress |
--- |
02/03/06 |
11:00 |
12:00 |
|
|||||||
13:00 |
14:00 |
|
|||||||||||
15:00 |
16:00 |
|
|||||||||||
08/03/06 |
08:30 |
09:30 |
|
||||||||||
09:40 |
10:40 |
|
|||||||||||
11:00 |
12:00 |
|
|||||||||||
14/03/06 |
11:00 |
12:00 |
|
||||||||||
15:30 |
16:30 |
|
|||||||||||
16:40 |
17:40 |
|
|||||||||||
20/03/06 |
11:00 |
12:00 |
|
||||||||||
13:15 |
14:15 |
|
|||||||||||
14:30 |
15:30 |
|
|||||||||||
24/03/06 |
11:00 |
12:00 |
|
||||||||||
13:05 |
14:05 |
|
|||||||||||
14:07 |
15:07 |
|
|||||||||||
30/03/06 |
09:45 |
10:45 |
|
||||||||||
11:00 |
12:00 |
|
|||||||||||
13:00 |
14:00 |
|
|||||||||||
AA1 |
Outside
CEDD Site Office |
02/03/06 |
16:15 |
03/03/06 |
16:55 |
--- |
|
||||||
08/03/06 |
12:15 |
09/03/06 |
12:24 |
|
|||||||||
14/03/06 |
17:50 |
15/03/06 |
17:42 |
|
|||||||||
20/03/06 |
16:00 |
21/03/06 |
16:07 |
|
|||||||||
24/03/06 |
15:04 |
25/03/06 |
15:01 |
|
|||||||||
30/03/06 |
14:15 |
31/03/06 |
14:49 |
|
|||||||||
AA2 |
Site
Egress |
02/03/06 |
16:15 |
03/03/06 |
16:56 |
--- |
|
||||||
08/03/06 |
12:15 |
09/03/06 |
12:22 |
|
|||||||||
14/03/06 |
17:50 |
15/03/06 |
18:00 |
|
|||||||||
20/03/06 |
16:00 |
21/03/06 |
16:50 |
|
|||||||||
24/03/06 |
15:09 |
25/03/06 |
15:11 |
|
|||||||||
30/03/06 |
14:15 |
31/03/06 |
14:16 |
|
|||||||||
4.5 Monitoring Methodology
Both 1-hr and 24-hr air quality
monitoring (High Volume Sampler)
Instrumentation
High volume sampler, as HVS, (Greasby GMWS2310) complete
with appropriate sampling inlets were employed for both 1-hour and 24-hour TSP
monitoring. The sampler is composed of a motor, a filter holder, a flow
controller and a sampling inlet and its performance specification complies with
that required by USEPA standard Title 40, Code of Federation Regulations
Chapter 1 (Part 50).
Installation
The installation of HVS refers to the
requirement stated in EM&A Manual.
Operation/Analytical
Procedures
Operating/analytical procedures
for the operation of HVS are as below:
Prior to the commencement of the
dust sampling, the flow rate of the high volume sampler was properly set
(between 0.6m3/min and 1.7m3/min.) in accordance with the
manufacturer’s instruction to within the range recommended in USEPA Standard
Title 40, CFR Part 50.
·
For TSP sampling, fiberglass
filters (GA-55) were used.
·
The power supply was checked to
ensure the sampler worked properly.
·
On sampling, the sampler was
operated 5 minutes to establish thermal equilibrium before placing any filter
media at designated air monitoring station.
·
The filter holding frame was
then removed by loosening the four nuts and carefully a weighted and
conditioned filter was centered with the stamped number upwards, on a
supporting screen.
·
The filter was aligned on the
screen so that the gasket formed an air-tight seal on the outer edges of the
filter. Then the filter holder frame
was tightened to the filter holder with swing bolts. The applied pressure
should be sufficient to avoid air leakage at the edges.
·
The programmable timer will be
set for a sampling period of 24 hours.
Information was recorded on the record sheet, which included the
starting time, the weather condition and the filter number (the initial weight
of the filter paper can be found out by using the filter number.).
·
After sampling, the filter was
transferred from the filter holder of the HVS to a sealed plastic bag and sent
to the laboratory for weighting. The
elapsed time was also recoded.
·
Before weighting, all filters
were equilibrated in a desiccator for 24 hour with the temperature of 25oC
+ 3oC and the relative humidity (RH) <50% +5%.
·
All measurement procedures in
Section 2.3 of the EM&A Manual were followed during the reporting month.
Maintenance
& Calibration
·
The HVS and their accessories
should be maintained in good working condition, such as replacing motor brushes
routinely and checking electrical wiring to ensure a continuous power supply.
·
HVS should be calibrated at
bi-monthly intervals.
Wind Data Monitoring
Measuring
Procedure
Upon
installation of the wind data logger on site, temperature, wind speed and
direction was automatically stored in the logger. Regular downloading of the
information was carried out weekly.
Maintenance
Cleaning
was provided for all the rotational parts of the wind data logger regularly.
Replacement of battery was carried out weekly. The wind data logger was checked
once per week and no calibration was required for the equipment as instructed
by the manufacturer.
4.6 Action and Limit Levels
Table
4.5 shows the Action and Limit levels for 24-hr TSP and 1-hr TSP monitoring.
Table 4.5 Action and Limit Levels for 24-hr TSP and 1-hr TSP
Monitoring Location |
24-hr TSP (mg/m3) |
1-hr TSP (mg/m3) |
||
Action Level * |
Limit Level * |
Action Level * |
Limit Level * |
|
AA1 |
210 |
260 |
376 |
500 |
AA2 |
210 |
260 |
376 |
500 |
* Traceable to Method Statement (Environmental
Monitoring and Audit Manual) of Contract No.CV/2002/08, Rev. 2
4.7 Event-Action
Plans
Please
refer to Appendix F for details.
4.8 Results and Observation
4.8.1 1-hour and 24-hour TSP Monitoring results
All
monitoring data of both 1-hour and 24-hour TSP monitoring is provided in
Appendix B2. Graphical presentation of 1-hour and 24-hour TSP monitoring
results for the reporting month is shown in Appendix B3. Wind data, including
wind speed and wind direction, are annexed in Appendix E. Table 4.6 summarizes
1-hr TSP and 24-hr TSP monitoring results.
Table
4.6 Summary of 1-hr TSP and 24-hr
TSP Monitoring Results
Air quality monitoring Stations |
Location |
Monitoring
Period |
||||||
24-hr TSP |
1-hr TSP |
|||||||
Date |
Result (mg/m3) |
Exceedance # |
Date |
Start Time |
Result (mg/m3) |
Exceedance # |
||
AA1 |
Outside
CEDD Site Office |
02/03/06 |
202 |
X |
02/03/06 |
11:00 |
345 |
X |
13:00 |
336 |
|||||||
15:00 |
309 |
|||||||
08/03/06 |
175 |
X |
08/03/06 |
08:30 |
315 |
X |
||
09:40 |
332 |
|||||||
11:00 |
359 |
|||||||
14/03/06 |
171 |
X |
14/03/06 |
11:00 |
362 |
X |
||
15:30 |
322 |
|||||||
16:40 |
308 |
|||||||
20/03/06 |
192 |
X |
20/03/06 |
11:00 |
370 |
X |
||
13:15 |
352 |
|||||||
14:30 |
344 |
|||||||
24/03/06 |
192 |
X |
24/03/06 |
11:00 |
358 |
X |
||
13:00 |
347 |
|||||||
14:02 |
335 |
|||||||
30/03/06 |
202 |
X |
30/03/06 |
09:45 |
325 |
X |
||
11:00 |
374 |
|||||||
13:00 |
362 |
|||||||
A2 |
Site Egress |
02/03/06 |
194 |
X |
02/03/06 |
11:00 |
330 |
X |
13:00 |
318 |
|||||||
15:00 |
285 |
|||||||
08/03/06 |
168 |
X |
08/03/06 |
08:30 |
282 |
X |
||
09:40 |
314 |
|||||||
11:00 |
352 |
|||||||
14/03/06 |
162 |
X |
14/03/06 |
11:00 |
371 |
X |
||
15:30 |
351 |
|||||||
16:40 |
314 |
|||||||
20/03/06 |
188 |
X |
20/03/06 |
11:00 |
366 |
X |
||
13:15 |
360 |
|||||||
14:30 |
328 |
|||||||
24/03/06 |
191 |
X |
24/03/06 |
11:00 |
354 |
X |
||
13:05 |
343 |
|||||||
14:07 |
320 |
|||||||
30/03/06 |
195 |
X |
30/03/06 |
09:45 |
336 |
X |
||
11:00 |
368 |
|||||||
13:00 |
357 |
Remark
(#): L=Limit Level exceedance, A=Action Level exceedance and X= not
an exceedance
No exceedances of Action and Limit Level of both 1-hour and
24-hour TSP monitoring results were recorded during the reporting month.
4.8.2 Observation
Generally, the Contractor implemented sufficient dust
mitigation measures, including operation of the mist spraying systems at the
CEDD Combined Reception Office and the site egress area, wheel washing
facilities, road dampening by water bowsers and automatic water sprinklers on
the main haul roads. Furthermore, hydroseeded slopes on the stockpiling areas
was maintained properly in order to prevent dust generation from wind erosion
of the exposed surfaces. Besides the Fill Bank operation, the other dust
sources near TKO Area 137 also included operation of the C&DMSF at PBR2
Project, the temporary C&DMSF at Portion K and dumping activities at the
SENT Landfill.