Executive
SUMMARY
This is the third
monthly Environmental Monitoring and Audit (EM&A) report prepared by
ETS-Testconsult Ltd (ET) for the “Contract No. CV/2005/12 Operation of Public
Fill Reception Facilities at Tseung Kwan O Area 137, Quarry Bay and Mui Wo”
(The Project).
This report
documented the findings of EM&A Works conducted during the operation phase
of Fill Bank at Tseung Kwan O Area 137 in March 2006.
Construction
Progress
As informed by
the Contractor, the construction activities in this reporting month were as
below:
§
Manage the incoming public fill dump
trucks arriving through land access;
§
Transport temporary stockpiled public
fill from the Barge Handling Area (BHA) to Stockpile Areas or the Sorting
Facility for Penny’s Bay Reclamation Stage 2 (PBR2);
§
Transport stockpile public fill from
Stockpile Areas to the Sorting Facility for Penny’s Bay Reclamation Stage 2
(PBR2);
§
Direct some incoming public fill dump
trucks to the Sorting Facility for Penny’s Bay Reclamation Stage 2 (PBR2) for
unloading;
§
Routine site cleaning and maintenance of
internal haul roads and access roads; and
§
Routine implementation of environmental
mitigation measures such as dust suppression by water spraying, cleaning of
nearby public roads by using road sweeper and collection of floating debris
inside a berthing basin within the site boundary; and
§
Landscaping works in the vicinity of the
main entrance of the Fill Bank at Tseung Kwan O Area 137 and in front of the
Engineer’s Site Office.
Environmental
Monitoring Progress
The summary of
the monitoring activities in this monitoring month is listed below:
·
Noise Monitoring (Day-time): 1 Occasion at 1 designated
location
·
24-hour TSP Monitoring: 6 Occasions at 2 designated
locations
·
1-hour TSP Monitoring: 18 Occasions at 2 designated
locations
·
Marine Water Quality Monitoring: 14 Occasions at 2
designated locations
·
Weekly-site inspection: 5 Occasions
Noise
Monitoring
No exceedances of
Action and Limit levels for noise monitoring were recorded in the reporting
month.
Air
Monitoring
No exceedances of Action and
Limit levels were recorded for 24-hr and 1-hr TSP monitoring in the reporting
month.
Marine
Water Quality Monitoring
According to the summary of marine water monitoring results, one
exceedance of Turbidity on Action Level at Monitoring Stations M4 was recorded
at 29 March 2006 (mid-ebb). According to the site
observation, no abnormal site activities were observed at the Fill Bank. As
there was no sediment plume observed from the Fill Bank and no wastewater
discharge was noted from the Fill Bank and the TKO Basin, the exceedance was
considered not due to the Fill Bank. The exceedance might be due to natural
fluctuation of Turbidity in the water body around the area. Hence, no further
actions were required.
Site
Inspection
Environmental site inspections conducted in this
reporting month are presented as follows:
Concerned Parties |
Dates of Audit /
Inspection |
ET Weekly site inspection |
02, 08, 14, 20, 30 |
IEC site inspection |
27 |
In general, performance on environmental
mitigation measures implemented was found to be satisfactory in this reporting
month. The major
findings observed during site inspections are presented in the Section 7.0.
Landscape and Visual
The germination rate
on the panel at Portion A, B, G, H and I was satisfactory in this reporting
month. The Contractor should properly maintain the panel properly.
Environmental
Complaints, Notification of summons and successful prosecutions
No
notification of summons and prosecutions with respect to environmental issues
were received in this monitoring month.
One complaint was received from Public through EPD on 27 March 2006,
concerning the dust and debris on Wan Po Road near TVB City Caused by dump
trucks from CEDD site. In the response to the complaint, ET undertook a site
investigation as stipulated in the EM&A manual. According to the site
investigation, it confirmed that mitigation measures such as providing the
wheel washing facilities, cleaning and watering the site regularly had been
implemented by the Contractor. No violation relating to the depositing of
debris and mud on haul road near the exit point and public road (e.g. Wan Po
Road) was observed from the Fill Bank vehicles during the site investigation. Hence, it was concluded that the complaint was not related to the
operation of Fill Bank and no further action was required to be implemented. At the same time,
it was believed that traffic other than Fill Bank (such as dump tracks from the
Construction Waste Sorting Facility) may have deposited the mud and debris onto
the road surface as they traveled on Wan Po Road. This was reported to have
been observed by the Contractor during an inspection of Wan Po Road after the
complaint was received. Although the complaint
was not related to the operation of Fill Bank, the Contractor was still
reminded to arrange road sweeper to carry out routine cleaning the haul road
and the public roads outside the Fill Bank including the section of Wan Po Road
nearby the TVB City. Ad-hoc additional cleaning may be required if necessary.
Since the investigation report was still being prepared at the end of the
reporting month, it will be submitted to relevant parties in the coming month.
Permits
and Licenses
An
Amended Environmental Permit (No.: EP-134/2002/F) (the EP) was granted to the
Project by EPD on 26 January 2006. Effluent discharge licence (Ref. No.:
TE/D1152/839/1) for the site toilet and shower room issued on 06 June 2003
obtained from the previous contract continued to be valid in this Project.
Chemical Waste Producer Licence (WPN No.: 5213-839-P2800-23) was also valid
from 04 August 2005.
Future
Key Issues
Based
on the site inspections and forecast of engineering works in the coming month,
key issues to be considered are as follows:
·
Noise and air quality impact due
to construction works;
·
Maintain wheel washing facilities
properly;
·
Maintain all drainage and desilting
facilities properly;
·
Use and maintain silt curtain properly;
·
Clean up the fill material on concrete
pavement along the BHA frequently;
·
Watering, hydroseeding or covering all
opening slopes and stockpiles with tarpaulin to avoid wind and water erosion;
·
Sufficient drip trays for all oil drums /
chemical containers;
·
Implement all necessary preventive
measures to avoid oil leakage. In the event an oil leakage happens, the
Contractor should properly remove the leaked oil and handle the contaminated
soil and all materials using for this cleaning works as chemical
waste;
·
Maintain good site practice and
waste management to minimize environmental impacts at the site; and
·
Follow-up improvements on waste management
issues.