EXECUTIVE SUMMARY

 

Introduction

 

This is the sixth monthly Environmental Monitoring and Audit (EM&A) report prepared by Maunsell Environmental Management Consultants Limited (MEMCL) for the “Temporary Construction Waste Sorting Facility at Tseung Kwan O Area 137” (the Project). This report documents the findings of EM&A Works conducted during the impact period in April 2006 for Tseung Kwan O Area 137.

 

As advised by the Contractor, the project commenced on 12 November 2005. The construction activities in April 2006 were:

 

l             Temporary access road construction including road kerb and U-channel;

l             Widening of temporary access road;

l             Installation of surveillance system and public address system;

l             Construction of Engineer’s site office and car parking area;

l             Operation of Construction Waste Sorting Facilities (CWSF) by manual sorting; and

l             Installation of water spraying system for dust suppression.

 

Environmental Monitoring Works

 

Air Quality

 

1-hr TSP Monitoring

 

All the monitoring data complied with the AL levels in the reporting month. The 1-hr TSP monitoring results remained at an acceptable level during the construction and operation of the temporary CWSF.

 

24-hr TSP Monitoring

 

There were two limit level exceedances recorded on 4 April 2006 at monitoring station TKO1 and TKO2. Exceedances recorded were considered related to the Project.

 

Complaints, Non-compliance and Prosecutions

 

No environmental complaints, non-compliances or prosecutions were received in the reporting month.

 

Permits and Licences

 

No new permit or license was obtained / applied in the reporting month. The Contractor was advised to apply for the effluent discharge license.

 

Environmental Site Inspection

 

There were 4 site inspections conducted in April 2006. Due to the wet weather condition, water ponding was occasionally observed at site office area in Area B1 and inside the trapezoidal channel. Fugitive dust was observed during transferring and dumping of materials. The Contractor had installed the sprinkler system at tipping hall by 27 April 2006, yet the water supply was still awaiting.

 

Construction waste inside the trapezoidal channel had been cleared by 13 April 2006. The Contractor was reminded to prevent any silty materials or waste entering to the channel. The wheel-washing bay at Area B2 was found mal-function, the Contractor was reminded to repair it as soon as possible.  

 

 

 

 

 

Future Key Issues

 

The weather is expected to be wet and windy in the forthcoming month and as such, the Contractor should provide preventive measures to prevent surface runoff, such as bunding around the site boundaries, to ensure functional temporary drainage system is in place around the site and to maintain sufficient dust suppression measures for vehicle movement along haul roads and during sorting activities. It is recommended to implement sufficient mitigation measures to eliminate dust emission from dump truck traffic and sorting activities.

 

It is also recommended to implement all necessary preventive measures to avoid oil leakage on ground/soil, such as provision of drip trays for all oil drums/chemical containers and placement of tarpaulin sheets on the ground during maintenance of equipment on site. In the event of any oil leakage problem, the Contractor should properly remove the leaked oil and handle the contaminated soil as chemical waste.