Interim Notifications of
Environmental Quality Limits Exceedances
Project |
Contract No. CV/2004/13 Construction
Waste Sorting Facilities at Tseung Kwan O Area 137
and Tuen Mun Area 38 |
Sampling Date |
4 April 2006 |
Time |
09:00 – 09:00 |
Monitoring Location |
TKO1 |
Parameter |
24-hr TSP |
Action / Limit Level |
260 / 260 µg/m3 |
Measured Level |
395.6 µg/m3 |
Major Construction Dust Source(s) During
Measurement |
·
Major dust source was fugitive
dust from vehicles movement along the haul road between Area A and Area B2; ·
Other dust source was from
dumping and sorting of waste inside the site. |
Observed Construction Activities from Other
Construction Site |
·
Vehicles movement and excavation
activities on the stockpile inside the adjacent CWSF. |
Possible reason for Action / Limit Level
Non-compliance |
·
Exceedance was considered mainly due to the dust emission from
vehicles movement along haul road and from dumping and sorting activities in
Area A. |
Actions taken / to be taken |
·
Fugitive dust was observed
during the site inspection on 6 April 2006 during dumping and sorting activities,
the Contractor was reminded to review the water dampening programme; ·
Water truck had been deployed 4 times for dampening the haul road, yet
frequency had to be increased; ·
ET continue to monitor the
24-hour TSP; ·
Additional monitoring had been
scheduled to 12 April 2006; ·
Results of the additional
monitoring for 24-hour TSP conducted to 6 April 2006 did not exceed the
established action/limit level. |
ET Advice |
·
Ensure all sorting activities
and dumping areas are sufficiently dampened; ·
Provide water sprinklers to haul
road, dumping areas and sorting area for water spraying; ·
Implement proper mitigation
measures inside the sorting facilities; ·
Ensure all the haul roads to be
sufficiently wet; ·
Advise the dump truck drivers to
travel on the dampened haul roads. |
Remarks |
·
Nil |
Interim Notifications of
Environmental Quality Limits Exceedances
Project |
Contract No. CV/2004/13 Construction
Waste Sorting Facilities at Tseung Kwan O Area 137
and Tuen Mun Area 38 |
Sampling Date |
4 April 2006 |
Time |
09:00 – 09:00 |
Monitoring Location |
TKO2 |
Parameter |
24-hr TSP |
Action / Limit Level |
260 / 260 µg/m3 |
Measured Level |
283.3µg/m3 |
Major Construction Dust Source(s) During
Measurement |
·
Vehicles movement inside the
CWSF. |
Observed Construction Activities from Other
Construction Site |
·
Vehicles movement inside the
Fill Bank. |
Possible reason for Action / Limit Level
Non-compliance |
·
Major dust
source was considered to be dust generated from dump truck travelled along
the unpaved road. |
Actions taken / to be taken |
·
Increase water spraying frequency at works area and the
all haul road, including the unpaved road used by dump truck from the
Project; ·
During the site inspection on 6 March 2006, the unpaved
haul road appeared dampened; ·
ET continue to monitor the
24-hour TSP to confirm finding; ·
Additional monitoring had been
scheduled to 12 April 2006. |
ET Advice |
·
Implement proper mitigation
measures inside the sorting facilities; ·
Ensure the area near the site
exit and all the haul roads to be sufficiently dampened; ·
Advise the dump truck drivers to
travel on the dampened haul roads. |
Remarks |
·
Nil |