EXECUTIVE SUMMARY

 

Introduction

 

This is the seventh monthly Environmental Monitoring and Audit (EM&A) report prepared by Maunsell Environmental Management Consultants Limited (MEMCL) for the “Temporary Construction Waste Sorting Facility at Tseung Kwan O Area 137” (the Project). This report documents the findings of EM&A Works conducted during the impact period in May 2006 for Tseung Kwan O Area 137.

 

As advised by the Contractor, the project commenced on 12 November 2005. The construction activities in May 2006 were:

 

l             Temporary access road construction including road kerb and U-channel;

l             Installation of steel fence along temporary access road;

l             Construction of car parking shelter at Engineer’s office;

l             Operation of Construction Waste Sorting Facilities (CWSF) by manual sorting;

l             Installation of water spraying system for dust suppression;

l             Forming end-tipping platform and access ramp for mechanical sorting plant; and

l             Erection of mechanical sorting plant.

 

Environmental Monitoring Works

 

Air Quality

 

1-hr TSP Monitoring

 

All the monitoring data complied with the AL levels in the reporting month. The 1-hr TSP monitoring results remained at an acceptable level during the construction and operation of the temporary CWSF.

 

24-hr TSP Monitoring

 

All the monitoring data complied with the AL levels in the reporting month. The 24-hr TSP monitoring results remained at an acceptable level during the construction and operation of the temporary CWSF.

 

Complaints, Non-compliance and Prosecutions

 

No environmental complaints, non-compliances or prosecutions were received in the reporting month.

 

Permits and Licences

 

No new permit or license was obtained / applied in the reporting month. The Contractor was advised to apply for the effluent discharge license.

 

Environmental Site Inspection

 

There were 4 site inspections conducted in May 2006. Due to the wet weather condition, water ponding was occasionally observed at Area A and inside the tipping hall. Fugitive dust was occasionally observed during transferring and dumping of materials. The Contractor had installed the sprinkler system at tipping hall by 27 April 2006, yet the water supply was still awaiting.

 

The Contractor was reminded to prevent any silty materials or waste entering to the channel by providing bundings along the trapezoidal channel. The Contractor was also reminded to clear the accumulated silt inside the perimeter channel in Area B2, particularly after heavy rainfall. 

 

 

Future Key Issues

 

The weather is expected to be wet and windy in the forthcoming month and as such, the Contractor should provide preventive measures to prevent surface runoff, such as bunding around the site boundaries, to ensure functional temporary drainage system is in place around the site and to maintain sufficient dust suppression measures for vehicle movement along haul roads and during sorting activities. It is recommended to implement sufficient mitigation measures to eliminate dust emission from dump truck traffic and sorting activities.

 

It is also recommended to implement all necessary preventive measures to avoid oil leakage on ground/soil, such as provision of drip trays for all oil drums/chemical containers and placement of tarpaulin sheets on the ground during maintenance of equipment on site. In the event of any oil leakage problem, the Contractor should properly remove the leaked oil and handle the contaminated soil as chemical waste.