3.         MONITORING RESULTS

 

Air Quality

 

3.1               Air quality monitoring, including 1-hr and 24-hr TSP, was conducted three times a week and once a week respectively, in accordance with the EM&A Manual.

 

3.2               The weather was generally dry and windy from February 2007 to March 2007 and gradually become wet in April 2007. The monitoring data and trend of air quality for the reporting quarter are given in Appendix E. Major dust sources of the temporary CWSF were dump truck traffic, dumping and sorting activities inside the CWSF. Other dust sources were the dump truck traffic inside and outside of the Fill Bank and the dumping activities inside the adjacent CWSF.

 

3.3               There were two limit level exceedances of 24-hr TSP recorded in the reporting quarter. One additional monitoring was conducted in the reporting quarter. All exceedances were considered related to the Project.

 

3.4               Table 3.1 presents the number of exceedances recorded in each month of the reporting quarter. The number of monitoring events included regular monitoring events and additional ones, if any.

 

Table 3.1    Summary of Number of Exceedances for 1-hr & 24-hr TSP Concentration

Monitoring Parameter

Level of Exceedance

Month

Feb 07

Mar 07

Apr 07

1-hr TSP

No. of monitoring events

15

12

12

Action

0

0

0

Limit

0

0

0

Total

0

0

0

24-hr TSP

No. of monitoring events

5

4

6

Action

0

0

0

Limit

1

0

1

Total

1

0

1

 

Environmental Site Inspection

 

3.5               There were 13 site inspections conducted in the reporting quarter to monitor the implementation of proper environmental pollution control and mitigation measures for the Project. The major concerns for the Project are air quality and waste management on site. Dust emission along haul roads and during earth movement was observed during site inspections, while general refuse and chemicals were observed without proper collection.

 

3.6               The implementation status of environmental mitigation measures are given in Appendix D.

 

3.7               Major dust sources in the temporary CWSF would be the manual sorting of non-inert waste, dumping activities and dump truck traffic inside the CWSF. Although mitigation measures, including dampening of haul roads and operation of wheel-washing facilities, had been implemented, the Contractor was still advised to provide sufficient water spraying during manual sorting of non-inert waste at Area A.

 

3.8               Besides the afore-said issues, the Contractor was reminded to maintain the drainage systems regularly. It was recommended to arrange additional maintenance for the silt trap at the wheel washing bay and oil interceptor pump pit before and after rainstorms so as to ensure their maximum treatment capacities.

 

3.9               The Contractor had obtained the effluent discharge license on 13 November 2006.

 

 

 

Advice on Solid and Liquid Waste Management Status

 

3.10            There was disposal of inert C&D materials and C&D waste in the reporting quarter.

 

3.11            The Contractor was advised to provide drip trays to all chemicals containers and implement sufficient preventive measures, including placing tarpaulin sheets or drip tray on ground, during equipment maintenance works to avoid oil leakage on the ground. In the event of oil leakage, the Contractor should clean up the polluted soil and dispose of as chemical waste.