EXECUTIVE SUMMARY

 

Introduction

 

This is the nineteenth monthly Environmental Monitoring and Audit (EM&A) report prepared by Maunsell Environmental Management Consultants Limited (MEMCL), which changed the name to ENSR Asia (HK) Ltd. (ENSR) on 1 May 2007 for the “Temporary Construction Waste Sorting Facility at Tseung Kwan O Area 137” (the Project). This report documents the findings of EM&A Works conducted during the impact period in May 2007 for Tseung Kwan O Area 137.

 

As advised by the Contractor, the project commenced on 12 November 2005. The construction activities in May 2007 were:

 

l             Operation of Construction Waste Sorting Facilities (CWSF) by mechanical sorting plant;

l             Enhanced dust suppression system at Portion A; and

l             Safety barrier at VGF end-tipping platform.

 

Environmental Monitoring Works

 

Air Quality

 

1-hr TSP Monitoring

 

All the monitoring data complied with the AL levels in the reporting month. The 1-hr TSP monitoring results remained at an acceptable level during the construction and operation of the temporary CWSF.

 

24-hr TSP Monitoring

 

One limit level exceedance was recorded in May 2007. The exceedance was concluded partially due to the Project. One additional monitoring was carried out on 16 May 2007 and the result did not exceed the action / limit level.

 

Complaints, Non-compliance and Prosecutions

 

No environmental complaint, non-compliances or prosecutions were received in the reporting month.

 

Permits and Licences

 

No new permit or license was obtained in the reporting month.

 

Environmental Site Inspection

 

There were 5 site inspections conducted in May 2007. Due to the occasion dry weather conditions, fugitive dust was occasionally observed during transferring and dumping of materials in Area A and along the haul road during dry weather.

 

The Contractor was reminded to prevent any silty materials or waste from entering the trapezoidal channel by providing bunding along the banks of the channel. The Contractor was also reminded to properly store the chemicals on site to prevent spillage.

 

 

Future Key Issues

 

The weather is expected to be wet and windy in the forthcoming month and as such, the Contractor should provide preventive measures to prevent surface runoff, such as bunding around the site boundaries, to ensure that a functional temporary drainage system is in place around the site. The Contractor should also maintain sufficient dust suppression measures for vehicle movement along haul roads and during sorting activities. It is recommended to implement sufficient mitigation measures to eliminate dust generation from dumping and sorting activities.

 

It is also recommended to implement all necessary preventive measures to avoid oil leakage on ground/soil, such as provision of drip trays for all oil drums/chemical containers and placement of tarpaulin sheets on the ground during maintenance of equipment on site. In the event of any oil leakage problem, the Contractor should properly remove the leaked oil and handle the contaminated soil as chemical waste.