Site
Inspection Summary
Date: |
2 August 2007 |
Time: |
14:30 |
Site: |
Tseung Kwan O Area 137 |
Inspection No.: |
172 |
|
Nil |
|
|
|
Follow
up Observations |
|
|
1. |
Most of
the mud in the trapezoidal channel in Area A had been cleared. The Contractor
was still reminded to clear the remaining mud inside the trapezoidal channel
under the access bridge next to the Engineer’s Site Office. |
|
|
2. |
Minor
fugitive dust was observed during dumping and manual sorting of non-inert
waste in Area A and during vehicle movement along the haul road. The
Contractor was reminded to increase water spraying frequency by water truck
or provide more water sprinklers for dust suppression. |
|
|
3. |
No dark smoke was emitted from
the excavator (C3) at Area A. (Closed) |
|
|
4. |
The
removal of deposited mud and refuse inside the catchpit and u-channel in Area
B2 was in progress. The Contractor was reminded to clear the remaining mud
inside the catchpit and u-channel to avoid blockage. 444 |
|
|
|
New
Observations |
|
|
5. |
General
refuse was found accumulated near the site exit at Area B1. The Contractor
was advised to clear the refuse. |
|
|
6. |
General
refuse was found inside the desilting pits and u-channel next to the
trapezoidal channel at Area A. The Contractor was advised to clear the refuse
and maintain the drainage system properly. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Nil. |
Site
Inspection Summary
Date: |
8 August 2007 |
Time: |
14:30 |
Site: |
Tseung Kwan O Area 137 |
Inspection No.: |
174 |
|
Nil |
|
|
|
Follow
up Observations |
|
|
1. |
Minor
fugitive dust was observed during dumping and manual sorting of non-inert
waste in Area A and during vehicle movement along the haul road in Area A.
The Contractor was reminded to increase water spraying frequency by water
truck or provide more water sprinklers for dust suppression. |
|
|
2. |
The
removal of general refuse near the site exit in Area B1 was in progress. The
Contractor was still reminded to clear the refuse to avoid accumulation. |
|
|
3. |
Deposited
mud and general refuse inside catchpit and u-channel in Area B2 had been
cleared. (Closed) |
4. |
General refuse inside the
desilting pits and u-channel next to the trapezoidal channel at Area A had
been cleared. (Closed) |
5. |
Stagnant water and deposited mud
was found inside the trapezoidal channel in Area A. The Contractor was
reminded to clear the stagnant water and deposited mud. |
|
New
Observations |
|
|
6. |
Dark
smoke was observed emitted from a bulldozer at Area A. The Contractor was
reminded to properly maintain the plant on site. |
|
|
7. |
Mud was
found deposited on part of the access road in Area B2. The Contractor was
reminded to clear the deposited mud along the access road frequently during
wet season. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1. |
Typhoon signal No.1 was hoisted during
the site inspection. |
Site
Inspection Summary
Date: |
16 August 2007 |
Time: |
14:30 |
Site: |
Tseung Kwan O Area 137 |
Inspection No.: |
176 |
|
Nil |
|
|
|
Follow-up
Observations |
|
|
1. |
No
fugitive dust was observed during dumping and manual sorting of non-inert
waste and during vehicle movement along the haul road in Area A due to heavy
rainfall during the inspection. (Closed) |
|
|
2. |
No dark
smoke was emitted from the bulldozer at Area A. (Closed) |
|
|
3. |
The
removal of general refuse near the site exit in Area B1 was in progress. The
Contractor was still reminded to clear the refuse to avoid accumulation. |
4. |
Deposited mud was left inside the
trapezoidal channel under the access bridge next to CEDD’s site office in
Area A. Waterflow was observed and no stagnant water was observed inside the
trapezoidal channel in Area A due to heavy rainfall during the inspection.
The Contractor was still reminded to clear the deposited mud. |
5. |
Mud was found deposited on part of
the access road in Area B2. The Contractor was still reminded to clear the
deposited mud along the access road frequently during the wet season. |
|
New
Observations |
|
|
6. |
Oil
stain was found on ground in Area B1. The Contractor was reminded to clear
the oil stain and contaminated soil/ aggregates and dispose of as chemical
waste. |
|
|
7. |
General
refuse was found inside the u-channel in Area B2 and Area A. The Contractor
was advised to clear the refuse. |
|
|
8. |
Muddy
water was observed discharged directly into the trapezoidal channel from the
opening under the access bridge next to CEDD’s site office. The Contractor
was requested to provide bunding along the trapezoidal channel to divert the muddy
water to the desilting facilities prior to discharge. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Nil. |
Site
Inspection Summary
Date: |
23 August 2007 |
Time: |
14:30 |
Site: |
Tseung Kwan O Area 137 |
Inspection No.: |
178 |
|
Nil |
|
|
|
Follow-up
Observations |
|
|
1. |
The
bunding along the trapezoidal channel next to CEDD’s site office was provided
to divert the muddy water to the desilting facilities prior to discharge.
(Closed) |
|
|
2. |
The oil
stain on ground in Area B1 was cleared. (Closed) |
|
|
3. |
The
removal of general refuse near the site exit in Area B1 was in progress. The
Contractor was reminded to clear the refuse to avoid accumulation. |
|
|
4. |
The removal of general refuse
inside the u-channel in Area B2 was in progress. The Contractor was reminded
to clear the refuse to avoid accumulation. |
|
|
5. |
The
removal of deposited mud on part of the access road in Area B2 was in
progress. The Contractor was reminded to clear the deposited mud along the
access road frequently during the wet season. |
6. |
Deposited mud was still left
inside the trapezoidal channel under the access bridge next to CEDD’s site
office in Area A. The Contractor was reminded to clear the deposited mud. |
|
New
Observations |
|
|
7. |
General
refuse was found inside the catchpit in Area B2. The Contractor was advised
to clear the refuse. |
|
|
8. |
Stagnant
water and general refuse was found inside the trapezoidal channel in Area A.
The Contractor was reminded to clear the stagnant water and the refuse. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Nil. |
Site
Inspection Summary
Date: |
30 August 2007 |
Time: |
14:30 |
Site: |
Tseung Kwan O Area 137 |
Inspection No.: |
180 |
|
Nil |
|
|
|
Follow-up
Observations |
|
|
1. |
The general
refuse inside the catchpit in Area B2 was cleared. (Closed) |
|
|
2. |
The
removal of general refuse near the site exit in Area B1 was in progress. The
Contractor was reminded to clear the refuse to avoid accumulation. |
|
|
3. |
The
removal of general refuse inside the u-channel in Area B2 was in progress.
The Contractor was reminded to clear the refuse to avoid accumulation. |
|
|
4. |
The removal of deposited mud on
part of the access road in Area B2 was in progress. The Contractor was
reminded to clear the deposited mud along the access road frequently during
the wet season. |
|
|
5. |
Deposited
mud was still left inside the trapezoidal channel under the access bridge
next to CEDD’s site office in Area A. The Contractor was reminded to clear
the deposited mud. |
6. |
Stagnant water and general refuse
was still found inside the trapezoidal channel in Area A. The Contractor was
reminded to clear the stagnant water and the refuse. |
|
New
Observations |
|
|
7. |
Deposited
mud was found inside the desilting pit in Area A. The Contractor was reminded
to clear the deposited mud. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Nil |
|