Environmental Mitigation Implementation Schedule
Environmental Protection Measures |
Location |
Implementation Status |
|||
May 07 |
Jun 07 |
Jul 07 |
Aug 07 |
||
Air Quality |
|||||
Sufficient watering |
Tipping hall (barging point), stockpiled materials, access
road, All unpaved haul roads, exposed site areas |
@ |
Ö |
@ |
@ |
Truck speed below |
All areas |
Ö |
Ö |
Ö |
Ö |
Trucks fitted with power-operated dump bed cover |
All areas |
Ö |
Ö |
Ö |
Ö |
Watering for truck loads after removal of tarpaulin cover |
Site egress |
Ö |
Ö |
Ö |
Ö |
Provision of vehicle washing facilities |
Site egress |
Ö |
Ö |
Ö |
Ö |
Prohibition of open burning |
All areas |
Ö |
Ö |
Ö |
Ö |
Provision of top and side covers for conveyor belts |
C&DMSF |
Ö |
Ö |
Ö |
Ö |
Buffer
zone of at least |
Seafront |
Ö |
Ö |
Ö |
Ö |
Buffer
zone of at least |
Northern
site boundary |
Ö |
Ö |
Ö |
Ö |
Noise |
|||||
Noisy equipment and activities should be sited by the
Contractor as far away from sensitive receivers as is practical |
All areas |
Ö |
Ö |
Ö |
Ö |
Replace noisy plant with quieter alternatives |
All areas |
Ö |
Ö |
Ö |
Ö |
Idle equipment should be turned off or throttled down |
All areas |
Ö |
Ö |
Ö |
Ö |
Quieter power units of stationary and earth moving plant
with partial or full enclosures or vibratory isolation |
All areas |
Ö |
Ö |
Ö |
Ö |
Properly maintain powered mechanical equipment |
All areas |
Ö |
Ö |
Ö |
Ö |
Schedule noisy activities to reduce duration and severity
of noise |
All areas |
Ö |
Ö |
Ö |
Ö |
Include contract clauses for environmental protection |
All areas |
Ö |
Ö |
Ö |
Ö |
Water Quality |
|||||
Obtain discharge license |
Site offices |
Ö |
Ö |
Ö |
Ö |
Provide proper sewage treatment and disposal facilities in
the form of chemical toilets for site workers |
All areas |
Ö |
Ö |
Ö |
Ö |
Include contract specifications for environmental
protection |
All areas |
Ö |
Ö |
Ö |
Ö |
Provide proper drainage for collection of surface runoff |
All areas |
Ö |
Ö |
Ö |
@ |
Provision of buffer distance of at least |
C&DMSF |
Ö |
Ö |
Ö |
Ö |
Provision of sand & silt settling tank |
Vehicle washing facility |
Ö |
Ö |
Ö |
@ |
Sand and silt removal facility provided for stormwater to
be treated before discharge |
All areas |
Ö |
Ö |
Ö |
@ |
Construction of temporary storm water system |
Perimeter of Fill Bank |
Ö |
Ö |
Ö |
Ö |
Regular removal of sand and silt |
All channels |
@ |
@ |
@ |
@ |
Construction Waste |
|||||
Segregate different categories of waste |
All areas |
Ö |
Ö |
Ö |
Ö |
Register chemical and maintenance wastes |
All areas |
Ö |
Ö |
Ö |
Ö |
Do not connect chemical material storage areas to the foul
or stormwater drainage system |
Works yards |
Ö |
Ö |
Ö |
Ö |
Store and label dangerous goods |
All areas |
Ö |
Ö |
Ö |
Ö |
Prevent disposal of hazardous materials to air, soil,
water bodies |
All areas |
Ö |
@ |
Ö |
@ |
Provide refuse containers at all work areas |
All areas |
Ö |
Ö |
Ö |
Ö |
Human waste discharged into septic tanks or tankered away |
All areas |
Ö |
Ö |
Ö |
Ö |
Landscape and Visual |
|||||
Is the night-time lighting controlled to minimize glare to
sensitive receivers |
All areas |
Ö |
Ö |
Ö |
Ö |
Is hydroseeding process conducted and maintained properly |
All areas |
N/A |
N/A |
N/A |
N/A |